How to Compare Weekly Lookahead Schedules and Report Variances!!

OFFLINE
Joined On:
30 Sep 2017

How to Compare Weekly Lookahead Schedules and Report Variances!!

24 March 2010 1:22
When I create a copy of my current schedule in P6 and save it as target schedule, next week, when I update the schedule and compare their finish dates with last week, the activities that have started, show different finish dates and different variances than what I should expect. My column titles are Start, Finish, BL1 Start, BL1 Finish, Variance BL1 Finish. Any suggestions??
The following user(s) said Thank You: Brenda Spurlock
OFFLINE
Joined On:
30 Sep 2017

Re: How to Compare Weekly Lookahead Schedules and Report Variances!!

24 March 2010 1:24
The only solution to this problem is custom data items and global change. Unfortunately the issue remains with P6 . The Solution: 1 - Create custom data fields for last weeks dates 2 - Move last weeks dates in those fields using global change 3 - Update the schedule 4 - calculate the variance using a global change There is also another solution for this if you know .asp or .cfm or .net web applications. You can create a web page that looks at each database and easily calculates this, so you dont even have to worry about anything AT ALL
The following user(s) said Thank You: BradleyLewington