progress updating and reporting - P6

  • Page:
  • 1

progress updating and reporting - P6

OFFLINE

progress updating and reporting - P6

20 April 2010 7:24
i am a beginner in planning, kindly please tell me the proper way of updating and progress reporting in primavera 6.. right now, i dont have any problems in creating schedules, the problem is on resources, progress reporting and updating. Please help me master planners, ull help will highly be appreciated.
OFFLINE
Joined On:
30 Sep 2017

Re: progress updating and reporting - P6

20 April 2010 7:26
There are plenty of ways to update the project. The simpliest method is by using percent complete type = duration. But, take note to check "Recalculate Actual Units and Cost when duration % complete changes" on calculation tab. This way, the % complete of units together with the duration %. The "Duration Type" & "Earned value calculation" affects on how P6 calculate the progress. You can now use "Labor Units % Complete" in your reporting. Before you understand this things, you must fully understand what is "Actual" & what is "Earned Value". Read the Help file as well.
  • Page:
  • 1