CFI/GFI links

OFFLINE
Joined On:
30 Sep 2017

CFI/GFI links

24 June 2013 6:01
Good afternoon all, Just wondered what best practice is for CFI/GFI (Customer/Government Furnished Information) - customer provided information required to perform certain activities? At the moment Im linking the CFI into the relevant task that needs it as a successor and putting a constraint on it so that it is held in place X days before the baseline start date of the task,, this would have to change with each schedule status.... It was suggested to me that using As Late As Possible constraints are better because then the date would change as the schedule moves around but sometimes artificially drives the successor task date miles to the right. What is the best practice? Thanks, MrG