To report abuse of any content on this site, please fill in the form. Please give a brief description of the rule being broken.

spacer
Welcome to PCO Forums

A place to share your ideas, knowledge, feelings and advice on a wide variety of topics having special interest to Project Controls practitioners. Please refer to Forum Rules and Guidelines for usage.

Please note user must be logged in to post or edit forum threads.

spacer
 
 
ForumForumProject Control...Project Control...Project/Constru...Project/Constru...Information required scheduleInformation required schedule
Previous Previous
 
Next
 Disabled
New Post
 3/8/2011 10:14 AM
 
Hi,

What is an "Information required schedule" produced by the contrators site agent; which is required by the design team at the pre contract meeting.what does it contain and what format should it be in.
Any one got an example?

Thanks.....
New Post
 11/22/2011 1:56 PM
 
I think it's a level 1 schedule with intermediate milestones and key interfaces clearly identified. Will be glad to know others opinion.
Previous Previous
 
Next
 Disabled
ForumForumProject Control...Project Control...Project/Constru...Project/Constru...Information required scheduleInformation required schedule

spacer