Delay Analysis Tools & Technique

OFFLINE

Delay Analysis Tools & Technique

2 September 2010 5:42
I am interested in learning the standard way of doing Delay analysis using a Schedule for claim purpose or time extension. is there any template/ checklist that can be use for the said purpose
OFFLINE

Re: Delay Analysis Tools & Technique

2 September 2010 5:47
Try downloading the Forensic Schedule Analysis Recommended Practice from the AACEi website, no charge. This provides the framework for schedule analysis done in a claims situation (after the impact event has actualized or the risk is no longer shared). Download the Change Management Time Impact Analysis Recommended Practice from the same site for a great explanation of how to do time extension requests.