Actual Cost loading in Primavera R 8.3.2 with different rates

OFFLINE
Joined On:
30 Sep 2017

Actual Cost loading in Primavera R 8.3.2 with different rates

8 January 2015 7:21
Dear Members I am using Primavera R8.3.2 standalone version.I have uploaded the resources in my schedule with their respective rates. For some of the activities , the actual rates of the resources have changed than what was planned. For example: rate/cum of concrete was planned to be $200. Now the actual rate of the concrete is coming to be $210 per cum. The total quantity of the material is same during planned and actual case. Please advice how to show the actual rate of the resource in this case to get the actual cost. Many thanks and regards Sarbajit