Acceleration
AACEi :
Conduct by the owner or its agent (either in a directed or constructive manner) in which a contractor is required to complete performance of a contracted scope of work earlier than scheduled. A directed acceleration occurs when the owner formally directs such acceleration completion. A constructive acceleration generally occurs when a contractor is entitled to an excusable delay; the contractor requests a time extension from the owner; the owner declines to grant a time extension or grants one in an untimely manner; the owner or its agent either expressly orders completion within the original performance period or implies in a clear manner that timely completion within the original performance period is expected; and the contractor gives notice to the owner or its agent that the contractor considers this action an acceleration order.
Accept/Acceptance
AACEi :
(1) The formal process of accepting delivery of a product or a deliverable.
(2) The act of taking custody based on satisfactory verification.
(3) The act of an authorized representative, for itself or as agent for another, assumes ownership of existing identified supplies tendered or approves specific services rendered as partial or complete performance of the contract.
(4) In TCM risk management, a response strategy for both threats and opportunities.
APM :
A response to a threat where no course of action is taken.
PCI :
(1) The formal process of accepting delivery of a product or a deliverable.
(2) The act of taking custody based on satisfactory verification.
(3) The act of an authorized representative, for itself or as agent for another, assumes ownership of existing identified supplies tendered or approves specific services rendered as partial or complete performance of the contract.
(4) In TCM risk management, a response strategy for both threats and opportunities.
Acceptance Criteria
AACEi :
Implicit or explicit specifications that must be achieved for a product or service to be acceptable within the terms of the contract or agreement seeking its delivery.
APM :
The requirements and essential conditions that have to be achieved before a deliverable is accepted.
PMI :
A set of conditions that is required to be met before deliverables are accepted.
Acceptance Deliverables
PMI :
Products, results, or capabilities produced by a project and validated by the project customer or sponsors as meeting their specified acceptance criteria.
Acceptance, Final (Partial)
AACEi :
The formal action by the owner accepting the work (or a specified part thereof), following written notice from the engineer that the work (or specified part thereof) has been completed and is acceptable subject to the provisions of the contract regarding acceptance.
Accepted Risk
AACEi :
Risks that are identified, but for which no other risk response is taken in the risk treatment process (e.g., avoid, reduce, transfer).
Access To The Work
AACEi :
The right of the contractor to ingress and egress, and to occupy the work site as required to reasonably perform the work described in the contract documents. An example of denial of access to the work would be on the segment of a sewer installation project where no easements or work limits are indicated, but the contractor is ordered, after contract award, to conduct operations within a narrow work corridor necessitating different or unanticipated construction methods (e.g., use of sheeting).
Account Code Structure
AACEi :
System used to assign summary numbers to elements of the work breakdown and account numbers to individual work packages.
Account Number
AACEi :
An alphanumeric identification of a work package. An account number may be assigned to one or more activities. Syn.: Shop Order Number.
Accountability
AACEi :
Answerable, but not necessarily charged personally with doing the work. Accountability cannot be delegated but it can be shared.
Accounting
APM :
The process of collecting and communicating financial information to meet legal requirements, business management requirements, plus internal and external stakeholders’ needs.
Accounts Payable
AACEi :
The value of goods and services rendered on which payment has not yet been made.
Accounts Receivable
AACEi :
The value of goods shipped or services rendered to a customer on which payment has not yet been received. Usually includes an allowance for bad debts.
Accrual
AACEi :
In earned value management, the actual costs that are recorded for goods and/or material received or services rendered before payment. For example, subcontractor service for a safety inspection for a specific piece of equipment in the month of January which was validated as completed may be recorded by accrual based on an estimated cost. However, the accruals originally recorded in January for the cost of this activity are adjusted after a final cost is determined.
Accuracy
PMI :
Within the quality management system, accuracy is an assessment of correctness.
Accuracy Range
AACEi :
An expression of an estimate’s predicted closeness to final actual costs or time. Typically expressed as high/low percentages by which actual results will be over and under the estimate along with the confidence interval these percentages represent. Syn.: Range of Accuracy.
Acquire Project Team
PMI :
The process of confirming human resource availability and obtaining the team necessary to complete project activities.
Acquisition
PMI :
Obtaining human and material resources necessary to perform project activities. Acquisition implies a cost of resources, and is not necessarily financial.
Action
AACEi :
A measure taken or implemented that is intended to influence the course of the project.
Action Item
AACEi :
Something agreed to be done as a meeting outcome and usually recorded in meeting minutes.
Action Owner
AACEi :
In TCM risk management, the party charged with implementing a risk response.
Action Plan
AACEi :
A plan that describes what needs to be done and by when. Project plans are action plans.
Activity
AACEi :
An operation or process consuming time and possibly resources (with the exception of dummy activities). An activity is an element of work that must be performed in order to complete a project. An activity consumes time, and may have resources associated with it. Activities must be measurable and controllable. An activity may include one or more tasks.
APM :
1. A task, job, operation or process consuming time and possibly other resources.
2. The smallest self-contained unit of work in a project.
PMI :
A distinct, scheduled portion of work performed during the course of a project.
PCI :
The smallest self-contained unit of work used to define the logic of a project. In general, activities share the following characteristics: a definite duration, logic relationships to other activities in a project, use resources such as people, materials or facilities, and have an associated cost.
Activity Attributes
AACEi :
Schedule-related characteristics and designations that uniquely describe a network activity. Attributes can include early and late start and finish dates; identification codes; resource assignments; predecessor and successor activities; and any other information that places the activity into accurate context of its place in the activity network.
PMI :
Multiple attributes associated with each schedule activity that can be included within the activity list. Activity attributes include activity codes, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, and assumptions.
Activity Bar
AACEi :
A rectangle representing an activity on the bar chart. Its length is scaled according to the time scale.
Activity Calendar
AACEi :
In computer scheduling, calendar that defines the working and non-working patterns applicable to an activity. The activity calendar is normally overridden by the project calendar.
Activity Code
AACEi :
Alphanumeric designation system, with code(s) assigned to an activity to group or categorize its properties. Coding is used for detail and summary reporting purposes.
PMI :
One or more numerical or text values that identify characteristics of the work or in some way categorize the schedule activity that allows filtering and ordering of activities within reports.
Activity Cost
AACEi :
The monetary amount expended to complete an activity. Depending upon the cost model and job cost system used, Activity cost may or may not include indirect costs (jobsite and home office) as well as direct costs.
PMI :
Activity Cost Estimate: The projected cost of the schedule activity that includes the cost for all resources required to perform and complete the activity, including all cost types and cost components.
Activity Definition
AACEi :
Process of identifying specific activities that must be performed to produce project deliverables.
PMI :
Define Activity: The process of identifying and documenting the specific actions to be performed to produce the project deliverables.
Activity Description
AACEi :
A unique activity name and word description, which generally defines the work to be accomplished which easily identifies an activity to any recipient of the schedule.
Activity Duration
AACEi :
(1) Length of time from start to finish of an activity, estimated or actual, in working or calendar time units.
(2) Best estimate of continuous time (hours, days, weeks, and months) needed to complete the work involved in an activity. This takes into consideration the nature of the work, and the resources needed to complete the task. Baseline activity duration development can become very complex when productivity impacts and nonstandard production rates must be utilized to meet the constraints of the project.
APM :
The length of time that it takes to complete an activity.
PMI :
The time in calendar units between the start and finish of a schedule activity.
PCI :
Activity duration specifies the length of time (hours, days, weeks, months) that it takes to complete an activity. This information is optional in the data entry of an activity. Work flow (predecessor relationships) can be defined before durations are assigned. Activities with zero durations are considered milestones (milestone value of 1 to 94) or hammocks (milestone value of 95 to 99).
Activity Duration Estimating
AACEi :
Estimation of the number of work periods that will be needed to complete the activity.
PMI :
A quantitative assessment of the likely amount or outcome for the duration of an activity.
Activity File
PCI :
A file containing all data related to the definition of activities on a particular project.
Activity Identifier
AACEi :
Syn.: Activity Code; Activity Number.
PMI :
A short, unique numeric or text identification assigned to each schedule activity to differentiate that project activity from other activities. Typically unique within any one project schedule network diagram.
PCI :
Activity Id: A unique code identifying each activity in a project.
Activity List
AACEi :
A table of scheduled activities listing their respective descriptions, unique identification codes, sufficiently detailed scopes, and predecessor and successor activities, so that the project team can readily discern the work of each activity and the project as a whole.
PMI :
A documented tabulation of schedule activities that shows the activity description, activity identifier, and a sufficiently detailed scope of work description so project team members understand what work is to be performed.
Activity Network Diagram
PMI :
Project schedule network diagram: A graphical representation of the logical relationships among the project schedule activities.
Activity Number
AACEi :
Syn.: Activity Code; Activity Identifier.
Activity On Arrow (AOA)
AACEi :
An activity network format. Schedule activities are represented by arrows and nodes are represented by circles. AOA networks require the use of “dummy” activities to properly model work flow.
Activity On Node (AON)
AACEi :
An activity network format. Schedule activities are represented by boxes or bars and relationships are represented by arrows. Pure AON networks rely solely on finish-to-start relationships and do not employ the use of activity lags to model work flow.
APM :
A network diagram where the activities are represented by the nodes.
PCI :
A network where activities are represented by a box or a node linked by dependencies.
Activity Relationship
AACEi :
Activity relationships determine how activities relate to one another and establish schedule logic.
Activity Resource Requirement
PMI :
The types and quantities of resources required for each activity in a work package.
Activity Sequencing
AACEi :
The process of identifying and documenting dependencies among schedule activities.
Activity Status
AACEi :
Information about the performance of an activity that is used to update schedule progress. Typical status information includes actual start and finish dates, percent complete, and remaining duration. This is information used to update the critical path method calculations periodically.
PCI :
The state of completion of an activity. A planned activity has not yet started. A started activity is in progress. A finished activity is complete.
Activity Times
AACEi :
Time information generated through the critical path method calculation that identifies the start and finish times for each activity in the network.
Activity Total Slack
AACEi :
The latest allowable end time minus earliest allowable end time. The activity slack is always greater than or equal to the slack of the activity ending event.
Activity Type
AACEi :
Dictates calendar used in scheduling software for schedule calculations. Typical activity types are: independent, task, hammock, WBS, and milestone.
Acts Of God
AACEi :
(1) An extraordinary interruption by a natural cause, as a flood or earthquake, or the usual course of events that experience, foresight or care cannot reasonably foresee or prevent.
(2) An event in nature over which neither the owner nor the contractor has any control.
Actual And Scheduled Progress
AACEi :
A comparison of the observable work done at a given time with the work planned up to that time.
APM :
Actual Progress: A measure of the work that has been completed for comparison with the baseline.
Actual Completion Date
AACEi :
The calendar date on which an activity was completed.
Actual Cost (AC)
AACEi :
Syn.: Actual Cost Of Work Performed.(ACWP).
PMI :
The realized cost incurred for the work performed on an activity during a specific time period.
PCI :
The cost actually incurred.
Actual Cost Of Work Performed (ACWP)
AACEi :
(1) The actual expenditures incurred by a program or project.
(2) The direct costs actually incurred and the direct costs actually recorded and assigned in accomplishing the work performed. These costs should reconcile with the contractor's incurred cost ledgers when they are audited by the client.
(3) In earned value management, a measure of the actual cost of the work performed as of a data date.
APM :
The costs that have been charged to the budget and for which payment has been made, or accrued.
PCI :
The actual cost derived from the employed accounting system. Also called ACWP. The sum of costs actually incurred in accomplishing the work performed.
Actual Dates
PCI :
Actual dates are entered as the project progresses. These are the dates that activities really started and finished as opposed to planned or projected dates.
Actual Direct Cost
PCI :
Those costs specifically identified with a contract or project, based upon the contractor’s cost identification and accumulation system.
Actual Finish Date
AACEi :
Date when work on an activity is substantially complete. Activity substantial completion is when only minor or remedial work remains and successor activities may proceed without hindrance from the predecessor’s remaining work. It is not necessarily the last day work will be performed on that activity. The remaining duration of this activity is zero.
PCI :
Date on which an activity was completed.
Actual Start Date
AACEi :
Date when work on an activity actually started with intention of completing activity within the planned duration. The actual start date is not necessarily the first date work was performed on that activity. Interim starts and stops for an activity may show the need for splitting the activity into component parts.
PCI :
Date on which an activity was started.
Actual Time (AT)
AACEi :
The number of whole project time increments from project inception through time now (data date).
Actual [Duration, Start, Finish, Logic, Etc.]
AACEi :
Schedule information that shows what has actually occurred. For example, the actual start date for a task is the day on which the task actually started, and its actual cost is the expenditures incurred spent up to the present
PMI :
Actual Duration: The time in calendar units between the actual start date of the schedule activity and either the data date of the project schedule if the schedule activity is in progress or the actual finish date if the schedule activity is complete.
Addaptive Life Cycle
PMI :
A project life cycle, also known as change-driven or agile methods, that is intended to facilitate change and require a high degree of ongoing stakeholder involvement. Adaptive life cycles are also iterative and incremental, but differ in that iterations are very rapid (usually 2–4 weeks in length) and are fixed in time and resources.
Addenda
AACEi :
Written or graphic instruments issued prior to the date for opening of bids which may interpret or modify the bidding documents by additions, deletions, clarification, or corrections.
Additional Quality Planning
PMI :
A set of tools used to define the quality requirements and to plan effective quality management activities. They include, but are not limited to: brainstorming, force field analysis, nominal group techniques and quality management and control tools.
Adjusted Internal Rate-Of-Return (AIRR)
AACEi :
The compound rate of interest that, when used to discount the terminal values of costs and benefits of a project over a given study period, will make the costs equal the benefits when cash flows are reinvested at a specified rate. [1]
Adjusting Leads And Lags
PMI :
A technique used to find ways to bring project activities that are behind into alignment with plan during project execution.
ADM
AACEi :
Syn.: Arrow Diagramming Method (ADM).
ADM Project
PCI :
Non-hierarchical project that uses the arrow-diagramming method.
Administrative Cost
AACEi :
Syn.: General & Administrative Costs (G&A).
Advance Material Release (AMR)
PCI :
A document used by organizations to initiate the purchase of long-lead-time or time-critical materials prior to the final release of a design.
Adverse Weather
AACEi :
Normal weather events that negatively affect the productivity of workers and/or which may affect a project’s critical path or consume float. What deems weather as being adverse is defined differently for each project depending on several factors, including location of a project, the project scope, and even the terms of union construction worker labor agreements. The definition of adverse weather cannot be standardized for all projects or locations, but represents conditions that should be expected during project execution that may impact work progress.
Advertising
PMI :
The process of calling public attention to a project or effort.
Affinity Diagram
PMI :
A group creativity technique that allows large numbers of ideas to be classified into groups for review and analysis.
Agent
AACEi :
A person authorized to represent another (the principal) in some capacity. The agent can only act within this capacity or "scope of authority" to bind the principal. Agency agreements can be oral or in writing.
Aggregate
AACEi :
A collection of items arbitrarily brought together as associated variables for analytical or comparative purposes.
Agile
APM :
A family of development methodologies where requirements and solutions are developed iteratively and incrementally throughout the life cycle.
Agreement
AACEi :
The written agreement between the owner and the contractor covering the work to be performed; other contract documents are attached to the agreement and made a part thereof as provided therein.
PMI :
Any document or communication that defines the initial intentions of a project. This can take the form of a contract, memorandum of understanding (MOU), letters of agreement, verbal agreements, email, etc.
Allocated Baseline
AACEi :
Requirements allocated to lower level system elements controlled by formal change control.
Allocated Requirements
AACEi :
Requirements apportioned to the elements of a system by applying applicable knowledge and experience. Determination of allocated requirements is not as scientifically rigorous as determination of derived requirements.
Allocation
AACEi :
1) In planning and scheduling, the process of distributing or assigning work on an activity to specific resources.
2) In cost estimating and budgeting, the process of distributing or assigning cost of an item or activity (often an overhead or indirect cost) to specific cost or budget accounts.
Allowances
AACEi :
1) For estimating, resources included in estimates to cover the cost of known but undefined requirements for an individual activity, work item, account or sub-account.
2) For scheduling, dummy activities and/or time included in existing activities in a schedule to cover the time for known, but undefined requirements for a particular work task, activity, account or subaccount.
Alternative Analysis
PMI :
A technique used to evaluate identified options in order to select which options or approaches to use to execute and perform the work of the project.
Alternative Dispute Resolution (ADR)
AACEi :
Any procedure or combination of procedures used to resolve issues in controversy without the need to resort to litigation. ADR typically includes assisted settlement negotiations, conciliation, facilitation, mediation, fact-finding, mini-trials, and arbitration.
Alternative Generation
PMI :
A technique used to evaluate identified options in order to select which options or approaches to use to execute and perform the work of the project.
Alternative Resource
PCI :
A resource that may be substituted as the requirement for an activity if the requested resource is not available.
Ambiguity
AACEi :
An uncertainty in the meaning of provisions of a contract, document or specification. Mere disagreement about the meaning of a provision does not indicate an ambiguity. There must be genuine uncertainty of meaning based on logical interpretation of the language used in the contract. Generally, ambiguities in contracts are construed against the drafter of the agreement.
Amendment
AACEi :
A modification of the contract by a subsequent agreement. This does not change the entire existing contract but does alter the terms of the affected provisions or requirements.
Amortization
AACEi :
(1) As applied to a capitalized asset, the distribution of the initial cost by periodic charges to operations as in depreciation. Most properly applies to assets with indefinite life.
(2) The reduction of a debt by either periodic or irregular payments.
(3) A plan to pay off a financial obligation according to some prearranged schedule.
Analogous Critical Path
AACEi :
The logic path determined by transferring the calculated critical path of the collapsed as-built onto the analogous logic path on the as-built schedule. The analogous critical path allows the analyst to reconcile the total difference in completion date between the collapsed state and the as-built state with the sum of the extracted delays, whole or in part, lying on the analogous path.
Analogous Estimating
APM :
An estimating technique based on the comparison with, and factoring from, the cost of similar, previous work.
PMI :
A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project.
Analysis
AACEi :
The examination of a complex whole and the separation and identification of its constituent parts and their relationships.
Analysis (Schedule Variance)
AACEi :
Comparison of actual cost/schedule performance to that planned. This comparison includes identification of “potential change notices” and their cause. Derives from the monitoring of project expenditures, progress and performance. Requires application of independent review and creative thought processes to come up with a comprehensive understanding of how, why, and where project accounts are headed. Analysis should result in corrective action to offset/minimize any potential overruns and maximize any potential under runs.
Analyst-Caused Risk
AACEi :
Syn.: Analyst-Induced Risk; Iatrogenic Risk.
Analyst-Induced Risk
AACEi :
Syn.: Analyst-Caused Risk; Iatrogenic Risk.
Analytical Estimating
APM :
An estimating technique that uses detailed specifications to estimate time and cost for each product or activity.
Analytical Techniques
PMI :
Various techniques used to evaluate, analyze, or forecast potential outcomes based on possible variations of project or environmental variables and their relationships with other variables.
And Relationship
AACEi :
Logical relationship between two or more activities that converges on or diverges from an event. The “and” relationship indicates that every one of the activities has to be undertaken.
Annual Value
AACEi :
A uniform annual amount equivalent to the project costs or benefits taking into account the time value of money throughout the study period. Syn.: Annual Worth; Equivalent Uniform Annual Value.
Annual Worth
AACEi :
Syn.: Annual Value; Equivalent Uniform Annual Value.
Annually Recurring Costs
AACEi :
Those costs that are incurred in a regular pattern each year.
Annuity
AACEi :
(1) An amount of money payable to a beneficiary at regular intervals for a prescribed period of time out of a fund reserved for that purpose.
(2) A series of equal payments occurring at equal periods of time.
Anticipatory Breach
AACEi :
A specific refusal by the contractor to perform within the terms of the contract documents before performance is due; or a clear indication that the contractor is unable or unwilling to perform. Syn.: Repudiation.
Application Area
AACEi :
Projects sharing specialized components that logically segregate work by product or production technology or by user.
PMI :
A category of projects that have common components significant in such projects, but are not needed or present in all projects. Application areas are usually defined in terms of either the product (i.e., by similar technologies or production methods) or the type of customer (i.e., internal versus external, government versus commercial) or industry sector (i.e., utilities, automotive, aerospace, information technologies, etc.). Application areas can overlap.
Application Area
AACEi :
The form furnished by the owner or the engineer which is to be used by the contractor in requesting progress or final payments and which shall contain an affidavit, if required, in the general or supplementary conditions. The application for payment includes all supporting documentation as required by the contract documents.
Applying Leads And Lags
PMI :
A technique that is used to adjust the amount of time between predecessor and successor activities.
Apportioned Effort
AACEi :
(1) An earned value technique that status is assessed consistent with a base task(s). The earned value percent complete of the base effort is used to status the apportioned effort work package. Apportioned effort is technically related and time-phased proportionally to the base until designated.
(2) Effort that cannot be readily measured or divided into discrete work packages, but its performance can be measured in proportion to other measureable efforts.
PMI :
An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. [Note: Apportioned effort is one of three earned value management (EVM) types of activities used to measure work performance.]
Approve
AACEi :
To accept as technically satisfactory by person or persons in authority. The approval may still require confirmation by someone else at a higher level of authority for legal or commercial considerations.
Approved Change Request
PMI :
A change request that has been processed through the integrated change control process and approved.
Approved Change Request Review
PMI :
A review of the change requests to verify that these were implemented as approved.
Approved System
PCI :
An EVM system that has been accepted by a customer, typically documented by an advance agreement or imilar document. Approval may be found at a single geographic location or in multiple locations. Multiple approved systems may also reside within a single geographic location.
Approved To Proceed
PCI :
Approval by the project board at initiation or prior to the beginning of the next stage.
Arbitration
AACEi :
A method for the resolution of disputes by an informal tribunal in which a neutral person or persons with specialized knowledge in the field in question renders a decision on the dispute. An arbitrator may grant any award which is deemed to be just and equitable after having afforded each party full and equal opportunity for the presentation of the case. Arbitration does not strictly follow the rules of evidence and discovery procedures found in litigation. Arbitration may be conducted under the auspices of an organization (e.g., the American Arbitration Association) which is available as a vehicle for conducting arbitration.
Archive Plan
PCI :
A function of some computer programs that allows versions of a plan to be archived.
Arrow
AACEi :
The graphic representation of activities in ADM network. One arrow represents one activity. The tail of the arrow represents the start of the activity. The head of arrow represents the finish. The arrow is not a vector quantity and is not drawn to scale. A solid line is used for actual activities and a dashed line for dummies. It is uniquely defined by two events.
Arrow Diagram
AACEi :
A network (logic diagram) on which the activities are represented by arrows between event nodes.
Arrow Diagramming Method (ADM)
AACEi :
A method of constructing a logical network of activities using arrows to represent the activities and connecting those head-to-tail. This diagramming method shows the sequence, predecessor and successor relationships of the activities. Syn.: ADM.
PCI :
One of two conventions used to represent an activity in a project. Also known as Activity-on-Arrow or i/j method.
Artifact (Planning)
AACEi :
A piece of information that is produced, modified, or used by a process, defines an area of responsibility, and is subject to version control. An artifact can be a model, a model element, or a document. A document can enclose other documents.
As-Built Schedule
AACEi :
Historical project record showing actual start and finish dates for work performed. Generally, shows logic used in the sequence of construction, along with actual start and finish dates.
As-Late-As-Possible (ALAP)
AACEi :
An activity for which the scheduling application sets the early dates as late as possible without delaying the early dates of any successor.
As-Of Date
AACEi :
Syn.: Data Date; Update Date.
As-Planned Schedule
AACEi :
The plan or baseline schedule the contractor developed to estimate/bid/contract to perform the work. The as-planned schedule incorporates planned production rates, work calendars, resource availability, logic ties, constraints and activity durations to meet contract requirements and contractor needs or desires.
As-Soon-As-Possible (ASAP)
AACEi :
An activity for which the scheduling application sets the early dates to be as soon as possible. This is the default activity type in most project management systems.
Assessed Value
AACEi :
That value entered on the official assessor's records as the value of the property applicable in determining the amount of taxes to be assessed against that property.
Assets
AACEi :
Anything owned that has a monetary value, e.g., property, both real and personal, including notes, accounts and accrued earnings or revenues receivable and cash or its equivalent. Assets may be subdivided into current, fixed, etc. Property: real, i.e. physical; or intangible, i.e. knowledge, systems, or practices. Assets are created through the investment of resources in projects.
Assumption
PMI :
A factor in the planning process that is considered to be true, real, or certain, without proof or demonstration.
Assumption Analysis
PMI :
A technique that explores the accuracy of assumptions and identifies risks to the project from inaccuracy, inconsistency, or incompleteness of assumptions.
Attribute
AACEi :
In the context of asset or project planning, a characteristic or property which is appraised in terms of whether it does or does not exist, (e.g., go or not-go) with respect to a given requirement.
Attribute Sampling
PMI :
Method of measuring quality that consists of noting the presence (or absence) of some characteristic (attribute) in each of the units under consideration. After each unit is inspected, the decision is made to accept a lot, reject it, or inspect another unit.
Audit
AACEi :
In the context of asset or project performance assessment, a formal, independent examination with intent to verify conformance with established requirements through surveillance and inspection. They may be either internal or external.
Authority
AACEi :
(1) Power of influence, either granted to or developed by individuals, that leads to others doing what those individuals direct.
(2) Formal conferment of such influence through an instrument such as a project charter.
PMI :
The right to apply project resources, expend funds, make decisions, or give approvals.
Authorize
AACEi :
Give final approval; a person who can authorize something is vested with authority to give final endorsement and which requires no further approval or agreement.
Authorized Unpriced Work (AUW)
PCI :
Any scope changed for which authorization to proceed has been given, but for which the estimated costs are not yet settled.
Authorized Work
AACEi :
An effort that has been approved by higher authority and may or may not be definitive.
PCI :
The effort which has been defined, plus that work for which authorization has been given, but for which defined contract costs have not been agreed upon.
Average Annual Cost
AACEi :
The conversion, by an interest rate and present worth technique, of all capital and operating costs to a series of equivalent equal annual costs. As a system for comparing proposal investments, it requires assumption of a specific minimum acceptable interest rate.
Average-Interest Method
AACEi :
A method of computing required return on investment based on the average book value of the asset during its life or during a specified study period.
Avoid
AACEi :
In TCM risk management, a response strategy for threats that involves eliminating either the probability or impact.
APM :
A response to a threat that eliminates its probability or impact on the project.
Avoidance (Risk)
AACEi :
Risk response strategy that eliminates the threat or opportunity of a specific risk event, usually by eliminating its potential cause.
PMI :
Risk Avoidance: A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Backcharge
AACEi :
Cost of corrective action taken by the purchaser, chargeable to supplier by contract terms.
Backlog
PMI :
A listing of product requirements and deliverables to be completed, written as stories, and prioritized by the business to manage and organize the project’s work.
Backup
AACEi :
Supporting documents for an estimate or schedule including detailed calculations, descriptions of data sources, and comments on the quality of the data.
Backward Pass
AACEi :
Network schedule calculation that determines the latest each activity in the network may start (LS) and finish (LF) and still maintain the minimum overall duration of the project as calculated by the forward pass. It counts backward toward the beginning of the schedule to determine the last possible start and finish dates for each activity that will not delay project completion.
PMI :
A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
PCI :
A procedure within time analysis to calculate the late start and late finish dates of all activities in a project.
Balance
APM :
A phase in the portfolio life cycle where the component projects and programmes are balanced in terms of risk, resource usage, cash flow and impact across the business.
Balanced Matrix
PCI :
An organizational matrix where functions and projects have the same priority.
Bar Chart
AACEi :
Graphic representation of a project that includes the activities that makes up the project and placed on a time scale. Bar charts are time scaled, show activity number, description, duration, start and finish dates, and an overall sequencing of the flow of work. Bar charts do not generally include the logic ties between activities.
PMI :
A graphic display of schedule-related information. In the typical bar chart, schedule activities or work breakdown structure components are listed down the left side of the chart, dates are shown across the top, and activity durations are shown as date-placed horizontal bars.
PCI :
A view of project data that uses horizontal bars on a time scale to depict activity information. Frequently called a Gantt chart.
Base
AACEi :
Syn.: Base Estimate; Base Schedule.
Base Date
AACEi :
Syn.:Base Time
PCI :
Original planned start and finished dates for an activity. Used to compare with current planned dates to determine any delays. Also used to calculate budgeted cost of work scheduled for earned-valued analysis.
Base Estimate
AACEi :
Estimate excluding escalation, foreign currency exchange, contingency and management reserves. Syn.: Point Estimate ; Single Point Estimate.
Base Period (Of A Given Price Index)
AACEi :
Period for which prices serve as a reference for current period prices; in other words, the period for which an index is defined as 100 (if expressed in percentage form) or as 1 (if expressed in ratio form).
Base Point For Escalation
AACEi :
Cost index value for a specific month or an average of several months that is used as a basis for calculating escalation.
Base Schedule
AACEi :
Schedule excluding risks (i.e., excluding contingency).
Base Time
AACEi :
The date to which all future and past benefits and costs are converted when a present value method is used (usually the beginning of the study period). Syn.: Base Date.
Baseline
AACEi :
(1) In project control, the reference plans in which cost, schedule, scope and other project performance criteria are documented and against which performance measures are assessed and changes noted.
(2) The budget and schedule that represent approved scope of work and work plan. Identifiable plans, defined by databases approved by project management and client management, to achieve selected project objectives. It becomes basis for measuring progress and performance and is baseline for identifying cost and schedule deviations. Syn.: Control Baseline.
(3) In earned value management systems, the general term to refer to the contractual baseline. See contract budget baseline and performance measurement baseline for the typical earned value management (EVM) definitions of the different baseline levels within the EVM baseline plan.
APM :
The reference levels against which a project, programme or portfolio is monitored and controlled.
PMI :
The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
PCI :
A copy of the project schedule for a particular time (usually before the project is started) that can be used for comparison with the current schedule.
Baseline Review
PCI :
A customer review conducted to determine with a limited sampling that a contractor is continuing to use the previously accepted performance system and is properly implementing a baseline on the contract or option under review.
Baseline Schedule
AACEi :
(1) A fixed project schedule that is the standard by which project performance is measured. The current schedule is copied into the baseline schedule that remains frozen until it is reset. Resetting the baseline is done when the scope of the project has been changed significantly, for example after a negotiated change. At that point, the original or current baseline becomes invalid and should not be compared with the current schedule.
(2) Version of schedule that reflects all formally authorized scope and schedule changes.
PCI :
The baseline schedule is a fixed project schedule. It is the standard by which project performance is measured. The current schedule is copied into the baseline.
Basis
AACEi :
Written documentation that describes how an estimate, schedule, or other plan component was developed and defines the information used in support of development. A basis document commonly includes, but is not limited to, a description of the scope included, methodologies used, references and defining deliverables used, assumptions and exclusions made, clarifications, adjustments, and some indication of the level of uncertainty.
Basis Of Estimate
PMI :
Supporting documentation outlining the details used in establishing project estimates such as assumptions, constraints, level of detail, ranges, and confidence levels.
Batch Operations
PCI :
Operations performed by the computer without the need for any user intervention.
Battery Limit
AACEi :
Comprises one or more geographic boundaries, imaginary or real, enclosing a plant or unit being engineered and/or erected, established for the purpose of providing a means of specifically identifying certain portions of the plant, related groups of equipment, or associated facilities. It generally refers to the processing area and includes all the process equipment, and excludes such other facilities as storage, utilities, administration buildings, or auxiliary facilities. The scope included within a battery limit must be well-defined so that all personnel will clearly understand it. On drawings, this is often referred to in the phrase: inside/outside battery limits or ISBL/OSBL.
Beginning (Start) Node Of Network (ADM)
AACEi :
A node at which no activities end, but one or more activities begin.
Beginning Event
AACEi :
An event that signifies the beginning of an activity. Syn.: Preceding Event; Predecessor Event; Starting Event.
Beginning Network Event
AACEi :
The event that signifies the beginning of a network (or subnet).
Benchmarking
AACEi :
A measurement and analysis process that compares practices, processes, and relevant measures to those of a selected basis of comparison (i.e., the benchmark) with the goal of improving performance. The comparison basis includes internal or external competitive or best practices, processes or measures. Examples of measures include estimated costs, actual costs, schedule durations, resource quantities, etc.
PMI :
Bench-marking is the comparison of actual or planned practices, such as processes and operations, to those of comparable organizations to identify best practices, generate ideas for improvement, and provide a basis for measuring performance.
Beneficial Occupancy
AACEi :
Use of a building, structure, or facility by the owner for its intended purpose (functionally complete), although other contract work, nonessential to the function of the occupied section, remains to be completed.
Benefit
APM :
The quantifiable and measurable improvement resulting from completion of deliverables that is perceived as positive by a stakeholder. It will normally have a tangible value, expressed in monetary terms that will justify the investment.
PCI :
The enhanced efficiency, economy and effectiveness of future business operations to be delivered by a program.
Benefit Cost Analysis
AACEi :
A method of evaluating projects or investments by comparing the present value or annual value of expected benefits to the present value or annual value of expected costs.
Benefit Framework
PCI :
An outline of the expected benefits of the program, the business operations affected and current and target performance measures.
Benefit Management
APM :
The identification, definition, planning, tracking and realisation of business benefits.
PCI :
Combined with program management, Benefits Management is the process for planning, managing, delivering and measuring the program benefits.
Benefit Management Plan
PCI :
Specifies who is responsible for achieving the benefits set out in the benefit profiles and how achievement of the benefits is to be measured, managed and monitored. The Benefits Management Plan is part of the program definition.
Benefit Profile
PCI :
Located in the program definition, the Benefits Profiles describe the planned benefits to be realized by the program. The benefits profile also states where, when and how they are to be realized.
Benefit Realization
APM :
The practice of ensuring that benefits are derived from outputs and outcomes.
Benefit-To-Cost Ratio (BCR)
AACEi :
Benefits divided by costs, where both are discounted to a present value or equivalent uniform annual value.
Best Practices
AACEi :
Practical techniques gained from experience that have been shown to produce best results.
Biases
AACEi :
Lack of objectivity based on the enterprise’s or individual's position or perspective. Systematic and predictable relationships between a person's opinion or statement and his/her underlying knowledge or circumstances. Note: There may be "System Biases" as well as "Individual Biases".
Bid
AACEi :
To submit a price for services; a proposition either verbal or written, for doing work and for supplying materials and/or equipment.
Bid Bond
AACEi :
Syn.: Bond, Bid.
Bid Security
AACEi :
Security is provided in connection with the submittal of a bid to guarantee that the bidder, if awarded or offered the contract, will execute the contract and perform the work. The requirements for the bid security are usually designated in a specific section of the bidding documents. The bid security is payable to the owner (usually around 5% of the total bid price) in the form of either a certified or bank check or a bid bond issued by a surety satisfactory to the owner. The bid security of the successful bidder is usually retained until the bidder has executed the agreement and furnished the required contract security, whereupon the bid security is returned. Bid security of the other bidders is returned after the bid opening.
Bidder
AACEi :
The individual, partnership, or corporation, or combination thereof, acting directly or through an authorized representative, formally submitting a bid directly to the owner, as distinct from a sub-bidder, who submits a bid to a bidder.
Bidder Conference
PMI :
The meetings with prospective sellers prior to the preparation of a bid or proposal to ensure all prospective vendors have a clear and common understanding of the procurement. Also known as contractor conferences, vendor conferences, or pre-bid conferences.
Bidding Documents
AACEi :
The advertisement for bids, instructions to bidders, information available to bidders, bid form with all attachments, and proposed contract documents (including all addenda issued prior to receipt of bids).
Bidding Requirements
AACEi :
The advertisement for bids, instructions to bidders, supplementary instructions and all attachments therein, information to bidders and all attachments therein, and bid form and all attachments therein.
Bill Of Materials (BOM)
AACEi :
(1) Set of physical elements required to build a project.
(2) Hierarchical view of the physical assemblies, subassemblies, and components needed to fabricate a manufacturing product.
(3) Descriptive and quantitative list of materials, supplies, parts, and components required to produce a designated complete end item of materials, assembly, or subassembly.
Bill Of Quantities (BOQ)
AACEi :
Descriptive and quantitative list of materials, supplies, parts, and components required to produce a designated complete end item of materials, assembly, or subassembly. Typically includes a description of the associated “method of measurement”.
Blanket Bond
AACEi :
An effort by a prime contractor to reduce the prices quoted by subcontractors and/or suppliers, by providing the bid price to other subcontractors or suppliers in an attempt to get the other subcontractors or suppliers to underbid the original price quoted. The reverse of this situation is when subcontractors try to get a better price out of a prime contractor. This is known as bid peddling.
Blue Print
APM :
A document defining and describing what a programme is designed to achieve in terms of the business and operational vision.
Board
APM :
A body that provides sponsorship to a project, programme or portfolio. The board will represent financial, provider and user interests.
Bond, Bid
AACEi :
A bond that guarantees the bidder will enter into a contract on the basis of the bid.
Bond, Payment
AACEi :
A bond that is executed in connection with a contract and which secures the payment of all persons supplying labor and material in the prosecution of the work provided for in the contract.
Bond, Performance
AACEi :
A bond that is executed in connection with a contract and which secures or guarantees the completion, performance and fulfillment of all the work, undertakings, covenants, terms, conditions, and agreements contained in the contract.
Bonds
AACEi :
Instruments of security furnished by the contractor and/or surety in accordance with the contract documents. The term contract security refers to the payment bond, performance bond and those other instruments of security
required in the contract documents.
Book Value (Net)
AACEi :
(1) Current investment value on the books calculated as original value less depreciated accruals.
(2) New asset value for accounting use.
(3) The value of an outstanding share of stock of a corporation at any one time, determined by the number of shares of that class outstanding.
Bottom-Line
AACEi :
Ambiguous term that in TCM cost estimating or risk management typically refers to the total overall cost or profit of a project or program. In TCM decision analysis, may refer to a stakeholder’s threshold or decision making criterion beyond which a decision not-to-proceed, approve, or accept will be made.
Bottom-Up Estimating
APM :
An estimating technique that uses detailed specifications to estimate time and cost for each product or activity.
PMI :
"A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS)."
PCI :
This is the method of making estimates for every activity in the work breakdown structure and summarizing them to provide a total project cost estimate.
Brainstorming
AACEi :
Process in which a group of people, selected for their creativity and knowledge, are brought together to seek solutions to particular problems or simply to find better ways of meeting objectives. Suggestions, however outlandish, are encouraged and pursued during a creativity session. From this, many ideas, some entirely new, are brought forward for analysis and ranking.
PMI :
"A general data gathering and creativity technique that can be used to identify risks, ideas, or solutions to issues by using a group of team members or subject matter experts.
PCI :
The unstructured generation of ideas by a group of people.
Breach Of Contract
AACEi :
Failure, by either the owner or the contractor, without legal excuse, to perform any work or duty owed to the other person.
Breakdown Structure
AACEi :
A hierarchical structure by which project elements are broken down, or decomposed.
APM :
A hierarchical structure by which project elements are broken down, or decomposed. Examples include: Cost Breakdown Structure (CBS), Organisational Breakdown Structure (OBS), Product Breakdown Structure (PBS), and Work Breakdown Structure (WBS).
Breakeven Chart
AACEi :
A graphic representation of the relation between total income and total costs for various levels of production and sales indicating areas of profit and loss.
Breakeven Point
AACEi :
(1) In business operations, the rate of operations output, or sales at which income is sufficient to equal operating costs or operating cost plus additional obligations that may be specified.
(2) The operating condition, such as output, at which two alternatives are equal in economy.
(3) The percentage of capacity operation of a manufacturing plant at which income will just cover expenses.
Breakout Schedule
AACEi :
Jobsite schedule, generally in bar chart form, used to communicate day-to-day activities to all working levels on the project as directed by construction manager. Detail information with regard to equipment use, bulk material requirements, and craft skills distribution, as well as the work to be accomplished, forms content of schedule. Issued on a weekly basis with a two to three-week look ahead from the issue date.
Brief
APM :
The output of the concept phase of a project or programme.
Budget At Completion (BAC)
AACEi :
The summation of time phased costs at any Work Breakdown Structure (WBS) level. In earned value management according to the ANSI EIA 748 standard, all levels have BAC including work packages, planning packages, summary planning packages, Performance Management Baseline (PMB), Management Reserve (MR), Undistributed Budget (UB), and Contract Budget Baseline (CBB).
PMI :
The sum of all budgets established for the work to be performed.
PCI :
The sum total of the time-phased budget.
Budget Elements
PCI :
Budget elements are the same as resources -- the people, materials, or other entities needed to do the work of the program. For example, Engineer, Technician, Travel, and Pipe can all be budget elements. These budget elements can be validated against a Resource Breakdown Structure (RBS). Budget elements are typically assigned to a work package, but can also be defined at the cost account level.
Budget Estimate
AACEi :
An estimate generally prepared to form the basis for authorization and/or appropriation of funds.
Budget Unit
PCI :
The budget unit is the base unit for the calculation. For example, the Engineer budget element might have a budget unit of hours. Since budget units are user defined, they can be any appropriate unit of measure. For example, a budget unit might be hours, dollars, linear feet, or tons.
Budgeted Cost Of Work Performed (BCWP)
AACEi :
Syn.: Earned Value (EV).
PCI :
A measure used to quantify the overall progress of the investment in monetary terms. BCWP is calculated by applying a performance measurement factor to the planned cost. (By comparing BCWP with ACWP, it is possible to determine if the investment is under or over budget.) Another term for BCWP is ""Earned Value.""
Budgeted Cost Of Work Scheduled (BCWS)
AACEi :
Syn.: Planned Value (PV).
PCI :
The sum of the budgets for all planned work scheduled to be accomplished within a given time period. This term is often used to designate the cumulative to-date budget.
Budgeting
AACEi :
A process used to allocate the estimated cost of resources into cost accounts (i.e., the cost budget) against which cost performance will be measured and assessed. Budgeting often considers time-phasing in relation to a schedule and/or time-based financial requirements and constraints.
APM :
Budgeting and cost control: The estimation of costs, the setting of an agreed budget, and management of actual and forecast costs against that budget.
PCI :
Time phased financial requirements.
Budget
AACEi :
A planned allocation of resources. The planned cost of needed materials is usually subdivided into quantity required and unit cost. The planned cost of labor is usually subdivided into the workhours required and the wage rate (plus fringe benefits and taxes).
PMI :
The approved estimate for the project or any work breakdown structure component or any schedule activity.
PCI :
The planned cost for an activity or project.
Buffer
APM :
A term used in critical chain for the centralised management of contingencies.
PMI :
A provision in the project management plan to mitigate cost and/or schedule risk. Often used with a modifier (e.g., management reserve, contingency reserve) to provide further detail on what types of risk are meant to be mitigated.
Bulk Material
AACEi :
Material bought in lots. These items can be purchased from a standard catalog description and are bought in quantity for distribution as required. Examples are pipe (non-spooled), conduit, fittings, and wire.
Burden
AACEi :
(1) In construction, the cost of maintaining an office with staff other than operating personnel. Also includes federal, state and local taxes, fringe benefits and other union contract obligations. In manufacturing, burden sometimes denotes overhead.
(2) In earned value, this is a broad term that refers to all non-direct costs including overheads, general & administrative, and cost of money as applicable. The common characteristic of a burden is the cost is expressed as a rate on top of the direct costs.
PCI :
Overhead expenses distributed over appropriate direct labor and/or material base.
Burden Of Proof
AACEi :
The necessity of proving the facts in a dispute on an issue raised between the owner and the contractor. In a claim situation, the burden of proof is always on the person filing the claim. This is true whether the contractor is claiming against the owner, or the owner is making a claim against the contractor.
Burn Rate
AACEi :
Rate at which resources such as funds or man-hours are or were being expended on a project.
Business Assurance
PCI :
Ensuring that actual costs and elapsed time is in line with plan costs and schedule times and that the business case remains available.
Business Assurance Coordinator
PCI :
A person in the project assurance team who is responsible for planning, monitoring and reporting on all business assurance aspects of a project.
Business Case
AACEi :
Defines a project’s or other investment’s justification for business decision making purposes. Depending upon the business’ decision making criteria, it typically includes an outline of objectives, deliverables, time, cost, technical, safety, quality and other attributes in respect to how the project or investment addresses the objectives and requirements of the business. May include information on project risks (either threats or opportunities), competitive impact, resource requirements, organizational impacts, key performance indicators (particularly profitability) and critical success factors.
APM :
Provides justification for undertaking a project or programme. It evaluates the benefit, cost and risk of alternative options and provides a rationale for the preferred solution.
PMI :
A documented economic feasibility study used to establish validity of the benefits of a selected
component lacking sufficient definition and that is used as a basis for the authorization of further project management activities.
PCI :
A document used to justify the commitment of resources to a project.
Business Change Manager
APM :
The role responsible for benefits management from identification through to realisation.
Business Planning
AACEi :
The determination of financial, production and sales goals of a business organization; and the identification of resources, methods, and procedures required to achieve the established objectives within specified budgets and timetables.
Business Risk Assessment
APM :
The assessment of risk to business objectives rather than risk to achieving project, programme or portfolio objectives.
Business Value
PMI :
A concept that is unique to each organization and includes tangible and intangible elements. Through the effective use of project, program, and portfolio management disciplines, organizations will possess the ability to employ reliable, established processes to meet enterprise objectives and obtain greater business value from their investments.
Business-As-Usual
APM :
An organisation’s normal day-to-day operations.
Buyer
PMI :
The acquirer of products, services, or results for an organization.
Calculate Schedule
AACEi :
A modeling process that defines all critical activities and individual activity scheduling data. The process applied in most scheduling software calculates the start and finish dates of activities in two passes. The first pass calculates early start and finish dates from the earliest start date forward. The second pass calculates the late start and finish activities from the latest finish date backwards. The difference between the pairs of start and finish dates for each task is the float or slack time for the task.
Calendar
AACEi :
Defined work periods and holidays that determine when project activities may be scheduled. Multiple calendars may be used for different activities, which allows for more accurate modeling of the project work plan. E.g., 5-day work week calendar vs. 7-day work week.
PCI :
A project calendar lists time intervals in which activities or resources can or cannot be scheduled. A project usually has one default calendar for the normal work week (Monday through Friday for example), but may have other calendars as well. Each calendar can be customized with its own holidays and extra work days. Resources and activities can be attached to any of the calendars that are defined.
Calendar Range
AACEi :
Span of the calendar from calendar start through end date. The calendar start date is unit number one. The calendar range is usually expressed in years.
Calendar Start Date
AACEi :
The date assigned to the first unit of the defined calendar; the first day of the schedule.
Calendar Unit
AACEi :
The smallest common/standard unit of time used in a particular calendar for scheduling an activity or a project. Calendar units are generally in hours, days, or weeks, but can also be shifts or even minutes.
Calendar File
PCI :
A file containing calendar information for one or more calendars.
Capacity Factor
AACEi :
In cost estimating, an exponential factor used in the capacity factor estimating method. Syn.: Capacity Utilization Factor; Scaling Factor.
Capacity Factor Method
AACEi :
In cost estimating, an exponential factor used in the capacity factor estimating method. Syn.: Capacity Utilization Factor; Scaling Factor.
Capacity Utilization Factor
AACEi :
Syn.: Capacity Factor; Scaling Factor.
Capital Budgeting
AACEi :
A systematic procedure for classifying, evaluating, and ranking proposed capital expenditures for the purpose of comparison and selection, combined with the analysis of the financing requirements.
Capital Project
AACEi :
A project in which the cost of the end result or product is capitalized (i.e., cost will be depreciated). The product is usually a physical asset such as property, real estate or infrastructure, but may include other assets that are depreciable.
Capital Recovery
AACEi :
(1) Charging periodically to operations amounts that will ultimately equal the amount of capital expenditure.
(2) The replacement of the original cost of an asset plus interest.
(3) The process of regaining the net investment in a project by means of revenue in excess of the costs from the project. (Usually implies amortization of principal plus interest on the diminishing, unrecovered balance.)
Capital Recovery Factor
AACEi :
A factor used to calculate the sum of money required at the end of each of a series of periods to regain the net investment of a project plus the compounded interest on the unrecovered balance.
Capital, Direct
AACEi :
Syn.: Direct Costs.
Capital, Fixed
AACEi :
The total original value of physical facilities which are not carried as a current expense on the books of account and for which depreciation is allowed by the Federal Government. It includes plant equipment, building, furniture and fixtures, and transportation equipment used directly in the production of a product or service. It includes all costs incident to getting the property in place and in operating condition, including legal costs, purchased patents, and paid-up licenses. Land, which is not depreciable, is often included. Characteristically it cannot be converted readily into cash.
Capital, Indirect
AACEi :
Syn.: Indirect Costs.
Capital, Operating
AACEi :
Capital associated with process facilities inside battery limits.
Capital, Sustaining
AACEi :
The fixed capital requirements to:
1) Maintain the competitive position of a project throughout its commercial life by improving product quality, related services, safety, or economy; or,
2) Required to replace facilities which wear out before the end of the project life.
Capital, Total
AACEi :
Sum of fixed and working capital.
Capital, Venture
AACEi :
Capital invested in technology or markets new at least to the particular organization.
Capital, Working
AACEi :
The funds in addition to fixed capital and land investment which a company must contribute to the project (excluding startup expense) to get the project started and meet subsequent obligations as they come due. Working capital includes inventories, cash and accounts receivable minus accounts payable. Characteristically, these funds can be converted readily into cash. Working capital is normally assumed recovered at the end of the project.
Capitalized Cost
AACEi :
(1) The present worth of a uniform series of periodic costs that continue for an indefinitely long time (hypothetically infinite).
(2) The value at the purchase date of the asset of all expenditures to be made in reference to this asset over an indefinite period of time. This cost can also be regarded as the sum of capital which, if invested in a fund earning a stipulated interest rate, will be sufficient to provide for all payments required to maintain the asset in perpetual service.
Cards-On-The-Wall Planning
AACEi :
A planning technique in which team members interact to create a project strategy, tactical approach, and resulting network by locating and interconnecting task cards using walls as the work space. The wall data are transferred into a computer model for scheduling, critical path analysis and iteration.
Case Structure
PCI :
A breakdown of the project budget. Case numbers can be subdivided only twice to produce three levels: Case, Sub-Case, and Sub-Sub-Case.
Cash Costs
AACEi :
Total cost excluding capital and depreciation spent on a regular basis over a period of time, usually one year. Cash costs consist of manufacturing cost and other expenses such as transportation cost, selling expense, research and development cost or corporate administrative expense.
Cash Flow (Net)
AACEi :
The net flow of funds into or out of a project. The sum, in any time period, of all cash receipts, expenses, and investments. Also called cash proceeds or cash generated. The stream of monetary values—costs and benefits—resulting from a project investment.
Cash Flow Management
AACEi :
The planning of project expenditures relative to income or authorized funding in such a way as to minimize the carrying cost of the financing for the project or keep within the constraints of a time-phased budget. This maybe achieved by accelerating or delaying some activities, but at the risk of ineffective performance, late completion and consequent increased cost.
Cash Flow
AACEi :
Inflow and outflow of funds within a project. A time-based record of income and expenditures, often presented graphically.
Cash Return, Percent Of Total Capital
AACEi :
Ratio of average depreciation plus average profit, to total fixed and working capital, for a year of capacity sales. Under certain limited conditions, this figure closely approximates that calculated by profitability index techniques where it is defined as the difference, in any time period, between revenues and all cash expenses, including taxes.
Categorise
APM :
A phase in the portfolio life cycle where the component projects and programmes may be grouped according to shared characteristics.
Causation
AACEi :
An explanation or description of the facts and circumstances that produce a result, the cause and effect for which the contractor claims entitlement to compensation from the owner under the contract.
Cause And Effect Diagram
PMI :
A decomposition technique that helps trace an sirable effect back to its root cause.
Cause Of Risk
AACEi :
Syn.: Risk Drivers.
Central Tendency
PMI :
property of the central limit theorem predicting that the data observations in a distribution will tend to group around a central location. The three typical measures of central tendency are the mean, median, and mode."
Certainty
AACEi :
Unquestionable. Free of doubt. No risk involved.
Chain
AACEi :
A series of elements joined together in sequence, such as a logical series of activities or occurrences.
Change
AACEi :
Alteration or variation to a scope of work and/or the schedule for completing the work.
Change Control
AACEi :
(1) Process of accepting or rejecting changes to the project's baselines. Lack of change control is one of the most common causes of scope creep.
(2) Process of implementing procedures that ensure that proposed changes are properly assessed and, if approved, incorporated into the project plan. Uncontrolled changes are one of the most common causes of delay and failure.
(3) Risk abatement process of accepting or rejecting changes to the project's baselines, based on predetermined criteria or "trigger points.”
APM :
The process through which all requests to change the baseline scope of a project, programme or portfolio are captured, evaluated and then approved, rejected or deferred.
PMI :
A process whereby modifications to documents, deliverables, or baselines associated with the project are identified, documented, approved, or rejected.
Change Control Board (CCB)
PMI :
A formally chartered group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project, and for recording and communicating such decisions.
PCI :
A formally constituted group of stakeholders responsible for approving or rejecting changes to the project baselines.
Change Control System
PMI :
A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
Change Control Tools
PMI :
Manual or automated tools to assist with change and/or configuration management. At a minimum, the tools should support the activities of the CCB.
Change Documentation/Log
AACEi :
Records of changes proposed, accepted and rejected.
APM :
Change Register: A record of all proposed changes to scope.
Change Freeze
APM :
A point after which no further changes to scope will be considered.
Change In Scope
AACEi :
A change in the defined deliverables or resources used to provide them. Syn.: Scope Change.
Change In Sequence
AACEi :
A change in the order of work initially specified or planned by the contractor. If this change is ordered by the owner and results in additional cost to the contractor, the contractor may be entitled to recovery under the changes clause.
Change Log
PMI :
A comprehensive list of changes made during the project. This typically includes dates of the change and impacts in terms of time, cost, and risk.
Change Management
AACEi :
The formal process through which changes to the project plan are identified, assessed, reviewed, approved and introduced.
APM :
Change management is a structured approach to moving an organisation from the current state to the desired future state.
Change Notice
AACEi :
The form that is used by the owner to communicate a change in scope or baseline to the contract.
PMI :
Requested Change: A formally documented change request that is submitted for approval to the integrated change control process.
Change Order
AACEi :
A document requesting and/or authorizing a scope and/or baseline change or correction.
1) From the owner’s perspective, it is an agreement between the project team and higher authority approving a change in the project control baseline.
2) From a contractor’s perspective, it is an agreement between the owner and the contractor to compensate for a change in scope or other conditions of a contract. It must be approved by both the client and the contractor before it becomes a legal change to the contract.
Change Request
APM :
A request to obtain formal approval for changes to the scope of work.
PMI :
A formal proposal to modify any document, deliverable, or baseline.
PCI :
Change requests may arise through changes in the business or issues in the project. Change requests should be logged, assessed and agreed on before a commitment to the project can be made. Changes may be needed to the scope, design, methods or planned aspects of a project.
Change, Cardinal
AACEi :
Work that is beyond the scope of that specified in the contract and consequently unauthorized. The basic tests for a cardinal change are whether the type of work was within the contemplation of the parties when they entered into the contract and whether the job as modified is still the same basic job.
Change, Constructive
AACEi :
An act or failure to act by the owner or the engineer that is not a directed change, but which has the effect of requiring the contractor to accomplish work different from that required by the existing contract documents.
Change, Unilateral
AACEi :
Syn.: Modification, Unilateral.
Changed Conditions
AACEi :
Syn.: Differing Site Conditions.
Chart Of Accounts
AACEi :
Syn.: Code of Accounts(COA).
PCI :
Any numbering system, usually based on corporate chart of accounts of the primary performing organization, used to monitor project costs by category.
Charter
PMI :
Project Charter: A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Checksheets
PMI :
A tally sheet that can be used as a checklist when gathering data.
Child
AACEi :
A lower-level element in a hierarchical structure.
Child Activity
AACEi :
Subordinate task belonging to a 'parent' task existing at a higher level in the work breakdown structure.
Chunk Chart
PCI :
List of prioritized project work areas for a given case number and fiscal year as part of a Dept. of Energy (DOE) Defense programs (DP) Sector Project Data Document (PDD).
Claim
AACEi :
A demand or assertion of rights by one party against another for damages sustained under the terms of a legally binding contract. Damages might include money, time, or other compensation to make the claimant whole.
PMI :
A request, demand, or assertion of rights by a seller against a buyer, or vice versa, for consideration,compensation, or payment under the terms of a legally binding contract, such as for a disputed change.
Claim Administration
PMI :
The process of processing, adjudicating, and communicating contract claims.
Client
AACEi :
(1) Party to a contract who commissions the work. On capital projects, may also be referred to as the “owner”.
(2) Customer, principal, owner, promoter, buyer, or end user of the product or service created by the project.
Close Procurements
PMI :
The process of completing each project procurement.
Closed Procurements
PMI :
Project contracts or other procurement agreements that have been formally acknowledged by the proper authorizing agent as being finalized and signed off.
Closeout
AACEi :
The completion of project work. The phase at the end of a project lifecycle just before the operations begins.
APM :
Closure: The formal end point of a project or programme, either because it has been completed or because it has been terminated early.
PMI :
Close Project or Phase: The process of finalizing all activities across all of the Project Management Process Groups to formally complete a project or phase.
PCI :
The completion of work on a project.
Closing Process Groups
PMI :
Those processes performed to finalize all activities across all Process Groups to formally close a project or phase.
Code
AACEi :
A referencing system typically applied to the elements of work and cost breakdown structures.
Code File
PCI :
A file used in reporting that contains information associated with codes entered on an activity record.
Code Of Accounts (COA)
AACEi :
A systematic coding structure for organizing and managing scope, asset, cost, resource, work, and schedule activity information. A COA is essentially an index to facilitate finding, sorting, compiling, summarizing, or otherwise managing information that the code is tied to. A complete code of accounts includes definitions of the content of each account. Syn.:Chart Of Accounts.
PMI :
A numbering system used to uniquely identify each component of the work breakdown structure (WBS).
Coding
AACEi :
The process of applying a code.
Collaborative Negotiation
APM :
Negotiation that seeks to create a ‘win-win’ scenario where all parties involved get part or all of what they were looking for from the negotiation.
Colocation
PMI :
An organizational placement strategy where the project team members are physically located close to one another in order to improve communication, working relationships, and productivity.
Commissioning
AACEi :
Activities performed to substantiate the capabilities of individual units and systems to function as designed. May include performance tests on mechanical equipment, water washing, flushing and drying of equipment and piping, control systems operability checks, checking of safety and fire protection devices, and operation of systems on inert fluids. Commissioning normally follows mechanical completion and ends with initial operation or startup.
Commitments
AACEi :
The sum of all financial obligations made, including incurred costs and expenditures as well as obligations, which will not be performed until later.
PCI :
A binding financial obligation typically in the form of a purchase order. If commitments are entered as a budget, a forecast using the method Retain EAC can show the open commitments.
Committed Cost
AACEi :
A cost which has not yet been paid, but an agreement, such as a purchase order or contract, has been made that the cost will be incurred.
APM :
Committed expenditure: Costs that have not yet been paid but cannot be cancelled.
PCI :
Costs that will still be incurred even if the project is terminated.
Commodity
AACEi :
In price index nomenclature, a good and sometimes a service.
Communication
APM :
The means by which information or instructions are exchanged.Successful communication occurs when the received meaning is the same as the transmitted meaning.
PCI :
The transmission of information so that the recipient understands what the sender intends.
Communication Constraints
PMI :
Restrictions on the content, timing, audience, or individual who will deliver a communication usually stemming from specific legislation or regulation, technology, or organizational policies.
Communication Management Plan
PMI :
A component of the project, program, or portfolio management plan that describes how, when, and by whom information about the project will be administered and disseminated.
Communication Methods
PMI :
A systematic procedure, technique, or process used to transfer information among project stakeholders.
Communication Models
PMI :
A description, analogy or schematic used to represent how the communication process will be performed for the project.
Communication Requirement Analysis
PMI :
An analytical technique to determine the information needs of the project stakeholders through interviews, workshops, study of lessons learned from previous projects, etc.
Communication Technology
PMI :
Specific tools, systems, computer programs, etc., used to transfer information among project stakeholders.
Communications Planning
PCI :
Determining project stakeholders’ communication and information needs.
Communities Of Practice
APM :
Groups of people who share a concern or passion for an aspect of P3 management and develop expertise through regular interaction.
Company
AACEi :
Term used primarily to refer to a business first party, the purpose of which is to supply a product or service. In a capital project, typically refers to the contractor who is performing services for an owner or client.
Comparative Estimating
APM :
An estimating technique based on the comparison with, and factoring from, the cost of similar, previous work.
Competence
APM :
The combined knowledge, skill and behaviour that a person needs to perform properly in a job or work role.
Competence Framework
APM :
A set of competences and competencies that may be used to define a role.
Competency
APM :
A personal attribute of an individual.
Completed Activity
AACEi :
An activity with an actual completion date and remaining duration of zero. An activity that is finished, ended and/or concluded in accordance with requirements.
Completion (Contract)
AACEi :
When the entire work has been performed to the requirements of the contract, except for those items arising from the provisions of warranty, and is so certified.
Completion Date (Planned)
AACEi :
The calculated date for completion derived from estimating, planning and risk evaluation taking into account contingencies for identified risks.
PCI :
The date calculated by which the project could finish following careful estimating.
Complexity
APM :
Complexity relates to the degree of interaction of all the elements that comprise P3 management and is dependent on such factors as the level of risk, range of stakeholders and degree of innovation.
Compliance
PMI :
A general concept of conforming to a rule, standard, law, or requirement such that the assessment of compliance results in a binomial result stated as “compliant” or “noncompliant."
Composite Price Index
AACEi :
An index which measures the price change of a range or group of commodities.
Compound Amount
AACEi :
The future worth of a sum invested (or loaned) at compound interest.
Compound Amount Factor
AACEi :
(1) The function of interest rate and time that determines the compound amount from a stated initial sum.
(2) A factor which when multiplied by the single sum or uniform series of payments will give the future worth at compound interest of such single sum or series.
Compound Interest
AACEi :
(1) The type of interest that is periodically added to the amount of investment (or loan) so that subsequent interest is based on the cumulative amount.
(2) The interest charges under the condition that interest is charged on any previous interest earned in any time period, as well as on the principal.
Compound Risk
AACEi :
Syn.: Risk (Impact) Compounding.
PCI :
A risk made up of a number of inter-related risks.
Compounding Period
AACEi :
The time interval between dates at which interest is paid and added to the amount of an investment or loan. Designates frequency of compounding.
Compounding, Continuous
AACEi :
(1) A compound interest situation in which the compounding period is zero and the number of periods infinitely great. A mathematical concept that is practical for dealing with frequent compounding and small interest rates.
(2) A mathematical procedure for evaluating compound interest factors based on a continuous interest function rather than discrete interest periods.
Concept Definition Document
AACEi :
A document describing the concept selected for development and the results of investigating alternative system concepts. It is used to derive the system specifications and the statement of work. Syn.: System Concept Document.
Concept Phase
AACEi :
First phase of a project in which need is examined, alternatives are assessed, the goals and objectives of the project are established and a sponsor is identified.
APM :
Concept is the first phase in the project or programme life cycle. During this phase the need, opportunity or problem is confirmed, the overall feasibility of the work is considered and a preferred solution identified.
Conceptual Estimate
AACEi :
An estimate generally prepared based on very limited information.
Conceptual Schedule
AACEi :
Similar to a proposal schedule except it is usually time-scaled and developed from the abstract or conceptual design of the project. Used primarily to give the client a general idea of the project scope and on overview of activities.
Concern
AACEi :
In TCM risk management, something that worries stakeholders because it may give rise to a risk event or condition.
Concurrency
AACEi :
The method of counting concurrent delay events based purely on contemporaneous occurrence without regard to CPM principles.
Concurrent Activities
AACEi :
Independent activities that may be, or are performed at the same time (fully or partially).
Concurrent Delays
AACEi :
(1) Two or more delays that take place or overlap during the same period, either of which occurring alone would have affected the ultimate completion date. In practice, it can be difficult to apportion damages when the concurrent delays are due to the owner and contractor respectively.
(2) Concurrent delays occur when there are two or more independent causes of delay during the same time period. The “same” time period from which concurrency is measured, however, is not always literally within the exact period of time. For delays to be considered concurrent, most courts do not require that the period of concurrent delay precisely match. The period of “concurrency” of the delays can be related by circumstances, even though the circumstances may not have occurred during exactly the same time of period. [10]
(3) True concurrent delay is the occurrence of two or more delay events at the same time, one an employer risk event, the other a contractor risk event and the effects of which are felt at the same time. The term ‘concurrent delay’ is often used to describe the situation where two or more delay events arise at different times, but the effects of them are felt (in whole or in part) at the same time. To avoid confusion, this is more correctly termed the ‘concurrent effect’ of sequential delay events. [12]
(4) Concurrent delay occurs when both the owner and contractor delay the project or when either party delays the project during an excusable but non-compensable delay (e.g., abnormal weather). The delays need not occur simultaneously but can be on two parallel critical path chains.
(5) The condition where another delay-activity independent of the subject delay is affecting the ultimate completion of the chain of activities.
Concurrent Engineering
PCI :
The systematic approach to the simultaneous, integrated design of products and their related processes, such as manufacturing, testing and supporting.
Condition (Risk Condition)
AACEi :
Any specific identifiable circumstance that might affect the outcome of the project.
Conditional Branching
AACEi :
Schedule analysis that allows for changes in schedule logic and/or durations depending on the occurrence of risk events or conditions.
Conditional Risk
AACEi :
Risk that occurs under certain conditions or is accepted provided that certain conditions are met.
Conduct Procurement
PMI :
The process of obtaining seller responses, selecting a seller, and awarding a contract.
Confidence Interval
AACEi :
The probability that a result will be within a range.
Confidence Level
AACEi :
The probability:
1) That results will be equal to or more favorable than the amount estimated or quoted; or
2) That the decision made will achieve the desired results; or
3) That the stated conclusion is true. Note: Confidence level may also be expressed as "equal to or less favorable". If that is the case, it should so be noted. Without such a note, the definition shown is assumed.
Configuration
AACEi :
A collection of an item's descriptive and governing characteristics, which can be expressed:
1) In functional terms, i.e. what performance the item is expected to achieve; and
2) In physical terms, i.e. what the item should look like and consist of when it is completed.
APM :
Functional and physical characteristics of a product as defined in its specification.
PCI :
The technical description needed to build, test, accept, operate install, maintain and support a system.
Configuration Control
AACEi :
A system of procedures that monitors emerging project scope against the scope baseline. Requires documentation and management approval on any change to the baseline.
Configuration Item
PCI :
A part a of configuration that has a set function and is designated for configuration management.
Configuration Librarian
PCI :
Responsible for administering configuration management. The configuration librarian may be on a project team or have system responsibilities rather than project responsibilities.
Configuration Management
AACEi :
Technical and administrative activities concerned with the creation, maintenance and controlled change of configuration throughout the life of the product. Configuration management is an integral part of life-cycle management.
APM :
Configuration management encompasses the administrative activities concerned with the creation, maintenance, controlled change and quality control of the scope of work.
PMI :
A subsystem of the overall project management system. It is a collection of formal documented procedures used to apply technical and administrative direction and surveillance to:identify and document the functional and physical characteristics of a product, result, service, or component; control any changes to such characteristics; record and report each change and its implementation status; and support the audit of the products, results, or components to verify conformance to requirements. It includes the documentation, tracking systems, and defined approval levels necessary for authorizing and controlling changes."
PCI :
The process of defining the configuration items in a system, controlling the release and change of those items throughout the project, recording and reporting the status of configuration items, and verifying the completeness of configuration items.
Conflict
AACEi :
Two or more parties having differing interests or perspectives that require resolution to achieve project goals. The state that exists when two groups have goals that will affect each other differently.
Conflict In Plans And Specifications
AACEi :
Statements or meanings in the contract documents (including drawings and specifications) that cannot be reconciled by reasonable interpretation on the part of the contractor and which may require the owner to provide an interpretation between alternatives.
Conflict Management
AACEi :
Handling of conflicts between project participants or groups in order to create optimal project results.
APM :
The process of identifying and addressing differences that, if left unresolved, could affect objectives.
PMI :
Handling, controlling, and guiding a conflictual situation to achieve a resolution.
PCI :
The ability to manage conflict effectively.
Conformance
PMI :
Within the quality management system, conformance is a general concept of delivering results that fall within the limits that define acceptable variation for a quality requirement.
Conformance Work
PMI :
In the cost of quality framework, conformance work is done to compensate for imperfections that prevent organizations from completing planned activities correctly as essential first-time work. Conformance work consists of actions that are related to prevention and inspection.
Consent Of Surety
AACEi :
An acknowledgement by a surety that its bond, given in connection with a contract, continues to apply to the contract as modified; or, at the end of a contract, permission from the surety to release all retainage to the contractor.
Consequence
AACEi :
In risk management, the impact or effect of a risk event or condition. Syn.: Effect; Impact.
Constant Basket
AACEi :
A set of goods and services with quantities fixed in relation to a given time period, used for computing composite price indexes.
Constant Basket Price Index
AACEi :
A price index which measures price changes by comparing the expenditures necessary to provide the same set of goods and services at different points in time.
Constant Dollars
AACEi :
Dollars of uniform purchasing power exclusive of general inflation or deflation. Constant dollars are tied to a reference year. Syn.: Real Dollars.
Constant Utility Price Index
AACEi :
A composite price index which measures price changes by comparing the expenditures necessary to provide substantially equivalent sets of goods and services at different points in time.
Constraint
AACEi :
(1) In planning and scheduling, any external factor that affects when an activity can be scheduled. A restriction imposed on the start, finish or duration of an activity. The external factor may be resources, such as labor, cost or equipment, or, it can be a physical event that must be completed prior to the activity being restrained. Constraints are used to reflect project requirements more accurately. Examples of date constraints are: Start-no-earlier-than, finish-no-later-than, mandatory start, and as-late-as-possible.
(2) In decision and risk management, something that limits the potential achievement of objectives.
PMI :
A limiting factor that affects the execution of a project, program, portfolio, or process.
PCI :
Applicable restrictions that will affect the scope of the project.
Constraint Date
AACEi :
Syn.: Plug Date.
Constructability
AACEi :
(1) A system (process) for achieving optimum integration of construction knowledge in the construction process, balancing various project and environmental constraints to achieve maximization of project goals and performance.
(2) Derived from early detailed construction planning that allows engineering and procurement to be scheduled to support construction in accordance with the overall optimized project schedule.
(3) The extent to which the design of a structure or system facilitates ease of construction, subject to the overall requirements for the completed form. The optimum use of construction knowledge and experience in planning, engineering, procurement and field operations to achieve the overall objective.
Construction Cost
AACEi :
The sum of all costs, direct and indirect, inherent in converting a design plan for material and equipment into a project ready for start-up, but not necessarily in production operation; the sum of field labor, supervision, administration, tools, field office expense, materials, equipment, and subcontracts.
Construction Management
AACEi :
(1) Project management as applied to construction.
(2) A professional service that applies to effective management techniques to the planning, design, and construction of a project from inception to completion for the purpose of controlling time, cost, and quality.
Construction Progress
AACEi :
Construction progress is monitored and reported as percent complete. Actual work units completed are measured against the planned work units for each applicable account in the bill of materials or quantities. Usually reported against individual accounts by area and total project, and summarized by area and total project.
Construction Progress Report
AACEi :
A report that informs management of overall construction progress (physical percent complete), costs, performance and manpower at a specific reporting cut-off date. Typically includes major accomplishments, objectives for the upcoming report period, areas of concern, and other pertinent information necessary for management and control.
Constructive Acceleration
AACEi :
An owner’s action or inaction, in absence of a specific direction to accelerate, that results in the contractor accelerating its work to maintain scheduled completion date(s). Case law has identified five elements normally required to establish a claim for constructive acceleration and include:
1) An excusable delay must exist;
2) Timely notice of the delay and a proper request for a time extension must have been given;
3) The time extension must have been postponed or refused;
4) Owner must have ordered (either by coercion, direction or some other manner) the project completed within its original performance period; and
5) Contractor must actually accelerate its performance, thereby incurring excess costs.
Constructive Change
AACEi :
An owner's action or inaction that impacts the contractor's working conditions and constitutes an unauthorized modification of contract intent.
Constructive Delay
AACEi :
An act or omission by the owner or its agent, which in fact delays completion of the work.
Consumable Resource
AACEi :
A type of resource that remains available until consumed (for example, a material).
APM :
A type or resource that only remains available until consumed (for example a material).
Consumables
AACEi :
Supplies and materials used up during construction. Includes utilities, fuels and lubricants, welding supplies, worker's supplies, medical supplies, etc.
Consumers Price Index (CPI)
AACEi :
A measure of time-to-time fluctuations in the price of a quantitatively constant market basket of goods and services, selected as representative of a special level of living.
Context
APM :
A collective term for the governance and setting of a project, programme or portfolio.
Context Diagram
PMI :
A visual depiction of the product scope showing a business system (process, equipment, computer system, etc.), and how people and other systems (actors) interact with it.
Contigency Allowance
AACEi :
1) In earned value management (based upon the ANSI EIA 748 Standard), an amount held outside the performance measurement baseline for owner level cost reserve for the management of project uncertainties is referred to as contingency.
PMI :
A provision in the project management plan to mitigate cost and/or schedule risk. Often used with a modifier (e.g., management reserve, contingency reserve) to provide further detail on what types of risk are meant to be mitigated.
Contigency Reserve
PMI :
Budget within the cost baseline or performance measurement baseline that is allocated for identified risks that are accepted and for which contingent or mitigating responses are developed.
Contingency
AACEi :
(1) An amount added to an estimate to allow for items, conditions, or events for which the state, occurrence, or effect is uncertain and that experience shows will likely result, in aggregate, in additional costs. Typically estimated using statistical analysis or judgment based on past asset or project experience.
Contingency usually excludes:
1) Major scope changes such as changes in end product specification, capacities, building sizes, and location of the asset or project;
2) Extraordinary events such as major strikes and natural disasters;
3) Management reserves; and
4) Escalation and currency effects. Some of the items, conditions, or events for which the state, occurrence, and/or effect is uncertain include, but are not limited to, planning and estimating errors and omissions, minor price fluctuations (other than general escalation), design developments and changes within the scope, and variations in market and environmental conditions. Contingency is generally included in most estimates, and is expected to be expended.
APM :
Resource set aside for responding to identified risks.
PMI :
An event or occurrence that could affect the execution of the project that may be accounted for with a reserve.
PCI :
A Contingency is the planned allotment of time and cost for unforeseeable elements with a project. Including contingencies will increase the confidence of the overall project.
Contingency Plan
AACEi :
A risk response plan made to address identified residual risks if they occur. Syn.: Fallback Plan.
PCI :
The development of a management plan that uses alternative strategies to ensure project success if specified risk events occur.
Contingent Response Strategies
PMI :
Responses provided which may be used in the event that a specific trigger occurs.
Contingent Risk Response
AACEi :
A planned alternative response to a risk that will be taken only in defined circumstances.
Contract
AACEi :
Legal agreement between two or more parties, which may be of the types enumerated below:
APM :
An agreement made between two or more parties that creates legally binding obligations between them. The contract sets out those obligations and the actions can be taken if they are not met.
PMI :
A contract is a mutually binding agreement that obligates the seller to provide the specified product or service or result and obligates the buyer to pay for it.
PCI :
A mutually binding agreement in which the contractor is obligated to provide services or products and the buyer is obligated to provide payment for them. Contracts fall into three categories: fixed price, cost reimbursable or unit price.
Contract "Read As A Whole"
AACEi :
Reading an entire contract document, instead of reading each clause in the contract in isolation. If a clause is ambiguous and can be interpreted in more than one way, the meaning that conforms to the rest of the document is usually the accepted meaning.
Contract Budget Baseline (CBB)
AACEi :
In earned value management according to the ANSI EIA 748 standard, the budget for the project at the total contract level. The CBB reconciles with the project authorization documents from the owner. The CBB plus fee is the total contract value. CBB = Performance Measurement Baseline (PMB) + Management Reserve (MR) unless an Over Target Baseline (OTB) has been implemented.
PCI :
The negotiated contract cost value plus the estimated value of authorized but unpriced work.
Contract Change
AACEi :
An authorized modification to terms of a contract. May involve, but is not limited to:
1) A change in the volume or conditions of the work involved;
2) The number of units to be produced;
3) The quality of the work or units;
4) The time for delivery; and/or
5) The consequent cost involved.
Contract Change Control System
PMI :
The system used to collect, track, adjudicate, and communicate changes to a contract.
Contract Close-Out
PCI :
Settlement of a contract.
Contract Completion Date
AACEi :
The date established in the contract for completion of all or specified portions of the work. This date may be expressed as a calendar date or as a number of days after the date for commencement of the contract time is issued.
Contract Data Requirement List (CDRL)
PCI :
An element of the contract that specifies the data submittal requirements.
Contract Dates
AACEi :
The start, intermediate, or final dates specified in the contract that impact the project schedule.
Contract Documents
AACEi :
The agreement, addenda (which pertain to the contract documents), contractor's bid (including documentation accompanying the bid and any post-bid documentation submitted prior to the notice of award) when attached as an exhibit to the agreement, the bonds, the general conditions, the supplementary conditions, the specifications and the drawings as the same are more specifically identified in the agreement, together with all amendments, modifications and supplements issued pursuant to the general conditions on or after the effective date of the agreement.
Contract Master Schedule
AACEi :
The management summary schedule that shows the overall plan for the total contract.
Contract Performance Report (CPR)
PCI :
The Contract Performance Report (CPR) presents the cost and schedule data for the current period as well as in a cumulative format. Costs are organised by WBS element at a level pre-determined by the HHS IT Investment team. Format 5, Variance Narrative, is a problem analysis and variance-oriented report. It provides explanations for cost and schedule variances that have exceeded thresholds. It provides a written explanation as to why the variance occurred, as well as written descriptions on how the contractor plans to resolve the cause of the variance. Examples of the CPR Forms 1-5 are provided in the CPIC guide.
Contract Plan
AACEi :
The conditions, methods, schedule, etc. for carrying out the work of the contract as agreed between the parties at the time of signing the contract.
Contract Price
AACEi :
The monies payable by the owner to the contractor under the contract documents as stated in the agreement.
Contract Target Cost (CTC)
PCI :
The negotiated costs for the original definite contract and all contractual changes that have been definitized, but excluding the estimated cost of any authorized, unpriced changes. The CTC equals the value of the BAC plus management or contingency reserve.
Contract Target Price (CTP)
PCI :
The negotiated estimated costs plus profit or fee.
Contract Time
AACEi :
The date when the contract time commences to run and on which the contractor shall start to perform the contractor's obligations under the contract documents.
Contract Work Breakdown Structure (CWBS)
PCI :
A customer-prepared breakout or subdivision of a project typically down to level three which subdivides the investment into all its major hardware, software, and service elements, integrates the customer and contractor effort, provides a framework for the planning, control, and reporting.
Contract, Cost Plus Contracts
AACEi :
In cost plus contracts the contractor agrees to furnish to the client services and material at actual cost, plus an agreed upon fee for these services. This type of contract is employed most often when the scope of services to be provided is not well defined.
Contract, Cost Plus Contracts, Cost Plus Fixed Fee
AACEi :
The client pays costs as defined in the contract document. Burden on reimbursable technical labor cost is considered in this case as part of cost. In addition to the costs and burden, the client also pays a fixed amount as the contractor's "fee".
Contract, Cost Plus Contracts, Cost Plus Fixed Sum
AACEi :
The client will pay costs defined by contract plus a fixed sum which will cover "non-reimbursable" costs and provide for a fee. This type of contract is used in lieu of a cost plus fixed fee contract where the client wishes to have the contractor assume some of the risk for items which would be reimbursable under a cost plus fixed fee type of contract.
Contract, Cost Plus Contracts, Cost Plus Percentage Burden And Fee
AACEi :
The client will pay all costs as defined in the terms of the contract, plus "burden and fee" at a specified percent of the labor costs which the client is paying for directly. This type of contract generally is used for engineering services. In contracts with some governmental agencies, burden items are included in indirect cost.
Contract, Cost Plus Contracts, Cost Plus Percentage Fee
AACEi :
The client pays all costs, plus a percentage for the use of the contractor's organization.
Contract, Fixed Price Contracts
AACEi :
Fixed price types of contract are ones wherein a contractor agrees to furnish services and material at a specified price, possibly with a mutually agreed upon escalation clause. This type of contract is most often employed when the scope of services to be provided is well defined.
Contract, Fixed Price Contracts, Bonus-Penalty
AACEi :
A special contractual arrangement usually between a client and a contractor wherein the contractor is guaranteed a bonus, usually a fixed sum of money, for each day the project is completed ahead of a specified schedule and/or below a specified cost, and agrees to pay a similar penalty for each day of completion after the schedule date or over a specified cost up to a specified maximum either way. The penalty situation is sometimes referred to as liquidated damages.
Contract, Fixed Price Contracts, Guaranteed Maximum (Target Price)
AACEi :
A contractor agrees to perform all services as defined in the contract document guaranteeing that the total cost to the client will not exceed a stipulated maximum figure. Quite often, these types of contracts will contain special share-of-the-saving arrangements to provide incentive to the contractor to minimize costs below the stipulated maximum.
Contract, Fixed Price Contracts, Lump Sum
AACEi :
Contractor agrees to perform all services as specified by the contract for a fixed amount. A variation of this type may include a turn-key arrangement where the contractor guarantees quality, quantity and yield on a process plant or other installation.
Contract, Fixed Price Contracts, Unit Price
AACEi :
Contractor will be paid at an agreed upon unit rate for services performed. For example, technical work-hours will be paid for at the unit price agreed upon. Often field work is assigned to a subcontractor by the prime contractor on a unit price basis.
Contractor
AACEi :
(1) A business entity that enters into contracts to provide goods or services to another party.
(2) A person or organization that undertakes responsibility for the performance of a contract. One that agrees to furnish materials or perform services at a specified price.
Control
AACEi :
(1) Management action, either preplanned to achieve the desired result or taken as a corrective measure prompted by the monitoring process.
(2) To take timely corrective action. Control occurs only if monitoring and forecasting activities indicate an undesirable final result is likely to occur and that a different final result is possible.
(3) Process of comparing actual performance with planned performance, analyzing the differences, and taking the appropriate corrective action.
APM :
Tracking performance against agreed plans and taking the corrective action required to meet defined objectives.
PMI :
Comparing actual performance with planned performance, analyzing variances, assessing trends to effect process improvements, evaluating possible alternatives, and recommending appropriate corrective action as needed.
PCI :
Control is the process of comparing actual performance with planned performance, analyzing the differences, and taking the appropriate corrective action.
Control Account (CA)
AACEi :
A management control point where earned value measurement takes place. It is the place where scope, schedule and budget, are integrated at the organizational level responsible for day to day management of a segment of the project. Syn.: Cost Account.
PMI :
A management control point where scope, budget, actual cost, and schedule are integrated and compared to earned value for performance measurement.
Control Account Manager (CAM)
AACEi :
The single person responsible for management of the scope, schedule, and budget of the control account. The CAM has control either through delegation or supervisory responsibility for all of the staff performing the control account work.
PCI :
A member of the organization responsible for cost account performance, and for the management of resources to accomplish such tasks.
Control Account Plan (CAP)
PCI :
Control Account Plans (CAPs) document the underlying work packages and provide the CAM with a source to evaluate his or her BCWS, ACWP, and BCWP (Earned Value) of each for the CAM's Control Accounts.
Control And Coordination
AACEi :
Control is the process of developing targets and plans; measuring actual performance and comparing it against planned performance and taking the steps to correct the situation. Coordination is the act of ensuring that work is being carried out in different organizations and places to fit together effectively in time, content and cost in order to achieve the project objectives effectively.
PCI :
Control is the process of developing targets and plans; measuring actual performance and comparing it against planned performance and taking the steps to correct the situation. Coordination is the act of ensuring that work is being carried out in different organizations and places to fit together effectively in time, content and cost in order to achieve the project objectives effectively.
Control Baseline
AACEi :
Syn.: Baseline.
Control Chart
PMI :
A graphic display of process data over time and against established control limits, which has a centerline that assists in detecting a trend of plotted values toward either control limit.
PCI :
Control charts display the results, over time, of a process. They are used to determine if the process is in need of adjustment.
Control Communication
PMI :
The process of monitoring and controlling communications throughout the entire project life cycle to ensure the information needs of the project stakeholders are met.
Control Cost
AACEi :
The process of monitoring the status of the project to update the project costs and managing changes to the cost baseline.
Control Gate
AACEi :
A major project milestone at which the project client has the opportunity to exercise a ‘go/no-go’ decision upon continuation into the succeeding phase.
Control Limits
PMI :
The area composed of three standard deviations on either side of the centerline or mean of a normal distribution of data plotted on a control chart, which reflects the expected variation in the data. See also specification limits.
Control Procurement
PMI :
The process of managing procurement relationships, monitoring contract performance, and making changes and corrections as appropriate.
Control Schedule
PMI :
The process of monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan.
Control Scope
PMI :
The process of monitoring the status of the project and product scope and managing changes to the scope baseline.
Control Stakeholder Engagement
PMI :
The process of monitoring overall project stakeholder relationships and adjusting strategies and plans for engaging stakeholders.
Controlling Path
AACEi :
An alternate term used in place of ‘as-built critical path’ in order to technically preserve the use of the term critical path to denote only to activity paths identified by float calculation using early and late dates. By definition, as-built activities do not have early and late dates.
Controlling Relationship
AACEi :
In planning and scheduling, the predecessor activity logic tie to an activity, with multiple predecessors, which “controls” or “drives” that activity and establishes it’s latest early finish.
PCI :
The early dates of an activity is controlled either by a target date on the activity or, more normally, by one of the predecessor relationships. In the latter case, the relationship is called the controlling relationship.
Coordinated Matrix
PCI :
An organizational structure where the project leader reports to the functional manager and doesn’t have authority over team members from other departments.
Correction Period
AACEi :
The period of time within which the contractor shall promptly, without cost to the owner and in accordance with the owner's written instructions, either correct defective work, or if it has been rejected by the owner, remove it from the site and replace it with non-defective work, pursuant to the general conditions.
Corrective Action
PMI :
An intentional activity that realigns the performance of the project work with the project management plan.
PCI :
Changes made to bring future project performance into the plan.
Corrective Action Plan
PCI :
Corrective Action Plans are documents that allow Investment Managers to define the strategy that will be employed to improve the performance of their investments.
Correlation
AACEi :
The measure of the relationship between two or more quantitative elements.
Cost
AACEi :
In project control and accounting, it is the amount measured in money, cash expended or liability incurred, in consideration of goods and/or services received. From a total cost management perspective, cost may include any investment of resources in strategic assets including time, monetary, human, and physical resources.
PCI :
Cost can be divided into internal and external expenses. External costs can be controlled by contracts and budgets for each phase of a project and for each deliverable or work product. Internal cost is the cost of project resources.
Cost Account
AACEi :
Syn.: Control Account (CA).
PCI :
A cost account is usually defined as the intersection of the program's work breakdown structure (WBS) and organizational breakdown structure (OBS). In effect, each cost account defines what work is to be performed and who will perform it. Cost accounts are the focal point for the integration of scope, cost, and schedule. Another term for Cost Account is Control Account.
Cost Account Manager (CAM)
PCI :
A member of a functional organization responsible for cost account performance, and for the management of resources to accomplish such tasks.
Cost Account Plan (CAP)
PCI :
The management control unit in which earned value performance measurement takes place.
Cost Accounting
AACEi :
The historical reporting of actual and/or committed disbursements (costs and expenditures) on a project. Costs are denoted and segregated within cost codes that are defined in a chart of accounts. In project control practice, cost accounting provides the measure of cost commitment and/or expenditure that can be compared to the measure of physical completion (or earned value) of an account.
Cost Aggregation
PMI :
Summing the lower-level cost estimates associated with the various work packages for a given level within the project’s WBS or for a given cost control account.
Cost Analysis
AACEi :
A historical and/or predictive method of ascertaining for what purpose expenditures on a project were made and utilizing this information to project the cost of a project as well as costs of future projects. The analysis may also include application of escalation, cost differentials between various localities, types of buildings, types of projects, and time of year.
Cost Approach
AACEi :
One of the three approaches in the appraisal process. Underlying the theory of the cost approach is the principle of substitution, which suggests that no rational person will pay more for a property than the amount with which he/she can obtain, by purchase of a site and construction of a building without undue delay, a property of equal desirability and utility.
Cost At Completion (CAC)
AACEi :
The amount an activity or group of activities will cost when it has been completed. It is the sum of the cost expended to date and the estimated cost to complete.
Cost Avoidance
AACEi :
An action taken in the present designed to decrease costs in the future.
Cost Baseline
AACEi :
A time-phased budget used to measure and monitor cost performance. It is developed by summing estimated costs by period and is usually displayed in the form of an S-curve.
PMI :
The approved version of the time-phased project budget, excluding any management reserves, which can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
Cost Breakdown Structure (CBS)
AACEi :
1) A hierarchical structure that divides budgeted resources into elements of costs, typically labor, materials and other direct costs. The lowest level, when assigned responsibility, typically defines a cost center.
2) Hierarchical breakdown of a project into cost elements or cost categories.
PCI :
A hierarchical structure that rolls budgeted resources into elements of costs, typically labor, materials and other direct costs.
Cost Budgeting
PCI :
Allocating cost estimates to individual project components.
Cost Category
AACEi :
A specifically defined division in a system of classification for estimated and/or expended money for which costs are to be summarized.
Cost Center
AACEi :
The smallest unit of activity or area of responsibility against which costs are accumulated; defined sections in the corporate system, representing units of responsibility as well as accounting units.
Cost Codes
AACEi :
Codes allocated to items or activities that allow costs to be consolidated according to the elements of the coding structure.
PCI :
Code assigned to activities that allow costs to be consolidated according to the elements of a code structure.
Cost Control
AACEi :
The application of procedures to monitor expenditures and performance against progress of projects or manufacturing operations; to measure variance from authorized budgets and allow effective action to be taken to achieve minimum costs.
Cost Control Point
PCI :
The point within a program at which costs are entered and controlled. Frequently, the cost control point for a program is either the cost account or the work package.
Cost Control System
AACEi :
Any system of managing costs within the bounds of budgets or standards based upon work actually performed. Cost control is typically performed at designated levels in the work breakdown structure.
PCI :
Any system of keeping costs within the bounds of budgets or standards based upon work actually performed. Cost Control is typically a level in the budget element breakdown structure.
Cost Curve
AACEi :
A graph that plots cumulative cost (e.g., planned, expended, incurred, etc) against a time scale.
PCI :
A graph plotted against a horizontal time scale and cumulative cost vertical scale.
Cost Distribution
AACEi :
Distribution or allocation of overhead (indirect) costs on some logical basis, e.g., the time or cost of all associated direct cost activities.
Cost Element
AACEi :
In earned value, a basic until of planning such as: labor, travel, material, subcontracts, and other direct costs as applicable.
Cost Engineer
AACEi :
An engineer whose judgment and experience are utilized in the application of scientific principles and techniques to problems of estimation; cost control; business planning and management science; profitability analysis; project management; and planning and scheduling.
Cost Estimate
AACEi :
A compilation of all the probable costs of the elements of a project or effort included within an agreed upon scope.
PMI :
Estimate Costs: The process of developing an approximation of the monetary resources needed to complete project activities.
Cost Estimate Category
AACEi :
A compilation of all the probable costs of the elements of a project or effort included within an agreed upon scope.
Cost Estimate Class
AACEi :
Syn.: Cost Eatimate Category; Cost Estimate Classification System; Cost Estimate Type.
Cost Estimate Classification System
AACEi :
There are numerous characteristics that can be used to categorize project cost estimate types. Some of these characteristics are: level of project definition, end usage of the estimate, estimating methodology, and the effort and time needed to prepare the estimate. AACE recommends that the primary characteristic used to define the classification category is the level of project. The other characteristics are considered secondary.
The level of project definition defines maturity, or the extent and types of input information available to the estimating process. Such inputs include project scope definition, requirements documents, specifications, project plans, drawings, calculations, lessons learned from past projects, reconnaissance data, and other deliverables and information that must be developed to define the project. Each industry will have a typical set of defining deliverables that are used to support the type of estimates used in that industry. The set of deliverables becomes more definitive and complete as the level of project definition (e.g., project engineering) progresses.
For projects, the estimate class designations that follow below are labeled Class 1, 2, 3, 4, and 5. A Class 5 estimate is based upon the lowest level of project definition, and a Class 1 estimate is closest to full project definition and maturity. This “countdown” approach considers that estimating is a process whereby successive estimates are prepared until a final estimate closes the process.
Cost Estimate Classification System, Class 1 Estimate
AACEi :
(Typical level of project definition required: 65% to 100% of full project definition.)Class 1 estimates are generally prepared for discrete parts or sections of the total project rather than for the entire project. The parts of the project estimated at this level of detail will typically be used by subcontractors for bids, or by owners for check estimates. The updated estimate is often referred to as the current control estimate and becomes the new baseline for cost/schedule control of the project. Class 1 estimates may be prepared for parts of the project to comprise a fair price estimate or bid check estimate to compare against a contractor’s or vendor’s bid estimate, or to evaluate/dispute claims or change orders.
Cost Estimate Classification System, Class 2 Estimate
AACEi :
(Typical level of project definition required: 30% to 75% of full project definition.)Class 2 estimates are generally prepared to form a detailed control baseline against which all project work is monitored in terms of cost and progress control. For contractors, this class of estimate is often used as the “bid” estimate to establish contract value.
Cost Estimate Classification System, Class 3 Estimate
AACEi :
(Typical level of project definition required: 10% to 40% of full project definition.)Class 3 estimates are generally prepared to form the basis for budget authorization, appropriation, and/or funding. Class 3 estimates are typically prepared to support full project funding requests, and become the first of the project phase “control estimate” against which all actual costs and resources will be monitored for variations to the budget. They are used as the project budget until replaced by more detailed estimates. In many owner organizations, a Class 3 estimate may be the last estimate required and could well form the only basis for cost/schedule control.
Cost Estimate Classification System, Class 4 Estimate
AACEi :
(Typical level of project definition required: 1% to 15% of full project definition.)Class 4 estimates are generally prepared based on limited information and subsequently have fairly wide accuracy ranges. They are typically used for project screening, determination of feasibility, concept evaluation, and preliminary (but generally not final) budget approval. Class 4 estimates are prepared for a number of purposes, such as but not limited to, detailed strategic planning, business development, project screening at more developed stages, alternative scheme analysis, confirmation of economic and/or technical feasibility, and preliminary budget approval or approval to proceed to next stage.
Cost Estimate Classification System, Class 5 Estimate
AACEi :
(Typical level of project definition required: >0% to 2% of full project definition.)Class 5 estimates are generally prepared based on very limited information, and subsequently have wide accuracy ranges. As such, some companies and organizations have elected to determine that due to the inherent inaccuracies, such estimates cannot be classified in a conventional and systemic manner. Class 5 estimates, due to the requirements of end use, may be prepared within a very limited amount of time and with little effort expended. Class 5 estimates are prepared for any number of strategic business planning purposes, such as but not limited to market studies, assessment of initial viability, evaluation of alternate schemes, project screening, project location studies, evaluation of resource needs and budgeting, long-range capital planning, etc.
Cost Estimate Resource
AACEi :
Cost estimate of physical resources needed to perform a specific construction activity which in turn drives an overall unit price. Typically includes labor resources, material resources, equipment resources, subcontractor costs and other costs. It is typically abbreviated Lmeso.
Cost Estimate Type
AACEi :
Syn.: Cost Estimate Category; Cost Estimate Class; Cost Estimate Classification System.
Cost Estimating
AACEi :
Cost estimating is the predictive process used to quantify, cost, and price the resources required by the scope of an investment option, activity, or project. Cost estimating is a process used to predict uncertain future costs. In that regard, a goal of cost estimating is to minimize the uncertainty of the estimate given the level and quality of scope definition. The outcome of cost estimating ideally includes both an expected cost and a probabilistic cost distribution. As a predictive process, historical reference cost data (where applicable) improve the reliability of cost estimating. Cost estimating, by providing the basis for budgets, also shares a goal with cost control of maximizing the probability of the actual cost outcome being the same as predicted.
PCI :
The process of predicting the costs of a project.
Cost Estimating Relationship (CER)
AACEi :
In estimating, an algorithm or formula that is used to perform the costing operation. CERs show some resource (e.g., cost, quantity, or time) as a function of one or more parameters that quantify scope, execution strategies, or other defining elements. A CER may be formulated in a manner that, in addition to providing the most likely resource value, also provides a probability distribution for the resource value.
Cost Estimator (Project)
AACEi :
Project cost estimators predict the cost of a project for a defined scope, to be completed at a defined location and point of time in the future. Cost estimators assist in the economic evaluation of potential projects by supporting the development of project budgets, project resource requirements, and value engineering. They also support project control by providing input to the cost control baseline. Estimators collect and analyze data on all of the factors that can affect project costs such as: materials, equipment, labor, location, duration of the project, and other project requirements.
Cost Incurred
PCI :
Costs identified through the use of the accrued method of accounting or costs actually paid. Costs include direct labor, direct materials, and all allowable indirect costs.
Cost Index
AACEi :
A number which relates the cost of an item at a specific time to the corresponding cost at some specified prior time.
Cost Loading
AACEi :
In planning and scheduling, assigning an estimated or actual cost to an activity. The estimated cost may be only direct costs, or may include indirect costs. However, the CPM (Critical Path Method) must be developed using only one cost loading method.
Cost Management
PMI :
A component of a project or program management plan that describes how costs will be planned, structured, and controlled.
PCI :
The effective financial control of the project through evaluating, estimating, budgeting, monitoring, analyzing, forecasting and reporting the cost information.
Cost Of Capital
AACEi :
A term, usually used in capital budgeting, to express as an interest rate percentage the overall estimated cost of investment capital at a given point in time, including both equity and borrowed funds.
Cost Of Living Index
AACEi :
In modern usage, a price index based on a constant utility concept as opposed to a constant basket concept.
Cost Of Lost Business Advantage
AACEi :
The cost associated with loss of repeat business and/or the loss of business due to required resources and costs.
Cost Of Money
PCI :
A form of indirect cost incurred by investing capital in facilities employed on government contracts.
Cost Of Ownership
AACEi :
The cost of operations, maintenance, follow-on logistical support, and end item and associated support systems.
Cost Of Quality
AACEi :
(1) Consists of the sum of those costs associated with:
(a) Cost of quality conformance;
(b) Cost of quality nonconformance; and
(c) Cost of lost business advantage.
(2) Cost incurred or expended to ensure quality, including those associated with the cost of conformance and nonconformance.
PMI :
A method of determining the costs incurred to ensure quality. Prevention and appraisal costs (cost of conformance) include costs for quality planning, Quality Control (QC), and quality assurance to ensure compliance to requirements (i.e., training, QC systems, etc.). Failure costs (cost of nonconformance) include costs to rework products, components, or processes that are non-compliant, costs of warranty work and waste, and loss of reputation.
PCI :
The cost of Quality Planning, Control, Assurance and Rework.
Cost Of Quality Conformance
AACEi :
The cost associated with the quality management activities of appraisal, training, and prevention.
Cost Of Quality Nonconformance
AACEi :
The cost associated with deviations involving rework and/or the provision of deliverables that are more than required.
Cost Overrun
PCI :
The amount by which a contractor exceeds or expects to exceed the estimated costs, and/or the final limitations (the ceiling) of a contract.
Cost Performance Index/Indicator (CPI)
AACEi :
The ratio of earned value to actual costs (CPI = BCWP/ACWP). A value greater than 1 indicates that costs are running under budget. A value less than 1 indicates that costs are running over budget. Often used to predict magnitude of a possible cost overrun by dividing it into the original cost estimate (original cost estimate/CPI = projected cost at completion).
PMI :
A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
PCI :
Ratio of work accomplished versus work cost incurred for a specified time period. The CPI is an efficiency rating for work accomplished for resources expended.
Cost Performance Report (CPR)
AACEi :
A common report used to report earned value management (EVM) information to an owner.
PCI :
A monthly cost report generated by the performing contractor to reflect cost and schedule status information for management.
Cost Plus Award Fee Contracts (CPAF)
PMI :
A category of contract that involves payments to the seller for all legitimate actual costs incurred for completed work, plus an award fee representing seller profit.
Cost Plus Fixed Fee Contracts (CPFF)
PMI :
A type of cost-reimbursable contract where the buyer reimburses the seller for the seller’s allowable costs (allowable costs are defined by the contract) plus a fixed amount of profit (fee).
PCI :
A type of contract where the buyer reimburses the seller for the seller’s allowable costs plus a fixed fee.
Cost Plus Incentive Fee Contracts (CPIF)
PMI :
A type of cost-reimbursable contract where the buyer reimburses the seller for the seller’s allowable costs (allowable costs are defined by the contract), and the seller earns its profit if it meets defined performance criteria.
PCI :
A type of Contract where the buyer reimburses the seller for the seller's allowable costs and the seller earns a profit if defined criteria are met.
Cost Schedule Status Report
PCI :
The low-end cost and schedule report generally imposed on smaller value contracts, not warranting full C/SCSC.
Cost To Complete
AACEi :
The amount that an in-progress activity or group of activities will cost to complete.
Cost Variance
AACEi :
The difference between the earned value and actual cost. Cost variance (CV) = budgeted cost of work performed (BCWP)-actual cost of work performed (ACWP). A negative cost variance indicates that the activity(ies) is running over budget.
PMI :
The amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual cost.
PCI :
The difference between the budgeted and actual cost of work performed.
Cost-Benefit Analysis
PMI :
A financial analysis tool used to determine the benefits provided by a project against its costs.
PCI :
The analysis of the potential costs and benefits of a project to allow comparison of the returns from alternative forms of investment.
Cost-Reimbursable Contract
PMI :
A type of contract involving payment to the seller for the seller’s actual costs, plus a fee typically representing seller’s profit. Cost-reimbursable contracts often include incentive clauses where, if the seller meets or exceeds selected project objectives, such as schedule targets or total cost, then the seller receives from the buyer an incentive or bonus payment.
PCI :
A category of contracts based on payments to a contractor for allowable estimated costs, normally requiring only a "best efforts" performance standard from the contractor. Risk for all growth over the estimated value rests with the project owner.
Cost/Schedule Control System Criteria (C/SCSC)
AACEi :
A standard method of earned value management used on US Government projects. C/SCSC combined time and cost measures to better measure performance in an integrated way. This standard was superseded by a government earned value management system (EVMS) standard.
PCI :
Thirty-five defined standards which have been applied against private contractor management control systems since 1967 in order to insure the government that cost reimbursable and incentive type contracts are managed properly.
Cost/Schedule Planning And Control Specification (C/SPCS)
PCI :
The United States Air Force initiative in the mid-1960's which later resulted in the C/SCSC.
Costing
AACEi :
(1) The application of cost and resources to a quantified scope.
(2) A process of determining actual costs from actual expenditures. The way costs are estimated and the way money is spent are rarely the same, making it necessary to analyze and redistribute actual expenditures to arrive at cost data that is useful for future estimating purposes.
Costing, Activity Based (ABC)
AACEi :
Costing in a way that the costs budgeted to an account truly represent all the resources consumed by the activity or item represented in the account.
CPM
AACEi :
Syn.: Critical Path Method (CPM).
Crash Costs
AACEi :
The cost of reducing an activity to its crash duration.
Crash Duration
AACEi :
When needing to shorten a network critical path, activities may be 'crashed'. This represents drastic action to reduce the duration of a critical activity and should only taken in exceptional circumstances due to a dramatic increase in resource consumption.
Crashing
AACEi :
Action to decrease the duration of an activity or project by increasing the expenditure of resources.
PMI :
A technique used to shorten the schedule duration for the least incremental cost by adding resources.
PCI :
The process of reducing the time it takes to complete an activity by adding resources.
Crew
AACEi :
A set of workers and work equipment designated to perform an activity.
Crew Hour
AACEi :
An hour of effort for a crew of workers. For example, if a crew has 2 workers, a crew hour includes 2 labor hours.
Crew Rate
AACEi :
Labor cost per crew hour for a given crew. The labor cost may include only wages or wages plus benefits, burdens, and other markups. The labor cost may also include an allowance for the costs of tools and equipment used by the crew -in performance of their work.
Criteria
PMI :
Standards, rules, or tests on which a judgment or decision can be based or by which a product, service, result, or process can be evaluated.
Critical Activity
AACEi :
An activity on the project’s critical path. A delay to a critical activity causes a corresponding delay in the completion of the project. Although some activities are “critical,” in the dictionary sense, without being on the critical path, this meaning is seldom used in the project context.
PMI :
Critical Path Activity: Any activity on the critical path in a project schedule.
PCI :
An activity is termed critical when it has zero or negative float.
Critical Chain
AACEi :
That set of tasks which determines the overall duration of a project, after considering resource capacity. It is typically regarded as the constraint or leverage point of a project.
APM :
A networking technique that identifies paths through a project based on resource dependencies, as well as technical dependencies.
Critical Chain Method
AACEi :
Differentiated from the critical path method, this project planning and management technique considers resources that constrain the work, not only the precedence of activities. The method determines the longest-duration sequence of resource-constrained activities through a project network—thus, the shortest-possible project duration—the critical chain. Algorithms for application of the method are both deterministic and stochastic. Time buffers are included to protect completion dates and provide adequate solutions, since contingency is removed from durations of individual activities.
PMI :
A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
Critical Element
AACEi :
A cost element or a profit element which, due to its potential variability, can change the bottom-line, either favorably or unfavorably, by an amount equal to or greater than its critical variance.
Critical Path
AACEi :
The longest continuous chain of activities be more than one path) which establishes the minimum overall project duration. A slippage or delay in completion of any activity by one time period will extend final completion correspondingly. The critical path by definition has no “float.”
APM :
A sequence of activities through a network diagram from start to finish, the sum of whose durations determines the overall duration. There may be more than one such path.
PMI :
The sequence of activities that represents the longest path through a project, which determines the shortest possible duration.
PCI :
Series of consecutive activities that represent the longest path through the project.
Critical Path Analysis
AACEi :
Procedure for calculating the critical path and floats in a network.
APM :
The procedure for calculating the critical path and floats in a network diagram.
Critical Path Method (CPM)
AACEi :
(1) Technique used to predict project duration by analyzing which sequence of activities has least amount of scheduling flexibility. Early dates are figured by a forward pass using a specific start date and late dates are figured by using a backward pass starting from a completion date.
(2) Network scheduling using activity durations and logic ties between activities to model the plan to execute the work. CPM scheduling is the method of choice for managing projects of long duration, complex technical integration, or the need to coordinate fast or early completion of the work. Syn.: CPM.
PMI :
A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
PCI :
The Critical Path Method (Calculate Schedule) is a modeling process that defines all the project's critical activities which must be completed on time. The Calc tool bar button on the Gantt and PERT (found in most GUI-based PM software) windows calculates the start and finish dates of activities in the project in two passes. The first pass calculates early start and finish dates from the earliest start date forward. The second pass calculates the late start and finish activities from the latest finish date backwards. The difference between the pairs of start and finish dates for each task is the float or slack time for the task (see FLOAT). Slack is the amount of time a task can be delayed without delaying the project completion date. A great advantage of this method is the fine-tuning that can be done to accelerate the project. Shorten various critical path activities, then check the schedule to see how it is affected by the changes. By experimenting in this manner, the optimal project schedule can be determined.
A technique used to predict project duration by analyzing which sequence of activities has the least amount of scheduling flexibility. Early dates are figured by a forward pass using a specific start date and late dates are figured by using a backward starting from a completion date.
Critical Relationship
AACEi :
A driving relationship between two critical activities, thus defining which activity influences the final completion of the project.
Critical Sequence
AACEi :
Sequence of activities having zero float after resource limits are taken into account in calculating float.
Critical Sequence Analysis
AACEi :
A process of calculating a critical sequence of activities while taking into account resource limits that reflects an activity's flexibility.
Critical Task
AACEi :
A task that must finish on time for the entire project to finish on time. If a critical task is delayed, the project completion date is also delayed. A critical task has zero slack time. A series of critical tasks make up the project’s critical path.
Critical Variance
AACEi :
A percentage of the bottom-line used to identify critical elements. The percentage is a function of the class of estimate (Class 1 or 2 vs. Class 3, 4, or 5) and the type of bottom-line (cost or profit). If necessary, the percentage can be increased to a maximum of twice its base value in order to reduce the number of qualifying elements to an acceptable number (typically 20 or so) in order to avoid introducing iatrogenic risk.
Criticality
AACEi :
A measure of the significance or impact of failure of a product, process, or service to meet established requirements.
APM :
Used in Monte Carlo analysis, the criticality index represents the percentage of calculations that resulted in the activity being placed on the critical path.
Criticality Index
AACEi :
Describes how often a particular task was on the critical path during the quantitative risk analysis (e.g., Monte Carlo computer simulation). Expressed as a factor between 0 and 1 or as a percentage. Tasks with a high criticality index appear more frequently on the critical path. When combined with the duration sensitivity, it determines the cruciality index.
PCI :
Used in risk analysis, the criticality index represents the percentage of simulation trails that resulted in the activity being placed on the critical path.
Cruciality
AACEi :
The degree that a change in a risk model element produces a change in the overall outcome (i.e., strong risk drivers have high cruciality). In schedule risk, cruciality of an activity increases with its criticality (i.e., sometimes referred to as the product of sensitivity and criticality).
Crude Materials
AACEi :
Includes products entering the market for the first time which have not been fabricated or manufactured but will be processed before becoming finished goods (e.g., steel scrap, wheat, raw cotton). Syn.: Raw Materials.
Current Cost Accounting (CCA)
AACEi :
a methodology prescribed by the Financial Accounting Board to compute and report financial activities in constant dollars.
Current Date Line
AACEi :
A vertical line in a Gantt chart, resource graph, or other charts with dates on one axis, indicating the current date.
Current Dollars
AACEi :
Dollars of purchasing power in which actual prices are stated, including inflation or deflation. In the absence of inflation or deflation, current dollars equal constant dollars.
Current Finish Date
AACEi :
The current estimate of the calendar date when an activity will be completed.
Current Period (Of A Given Price Index)
AACEi :
Period for which prices are compared to the base period prices.
Current Schedule
AACEi :
Schedule update, which reflects actual progress to date, plus forecast progress going forward and is accepted/used for monitoring and controlling the work.
Current Start Date
AACEi :
The current estimate of the calendar date when an activity will begin.
Current Status
AACEi :
In project control, a report that compares actual progress with planned progress as of the last reporting date.
Custom In The Industry
AACEi :
An established practice in a particular industry in the general area. It may be used to show the practice to be followed in a particular circumstance.
Customer
AACEi :
The ultimate consumer, user, client, beneficiary or second party who will be responsible for acceptance of the project's deliverables.
PMI :
Customer is the person(s) or organization(s) that will pay for the project’s product, service, or result. Customers can be internal or external to the performing organization.
PCI :
Any person who defines needs or wants, justifies or pays for part or the entire project, or evaluates or uses the results.
Customer Furnished Equipment (CFE)
AACEi :
Equipment provided to the contractor doing the project by the customer for the project and typically specified in the contract. Also referred to as owner furnished material/equipment (OFM/OFE).
Customer Satisfaction
PMI :
Within the quality management system, a state of fulfillment in which the needs of a customer are met or exceeded for the customer’s expected experiences as assessed by the customer at the moment of evaluation.
Cutoff Date
AACEi :
The ending date in a reporting period.
Cybernatic Control
APM :
The form of control that deals with routine progress tracking and corrective action using a feedback loop.
Cycle Time
AACEi :
The time duration that it takes to create a deliverable. Includes time for both direct effort on the deliverable and time spent on other activities, projects or processes that intentionally or unintentionally add to the duration.
Daily Crew Output
AACEi :
The amount of work accomplished by a crew in one day (typically 8 hours). This is a special form of production rate.
Damages, Actual
AACEi :
The increased cost to one party resulting from another party's acts or omissions affecting the contract but not incorporated into a contract modification.
Damages, Liquidated
AACEi :
An amount of money stated in the contract as being the liability of a contractor for failure to complete the work by the designated time(s). Liquidated damages ordinarily stop at the point of substantial completion of the project or beneficial occupancy by the owner. Also can apply to contract defined output performance. Syn.: Liqaidated Damages
Damages, Ripple
AACEi :
Syn.: Impact Cost.
Dangle
AACEi :
An activity in a network that has neither predecessors nor successors.
PCI :
An activity or network which has either no predecessors or no successors. If neither, referred to as an isolated activity.
Data Date
AACEi :
(1) The date on which the schedule has been updated to reflect actual progress (percent complete, remaining durations, new activities and changed logic, etc. input into schedule) and projects a new completion date.
(2) The calendar date that separates actual (historical) data from scheduled data. Scheduling software uses the data date to base its network calculations.
PMI :
A point in time when the status of the project is recorded.
Data Gathering And Representation Techniques
PMI :
Techniques used to collect, organize, and present data and information.
Data Item Description (DID)
PCI :
Data Item Description contains the format and content preparation instructions for the data product generated by the specific and discrete task requirements as delineated in the contract.
Date Constraint
AACEi :
A fixed date imposed on an activity to force it to start or finish by or on a certain date in a schedule model. A date constraint overrides the logic of the schedule and can, if improperly used, cause unintended results.
Date Of Acceptance
AACEi :
Date on which the client agrees to final acceptance of the project. Commitments against the authorized funds usually cease at this time. This is an event.
Day Work Account
AACEi :
A method of payment for work not included in the scope of the contract that the construction contractor is obliged to perform at the request or direction of the owner or its agent. Generally, such day work account is paid for on unit-price or cost-plus terms.
De-Escalate
AACEi :
A method to convert present-day costs or costs of any point in time to costs at some previous date via applicable indexes.
De-Scope
AACEi :
For earned value, project scope removed with a separate contractual action. It is scope with schedule and budget that is returned to the owner for other uses. The net result is the total project budget is reduced, and the overall duration of the project may also be reduced. Alternately, the amount of project scope removed may be kept in Undistributed Budget/Schedule Margin until returned to the owner.
Deceleration
AACEi :
The opposite of acceleration. A direction, either expressed or implied, to slow down job progress.
Decision Analysis (DA)
AACEi :
A systematic and typically quantitative process for selecting the optimum of two or more alternatives in order to address a problem or opportunity.
Decision Basis
AACEi :
Refers to the definition of the components or criteria on which a decision is based. Generally includes defined alternatives, information, and preferences.
Decision Driver
AACEi :
Variables in a decision model that influence decision outcomes.
Decision Event
AACEi :
State in the progress of a project when a decision is required before the start of any succeeding activity. The decision determines which of a number of alternative paths is to be followed.
Decision Framing
AACEi :
Methods to identify, define, layout or frame the decision to be addressed during the structuring step of decision analysis.
Decision Implementation
AACEi :
In decision analysis, this refers to the process step for implementing the selected alternative and performing continuous improvement.
Decision Model
AACEi :
A quantitative model that that provides a base methodology that supports objective, consistent and appropriate decision making by an organization considering all agreed model inputs and outputs.
Decision Policy
AACEi :
Definitive position of an organization on how investment or project decisions will be made. Establishes the basis for decision models. Provides a basis for consistent and appropriate decision making and defines authority and accountability within the organization.
Decision Quality Chain
AACEi :
A generally recognized quality management model for decision analysis. It includes the following elements:
a. Appropriate frame
b. Creative, doable alternatives
c. Meaningful, reliable information
d. Clear values and trade-offs
e. Logically correct reasoning and
f. Commitment to action.
Decision Tree
AACEi :
A graphical representation of the decision process. Sequential decisions are drawn in the form of branches of a tree, stemming from an initial decision point and extending all the way to final outcomes. Each path through branches of the tree represents a separate series of decisions and probabilistic events.
PMI :
Decision Tree Analysis : A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Decisions Under Certainty
AACEi :
Simple decisions that assume complete information and no uncertainty connected with the analysis of the decisions.
Decisions Under Risk
AACEi :
A decision problem in which the analyst elects to consider several possible futures, the probabilities of which can be estimated.
Decisions Under Uncertainty And Risk
AACEi :
A decision for which the analyst elects to consider several possible futures, the probabilities of which cannot be estimated.
Declining Balance Depreciation
AACEi :
Method of computing depreciation in which the annual charge is a fixed percentage of the depreciated book value at the beginning of the year to which the depreciation applies. Syn.: Percent On Diminishing Value.
Decomposition
AACEi :
Separation of the scope of work and requirements into smaller, component packages, so that work effort can be more effectively monitored and controlled.
PMI :
A technique used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts.
Defect
AACEi :
A deviation of a severity sufficient to require corrective action.
PMI :
An imperfection or deficiency in a project component where that component does not meet its requirements or specifications and needs to be either repaired or replaced.
Defect Repair
PMI :
An intentional activity to modify a nonconforming product or product component.
Defect, Latent
AACEi :
A defect in the work which cannot be observed by reasonable inspection.
Defect, Patent
AACEi :
A defect in the work which can be observed by reasonable inspection.
Defective
AACEi :
An adjective which, when modifying the work, refers to work that is unsatisfactory, faulty or deficient, or does not conform to the contract documents, or does not meet the requirements of any inspection, reference standard, test or approval referred to in the contract documents, or has been damaged prior to the engineer's recommendation of final payment (unless responsibility for the protection thereof has been assumed by the owner at substantial completion in accordance with the contract documents).
Defective Specifications
AACEi :
Specifications and/or drawings which contain errors, omissions, and/or conflicts, which affect or prevent the contractor's performance of the work.
Defined
APM :
The third level of a typical maturity model where processes are documented and standardised.
Definition (Project)
AACEi :
Process of quantifying performance and interface requirements during system decomposition and elaboration phase of a project.
APM :
The second phase of a project or programme life cycle where requirements are refined, the preferred solution is identified and ways of achieving it are identified.
Definition Phase
AACEi :
An early phase in the project life cycle when the scope is defined. Syn.: Development Phase; Front End; Planning Phase.
APM :
Define :The phase of a portfolio life cycle where the projects, programmes and change to business-as-usual required to meet strategic objectives are identified and evaluated.
Definitive Estimate
AACEi :
An estimate generally involving a high degree of deterministic estimating methods. It is generally prepared in great detail.
Deflation
AACEi :
A persistent decrease in the level of consumer prices, or a persistent increase in the purchasing power of money caused by a decrease in available currency and credit relative to the proportion of available goods and services (i.e., negative inflation).
Delay
AACEi :
To cause the work or some portion of the work to start or be completed later than planned or later than scheduled.
Delay, Compensable
AACEi :
(1) Delays that are caused by the owner's actions or inactions. Contractor is entitled to a time extension and damage compensation for extra costs associated with the delay.
(2) If the delay is deemed compensable the party will be entitled to additional compensation for the costs of delay, as well as additional time for contract performance. However, it is possible for a delay to be compensable without extending the contract performance time. Generally speaking, a delay that could have been avoided by due care of one party is compensable to the innocent party suffering injury or damage as a result of the delay’s impact. [10]
(3) A contractor is entitled to recover for delay costs and a time extension provided that three conditions are satisfied: 1) The delay is caused by the owner or is within the owner’s control; 2) The delay results in additional costs to the contractor; and 3) The contractor has not assumed the risk of delay. Because this entitlement is implied in every contract, it does not need to be expressly stated in the contract.
Delay, Concurrent
AACEi :
Two or more delays in the same time frame or which have an independent effect on the end date. The owner/engineer and the contractor may each be responsible for delay in completing the work. This may bar either party from assessing damage against the other. This may also refer to two or more delays by the same party during a single time period.
Delay, Excusable
AACEi :
Any delay beyond the control and without the fault or negligence of the contractor or the owner, caused by events or circumstances such as, but not limited to, acts of God or of the public enemy, acts of interveners, acts of government other than the owner, fires, floods, epidemics, quarantine restrictions, freight embargoes, hurricanes, tornadoes, labor disputes, etc. Generally, a delay caused by an excusable delay to another contractor is compensable when the contract documents specifically void recovery of delay costs.
Delay, Inexcusable
AACEi :
Any delay caused by events or circumstances within the control of the contractor, such as inadequate crewing, slow submittals, etc, which might have been avoided by the exercise of care, prudence, foresight, or diligence on the part of the contractor.
Delay, Nonprejudicial
AACEi :
Any delay impacting a portion of the work within the available total float or slack time, and not necessarily preventing completion of the work within the contract time.
Delay, Pacing
AACEi :
(1) Deceleration of the project work, by one of the parties to the contract, due to a delay to the end date of the project caused by the other party, so as to maintain steady progress with the revised overall project schedule.
(2) A delay resulting from a conscious and contemporaneous decision to pace progress of an activity against another activity experiencing delay due to an independent cause.
(3) The consumption of float created by another delay, in performing work on an activity not directly dependent on the progress of the work experiencing the other delay.
Delay, Parent
AACEi :
The alleged owner-caused delay that created or increased the relative total float consumed by the pacing delay. The parent delay must start or exist prior to the pacing delay. Also the parent delay must be on the critical path or have a lower float value than the paced activity prior to pacing.
Delay, Prejudicial
AACEi :
Any excusable or compensable delay impacting the work and exceeding the total float available in the progress schedule, thus preventing completion of the work within the contract time unless the work is accelerated.
Delaying Resource
AACEi :
In resource planning and scheduling, inadequate availability of one or more resources may require that completion of an activity be delayed beyond the date on which it could otherwise be completed. The delaying resource is the first resource on an activity that causes the activity to be delayed.
PCI :
In resource scheduling, inadequate availability of one or more resources may require that the completion of an activity be delayed beyond the date on which it could otherwise be completed. The delaying resource is the first resource on an activity that causes the activity to be delayed.
Delegation
APM :
The practice of giving a person or group the authority to perform the responsibilities of, or act on behalf of, another.
PCI :
Deligating :The process by which authority and responsibility is distributed from Project Manager to subordinates.
Deliverable
AACEi :
(1) A report or product of one or more tasks that satisfy one or more objectives and must be delivered to satisfy contractual requirements.
(2) Another name for products, services, processes, or plans created as a result of doing a project. A project typically has interim as well as final deliverables
APM :
A product, set of products or package of work that will be delivered to, and formally accepted by, a stakeholder.
PMI :
Any unique and verifiable product, result, or capability to perform a service that is required to be produced to complete a process, phase, or project.
PCI :
A report or product that must be completed and delivered to ensure satisfaction of contractual requirements.
Delivery
AACEi :
Transfer or handover of a product from one party to another. Syn.: Turnover.
Delphi Technique
AACEi :
A forecasting technique that seeks expert consensus by sharing their opinions with each other anonymously after each round of forecasts. Based on the array of anonymous expert opinions then shared, panel participants rethink and reforecast for the next round. When forecasts are congruent or nearly so, the forecasting process is complete.
PMI :
An information gathering technique used as a way to reach a consensus of experts on a subject. Experts on the subject participate in this technique anonymously. A facilitator uses a questionnaire to solicit ideas about the important project points related to the subject. The responses are summarized and are then recirculated to the experts for further comment. Consensus may be reached in a few rounds of this process.
The Delphi technique helps reduce bias in the data and keeps any one person from having undue influence on
the outcome.
PCI :
A process where a consensus view is reached by consultation with experts. Often used as an estimating technique.
Demand Factor
AACEi :
(1) The ratio of the maximum instantaneous production rate to the production rate for which the equipment was designed.
(2) The ratio between the maximum power demand and the total connected load of the system.
Deming Cycle
AACEi :
Syn.: Plain-Do-Check-Act (PDCA) Cycle.
Demobilisation
APM :
The controlled dispersal of personnel and disposal of assets when they are no longer needed on a project, programme or portfolio.
Demurrage
AACEi :
A charge made on cars, vehicles, or vessels held by or for consignor or consignee for loading or unloading, for forwarding directions or for any other purpose.
Dependencies
AACEi :
Relationships between products or tasks. For example, one product may be made up of several other 'dependent' products or a task may not begin until a 'dependent' task is complete.
Dependency
AACEi :
A relation between activities, such that one requires input from the other.
APM :
A relationship between activities in a network diagram.
PMI :
Logical Relationship: A dependency between two activities, or between an activity and a milestone.
PCI :
Dependencies are relationships between products or tasks. For example, one product may be made up of several other ‘dependent’ products or a task may not begin until a ‘dependent’ task is complete.
Dependency Determination
PMI :
A technique used to identify the type of dependency that is used to create the logical relationships between predecessor and successor activities.
Dependency Links
PCI :
Different types of links connecting activities in a precedence network.
Dependent Variable
AACEi :
An event or condition whose impact or probability of occurrence depends on another variable.
Depletion
AACEi :
(1) A form of capital recovery applicable to extractive property (e.g., mines). Depletion can be on a unit-of-output basis related to original or current appraisal of extent and value of the deposit. (Known as percentage depletion.)
(2) Lessening of the value of an asset due to a decrease in the quantity available. Depletion is similar to depreciation except that it refers to such natural resources as coal, oil, and timber in forests.
Depreciated Book Value
AACEi :
The first cost of the capitalized asset minus the accumulation of annual depreciation cost charges.
Depreciation
AACEi :
(1) Decline in value of a capitalized asset.
(2) A form of capital recovery applicable to a property with a life span of more than one year, in which an appropriate portion of the asset's value is periodically charged to current operations.
Descriptive
AACEi :
Portrayal of content in words, either orally or written. When applied to instructions, implies information concerning how something is to be done, rather than step by step details of what is to be done, i.e. prescriptive.
Design & Development Phase
AACEi :
Definition phase in a generic project life cycle that encompasses detailed technical, commercial and organizational decisions. There is often substantial opportunity to optimize these decisions without expenditure of significant resources by modeling, prototyping and testing. Management approval gates are necessary where major decisions will be made. In some industries, this phase is dealt with as two separate phases with a management gate between the two. This allows design to be matured before approval is given for significant resource expenditure on full design/development. Equally, the gate may be required before major procurement decisions and commitments are made after initial design but prior to full design/development.
PCI :
The time period in which production process and facility and production processes are developed and designed.
Design Development
AACEi :
Process of identifying and verifying technical solutions to meet requirements of conceptual design. Takes conceptual design to next level of detail, but not as detailed as the detailed design stage. Depending on size and nature of project, it may be a separate stage in the project life cycle.
Design Of Experiments
PMI :
A statistical method for identifying which factors may influence specific variables of a product or process under development or in production.
Design Review
AACEi :
A formal, documented, comprehensive and systematic examination of a design to evaluate design requirements and capability of the design to meet these requirements and to identify problems and propose solutions.
Desirable Logic
AACEi :
Network logic that is desirable for the contractor (but not necessarily for the client), based on some preference or advantage. Desirable logic may impose unnecessary conditions that preclude an optimum solution.
Detail(Ed) Schedule
AACEi :
(1) A schedule used to communicate the day-to-day activities to working levels on the project. The detailed schedule would typically cover activities up to at least the next major milestone. The detailed schedule supports and is consistent with the master schedule.
Detailed Engineering
AACEi :
The detailed design, drafting, engineering, and other related services necessary to purchase equipment and materials and construct a facility.
Detailed Requirement
AACEi :
A requirement that describes the specific function that a particular product provides at a level of detail sufficient to support execution of the work.
Detailed Resourse Plan
PCI :
A plan implemented when it’s necessary to plan and control a certain major activity within a stage. The plan sets costs and resource usage that correspond to the detailed technical plan.
Detailed Technical Plan
PCI :
A plan used to give a specific breakdown of major activities. It exists in all but the smallest projects.
Determine Budget
PMI :
The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.
Deterministic Estimate
AACEi :
An estimate where none of the variables are probabilistic and that is developed using deterministic methods (i.e., not subject to significant conjecture). In some usage, this term is synonymous with Base Estimate (even if the base estimate is developed using stochastic methods).
Deterministic Network/Model
AACEi :
(1) A network with no facilities to accommodate probabilistic dependencies. Precedence networks are said to be deterministic.
(2) A deterministic model, as opposed to a stochastic model, contains no random elements and for which, therefore, the future course of the system is determined by its state at present (and/or in the past).
Develop Project Charter
PMI :
The process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Develop Project Management Plan
PMI :
The process of defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive project management plan.
Develop Project Team
PMI :
The process of improving competencies, team member interaction, and overall team environment to enhance project performance.
Develop Schedule
PMI :
The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model.
Development
AACEi :
Process of working out and extending theoretical, practical, and/or useful application of an idea, concept, or preliminary design.
Development Costs
AACEi :
Those costs specific to a project, either capital or expense items, which occur prior to commercial sales and which are necessary in determining the potential of that project for consideration and eventual promotion. Major cost areas include process, product, and market research and development.
Development Phase
AACEi :
Syn.: Definition Phase; Front End; Planning Phase.
Deviation
AACEi :
(1) A departure from established requirements. Deviations occur when the work product either fails to meet or unnecessarily exceeds the requirements. The change (positive or negative) may be considered potential or it may already be in the process of actually occurring. The deviation is used to provide a detailed description and detailed estimate (or ROM estimate) of change impacts that are the result of design developments, productivity, omissions, errors, price fluctuation, supplier changes, etc., or anything else that changes the forecast cost and schedules. Deviations are documented by project controls and communicated to the project manager. A deviation provides the project team with an opportunity to mitigate an adverse impact or to optimize the outcome and is used primarily as a communication tool. Note: Deviation as used herein refers to a single point variance. Trend refers to a pattern of a data group.
(2) In systems engineering, a deviation in the work product may be classified as an imperfection, nonconformance, or defect.
Deviation Costs
AACEi :
The sum of those costs, including consequential costs such as schedule impact, associated with the rejection or rework of a product, process, or service due to a departure from established requirements. Also may include the cost associated with the provision of deliverables that are more than required.
Diagramming (Schedule)
AACEi :
Syn.: Scheduling.
PMI :
Diagramming Techniques: Approaches to presenting information with logical linkages that aid in understanding.
Dictatorship
PMI :
A group decision-making technique in which one individual makes the decision for the group.
Differing Site Conditions
AACEi :
Subsurface or latent physical conditions at the site differing materially from those conditions indicated in the contract documents or unknown physical conditions at the site, of an unusual nature, differing materially from conditions normally encountered and generally recognized as inherent in work of the nature provided for in the contract.
Direct And Manage Project Work
PMI :
The process of leading and performing the work defined in the project management plan and implementing approved changes to achieve the project’s objectives.
Direct Costs
AACEi :
Costs of completing work that are directly attributable to its performance and are necessary for its completion.
1) In construction, the cost of installed equipment, material, labor and supervision directly or immediately involved in the physical construction of the permanent facility.
2) In manufacturing, service, and other non-construction industries: the portion of operating costs that is readily assignable to a specific product or process area. Syn.: Capital ,Direct.
PCI :
Those costs (labor, material, and other direct costs) that can be consistently related to work performed on a particular project. Direct costs are best contrasted with indirect costs that cannot be identified to a specific project.
Direct Pacing
AACEi :
When the paced event has a logical relationship to the parent delay.
Disbenefit
APM :
A consequence of change perceived as negative by one or more stakeholders.
Discipline
AACEi :
(1) Area of technical expertise or specialty. [8]
(2) A discrete area of study and endeavor where only specialized education and experience enable the full comprehension of the content of the subject matter and its appropriate application.
Discontinuous Activity
AACEi :
An activity in which the interval between start and finish dates is allowed to exceed its duration in order to satisfy start-to-start and finish-to-finish relationships with other activities.
Discontinuous Processing
PCI :
This option assigns the discontinuous attribute to all activities for a time analysis session, except where overridden by a specific activity type.
Discount Factor
AACEi :
A multiplicative number (calculated from a discount formula for a given discount rate and interest period) that is used to convert costs and benefits occurring at different times to a common time.
Discount Rate
AACEi :
The rate of interest reflecting the investor's time value of money, used to determine discount factors for converting benefits and costs occurring at different times to a base time. The discount rate may be expressed as nominal or real.
Discounted Cash Flow
AACEi :
(1) The present worth of a sequence in time of sums of money when the sequence is considered as a flow of cash into and/or out of an economic unit.
(2) An investment analysis which compares the present worth of projected receipts and disbursements occurring at designated future times in order to estimate the rate of return from the investment or project. Also called discounted cash flow rate of return, interest rate of return, internal rate of return, investor's method or profitability index. Syn.: Investor's Method.
Discounted Payback Period (DPP)
AACEi :
The time required for the cumulative benefits from an investment to pay back the investment cost and other accrued costs considering the time value of money.
Discounting
AACEi :
A technique for converting cash flows that occur over time to equivalent amounts at a common time.
Discrete Effort
AACEi :
Tasks that have a specific measurable end product or end result. Discrete tasks are ideal for earned value measurement.
PMI :
An activity that can be planned and measured and that yields a specific output. [Note: Discrete effort is one of three earned value management (EVM) types of activities used to measure work performance.]
Discrete Milestone
AACEi :
A milestone that has a definite scheduled occurrence.
Discrete Task
AACEi :
A measurable activity with an output.
Discretionary Dependency
AACEi :
Dependency defined by preference, rather than necessity. These are typically employed in preferential or soft logic.
PMI :
A relationship that is established based on knowledge of best practices within a particular application area or an aspect of the project where a specific sequence is desired.
Disinflation
AACEi :
A decrease in the rate of inflation (for example, a change in the rate of inflation from 4% to 2%). Differs from, but may portend deflation.
Dispatching
AACEi :
The selecting and sequence of jobs to be run at individual work stations and the assignment of these jobs to workers. In many companies, dispatching is done by the actual shop line supervisor, set-up worker or lead worker. A dispatcher is usually a representative of the production control department which handles this job assignment task.
Dispute
AACEi :
A disagreement between the owner and the contractor as to a question of fact or contract interpretation which cannot be resolved to the mutual satisfaction of the parties.
Disruption
AACEi :
An interference (action or event) with the orderly progress of a project or activity(ies). Disruption has been described as the effect of change on unchanged work and manifests itself primarily as adverse labor productivity impacts. If such disruption is caused by owner or engineer action (or failure to act), the contractor may be entitled to recover any resulting costs.
Distributables
AACEi :
The portion of a project’s cost that can not be associated with any specific direct account. In construction, this includes the field non-manual staff, field office, office supplies, temporary construction, utilities, small tools, construction equipment, weather protection, snow removal, lost time, labor burden, etc. When completion cost reports are prepared, the distributable costs may be distributed across the direct accounts for fixed asset accounting.
Do Nothing Option
APM :
The result or consequence of not proceeding with the project or programme. Usually explained in the business case.
Document
AACEi :
(1) (noun) Words or images assembled for a communicative purpose within a bounded physical medium—typically on sheets of paper or in digital memory files.
(2) (verb) To record communications, events, actions, or circumstances within a bounded physical medium.
Document Analysis
PMI :
An elicitation technique that analyzes existing documentation and identifies information relevant to the requirements.
Documentation Reviews
PMI :
The process of gathering a corpus of information and reviewing it to determine accuracy and completeness.
Drawdown
APM :
The removal of funds from an agreed source resulting in a reduction of available funds.
Drawings, Plans
AACEi :
The drawings, plans or reproductions thereof, which show location, character, dimensions, and details of the work to be performed and which are referred to in the contract documents.
Driving Activity
AACEi :
The predecessor activity(ies) that determines another activity's early start.
Driving Relationship
AACEi :
A relationship between two activities in which the start or completion of the predecessor activity determines the early dates for the successor activity with multiple predecessors.
Dummy Activity
AACEi :
Used only in activity on arrow (AOA) networks to create logic relationships between activities denoting a dependency, but not an action. Dummies are “activities” with zero duration, but are not milestones. Dummy activities are typically drawn as dotted lines.
Dummy Start Activity
AACEi :
An activity entered into the network for the sole purpose of creating a single start for the network.
Durable Goods
AACEi :
Generally, any producer or consumer goods whose continuous serviceability is likely to exceed three years (e.g., trucks, furniture).
Duration
AACEi :
The amount of time estimated to complete an activity in the time scale used in the schedule (hours, days, weeks, etc.). Planned production rates and available resources will define the duration used in a given schedule. The following four types of duration are used:
1) Original duration: Duration input by the planner;
2) Current duration: Duration based on latest progress date for in-progress activities. Calculated rate of progress provides a new completion estimate;
3) Actual duration: Duration based on activity's actual start and actual finish. Applies only to completed activities; and
4) Remaining duration: The expected time required to complete an activity. It is calculated as the difference between the data date and the expected finish date for in-progress activities. (Equal to the original duration for non-progressed activities. Equal to zero for completed activities.)
PMI :
The total number of work periods (not including holidays or other nonworking periods) required to complete a schedule activity or work breakdown structure component. Usually expressed as workdays or workweeks. Sometimes incorrectly equated with elapsed time. Contrast with effort.
PCI :
Duration is the length of time needed to complete an activity.
Duration Compression
AACEi :
Shortening project schedule without reducing project scope. Duration compression is not always possible and often requires an increase in project cost.
PCI :
Often resulting in an increase in cost, duration compression is the shortening of a project schedule without reducing the project scope.
Duration Sensitivity
AACEi :
The measure of the correlation between the duration of a task and the duration of a project. When combined with the criticality index, it determines the cruciality index.
Dynamic Risk Analysis
AACEi :
Risk analysis which addresses dynamic risks. May employ elements of systems dynamics.
Dynamic Risk
AACEi :
Risk for which the characteristics, probability and/or impact change over time or with the occurrence of preceding events.
Earliest Expected Completion Date
AACEi :
The earliest calendar date on which the completion of an activity work package or summary item occurs.
Early Bar
AACEi :
An activity bar shown on the bar chart starting at the earliest date its predecessors’ completion will allow it to begin.
Early Dates
AACEI :
Calculated in the forward pass of time analysis, early dates are the earliest dates on which an activity can start and finish.
Early Event Time (EET)
AACEi :
The earliest time at which an event may occur.
Early Finish (EF)
AACEi :
The earliest date or time an activity may finish as calculated by the schedule during the forward pass. Equal to the early start of the activity plus its remaining duration.
PMI :
Early Finish Date (EF): In the critical path method, the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, the data date, and any schedule
constraints.
Early Start (ES)
AACEi :
The earliest date or time an activity may start as calculated by the schedule during the forward pass.
PMI :
Early Start Date (ES): In the critical path method, the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic, the data date, and any schedule constraints.
Early Work Schedule
AACEi :
Predicated on the parameters established by the proposal schedule and any negotiated changes, the early work schedule defines reportable pieces of work within major areas. The format is developed into a logic network including engineering drawings, bid inquiries, purchase orders, and equipment deliveries, and can be displayed as a time-phased network. The detail of this schedule concentrates on projected engineering construction issue drawings released and equipment deliveries. The activities of the early part of construction are more defined than in the proposal or milestone schedule.
Earned Hours (EH)
AACEi :
The time in standard hours credited as a result of the completion of a given task or a group of tasks.
Earned Schedule (ES)
AACEi :
(1) The number of whole plus partial project planned value (PV) time increments that equates to the earned value accrued.
(2) An extension of Earned Value Management (EVM) practices that develops counterparts to conventional EVM metrics calculated and expressed in terms of duration (time) instead of monetary value. These metrics are differentiated from their EVM counterparts by listing their time dependence (e.g., the ES metrics for schedule variance and schedule performance index are SV(t) and SPI(t) respectively). This distinction is often emphasized by labeling the cost dependence of conventional cost-based earned value metrics (e.g., the traditional EVM metrics schedule variance and schedule performance index are SV($) and SPI($) respectively). The use of the monetary denotation for conventional EVM metrics tends to be used only in discussions when ES and EVM are discussed together.
Earned Value (EV)
AACEi :
Measure of the value of work performed so far, also called the Budgeted Cost of Work Performed (BCWP). The “value” of the work earned at the date of analysis (data date). The cost of the work that has been accomplished in terms of the BCWS. Represents the budget value of work performed, rather than the actual cost of the work performed. In comparison to Planned Value (PV), provides a measure of performance taking into account both time and cost expended.
APM :
The value of completed work expressed in terms of the budget assigned to that work. A measure of progress which may be expressed in cost or labour hours.
PMI :
The measure of work performed expressed in terms of the budget authorized for that work.
PCI :
EV quantifies the amount or volume of work completed to date, and is commonly known as the Budgeted Cost of Work Performed (BCWP). When compared to the planned value (Budgeted Cost of Work Scheduled) and its actual cost (Actual Cost of Work Performed), EV provides an objective measure of schedule and cost performance.
Earned Value Concept
AACEi :
In general (non-EVMS) terms, the objective measurement at any time of work accomplished (performed) in terms of budgets planned for that work, and the use of these data to indicate contract cost and schedule performance.
Earned Value Management (EVM)
PCI :
EVM is a methodology that integrates a programme's work scope, schedule, and resources to enable government and contractor management to objectively track programme progress throughout the project's life cycle.
Earned Value Management Implementation Guide (EVIG)
PCI :
The EVMIG provides guidance for understanding earned value management concepts, defines objective criteria for earned value management systems and provides guidance in interpreting those criteria for use on large, risky, cost based government programmes. Procedural aspects for Government personnel for specifying and using earned value management systems and for evaluating those systems are also provided.
Earned Value Management [System] (EVM[S])
AACEi :
A project progress control system that integrates work scope, schedule, and resources to enable objective comparison of the earned value to the actual cost and the planned schedule of the project.
APM :
A project control process, based on a structured approach to planning, cost collection and performance measurement. It facilitates the integration of project scope, time and cost objectives and the establishment of a baseline plan of performance measurement.
PMI :
A methodology that combines scope, schedule, and resource measurements to assess project performance and progress.
PCI :
EVMS is the integrated set of processes, applications, and practices that follow the globally accepted guidelines that describe the attributes of an effectively integrated cost, schedule, and technical performance management system.
Earned Value Reports
AACEi :
Cost and schedule performance reports that are part of the performance measurement system. These reports make use of the earned value concept of measuring work accomplishment.
Earnings Value
AACEi :
The present worth of an income producer's probable future net earnings, as prognosticated on the basis of recent and present expense and earnings and the business outlook.
Economic Costs
AACEi :
A valuation measure used in decision making that combines accounting costs and opportunity costs.
Economic Evaluation Methods
AACEi :
A set of economic analysis techniques that considers all relevant costs associated with a project investment during its study period, comprising such techniques as life-cycle cost, benefit-to-cost ratio, savings-to-investment ratio, internal rate of return, and net savings.
Economic Life (Cycle)
AACEi :
Syn.: Life Cycle, Asset Life Cycle
Economic Return
AACEi :
The profit derived from a project or business enterprise without consideration of obligations to financial contributors and claims of others based on profit.
Economic Value
AACEi :
The value of property in view of all its expected economic uses, as distinct from its value in view of any particular use. Also, economic value reflects the importance of a property as an economic means to an end, rather than as an end in itself.
Economy
AACEi :
The cost or profit situation regarding a practical enterprise or project as in economy study, engineering economy, and project economy.
Effect
AACEi :
Syn.: Consequence; Impact.
Effective Date Of The Agreement
AACEi :
The date indicated in the agreement on which it becomes effective, but if no such date is indicated, the date on which the agreement is signed and delivered by the last of the two parties to sign and deliver.
Effective Interest
AACEi :
The true value of interest rate computed by equations for compound interest rate for a 1-year period.
Efficiency
AACEi :
Syn.: Productivity.
Efficiency Factor
AACEi :
A measure of overall performance used in a work measurement system. It is calculated by dividing the standard time to perform the work by the actual time.
Effort
AACEi :
The number of labor units necessary to complete work. Effort is usually expressed in staff hours, staff days or staff weeks and should not be confused with duration.
PMI :
The number of labor units required to complete a schedule activity or work breakdown structure component, often expressed in hours, days, or weeks.
Effort Remaining
AACEi :
Estimate of effort remaining to complete an activity. A far more useful measure of progress than percentage complete.
Effort-Driven Activity
AACEi :
An effort-drive activity provides the option to determine activity duration through resource usage. The resource requiring the greatest time to complete the specified amount of work on the activity will determine its duration.
Eighty-Hour Rule
AACEi :
Method of breaking down each project activity or task into work packages that require no more than 80 hours of effort to complete.
Eighty-Twenty Rule
AACEi :
A statistical principle named after Italian economist Vilfredo Pareto, who observed that 80% of the wealth in Italy was controlled by 20% of the population. In cost management, it is commonly used to describe the situation where a small subset of cost items, activities, and so on, are the source of most of the total cost, duration, etc. Syn.: Pareto's Law.
Elementary Commodity Groups (Elementary Groups)
AACEi :
The lowest level of goods and services for which a consistent set of value weights is available.
Emergent Risk
AACEi :
Occurred risk whose occurrence was not proactively anticipated.
Emotional Intelligence
PMI :
The capability to identify, assess, and manage the personal emotions of oneself and other people, as well as the collective emotions of groups of people.
End Activity
AACEi :
An activity with no logical successors.
End Event (Of A Project)
AACEi :
Event with preceding, but no succeeding activities. There may be more than one end event.
End Item
AACEi :
A final combination of end products components, parts or materials that is ready for its intended use.
End Network Event
AACEi :
The event that signifies the end of a network.
Ending Node Of Network (ADM)
AACEi :
A node where no activities begin, but one or more activities end.
Endowment
AACEi :
A fund established for the support of some project or succession of donations or financial obligations.
Engineer (In Contracts)
AACEi :
The individual, partnership, corporation, joint venture, or any combination thereof, named as the engineer in the agreement who will have the rights and authority assigned to the engineer in the contract documents. The term "the engineer" means the engineer or the engineer's authorized representative.
Engineered Items
AACEi :
Items that are purchased to be used for a particular purpose and are engineered to unique specifications, as opposed to commodity materials. This typically includes tagged items and materials that require detailed engineering data sheets.
Engineering Change Notice (ECN)
AACEi :
The formal release of an engineering change.
Engineering Change Proposal (ECP)
AACEi :
A proposal submitted by the seller in response to a buyer request for an ECP to change the existing contract effort. Only the buyer can initiate the request for an engineering change proposal. This activity is usually preceded by a request for change. The user, buyer, or the seller can initiate a request for change to the contract. It is an exploratory activity.
Engineering Change Request (ECR)
AACEi :
Request to consider a technical change to the technical baseline submitted to client or its agent.
Enhance
AACEi :
In TCM risk management, a response strategy for opportunities that involves increasing the probability and/or impact of risk.
APM :
A response to an opportunity that increases its probability, impact or both.
Enterprise
AACEi :
(1) A business organization involved in economic activity and taking risks for purposes of profit.
(2) In total cost management, any endeavor, business, government, group, individual or other entity that owns, controls, or operates strategic assets.
Enterprise Environment Factors
AACEi :
Conditions, not under the immediate control of the team, that influence, constrain, or direct the project, program, or portfolio.
Enterprise Project Management
AACEi :
Application of project management discipline throughout an enterprise. A concept based on principle that prosperity depends on adding value to business, and that value is added by systematically implementing new projects, i.e. projects of all types across the organization.
APM :
Enterprise project management office: An organisation that is responsible for the governance infrastructure of P3 management.
Enterprise Resource Planning (ERP)
AACEi :
Program/project resource planning of activities, supported by multi-module application software and processes to help an enterprise manage key parts of its business which may include product planning, maintaining inventories, supply chain processes, providing customer services, human resources planning, etc. It may include other system involving any kind of resource consumption that can benefit from integration of information across many functional areas.
Enterprise Risk Management
AACEi :
The risk management process applied to the overall enterprise, portfolio and program level objectives, not to just a single business unit, asset or project.
Environment
AACEi :
The circumstances and conditions within which the project, programme or portfolio must operate.
Equitable Adjustment
AACEi :
A contract adjustment in price or time under, certain contract clauses, or both, to compensate the contractor expense incurred due to actions of the owner or to compensate the owner for contract reductions. An equitable adjustment includes an allowance for profit. Certain contract clauses provided for adjustments, excluding profit, and are not considered “equitable adjustments.”
Equivalent Sets Of Commodities
AACEi :
Sets of commodities which provide the same total satisfaction to a given group of consumers (without necessarily being identical).
Equivalent Uniform Annual Value
AACEi :
Syn.: Annual Value; Annual Worth.
Equivalent Units Technique
AACEi :
An earned value technique that assigns a pre-assigned equal weight to a unit of completion (e.g. drawings complete).
Errors And Omissions
AACEi :
Deficiencies, usually in design or drafting, in the plans and specifications that must be corrected in order for the facility to operate properly. Errors in plans and specifications are normally items that are shown incorrectly, while omissions are normally items that are not shown at all.
Escalation
AACEi :
A provision in costs or prices for uncertain changes in technical, economic, and market conditions over time. Inflation (or deflation) is a component of escalation.
APM :
The process by which issues are drawn to the attention of a higher level of management.
Escalator Clause
AACEi :
Clause contained in collective agreements or purchase orders, providing for an automatic price adjustment based on changes in specified indices.
Estimate
AACEi :
A prediction or forecast of the resources (i.e., time, cost, materials, etc) required to achieve or obtain an agreed upon scope (i.e., for an investment, activity, project, etc.).
APM :
An approximation of time and cost targets, refined throughout the life cycle.
PMI :
A quantitative assessment of the likely amount or outcome. Usually applied to project costs, resources, effort, and durations and is usually preceded by a modifier (i.e., preliminary, conceptual, feasibility, order-of magnitude,definitive). It should always include some indication of accuracy (e.g., ± x percent).
Estimate Activity Duration
PMI :
The process of estimating the number of work periods needed to complete individual activities with estimated resources.
Estimate Activity Resources
PMI :
The process of estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity.
Estimate At Completion (EAC)
AACEi :
An estimate of the total cost an activity or group of activities will accumulate upon final completion.
PMI :
The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
PCI :
A value expressed in either dollars and /or hours, to represent the projected final costs of work when completed. The EAC is calculated as ETC + ACWP.
Estimate At Completion [EAC(T)]
AACEi :
The estimated project duration in time increments.
Estimate Backup
AACEi :
Basic data, project objectives, scope, drawings, quotes, estimating data, qualifications and assumptions used in preparing the estimate and supporting the basis.
Estimate To Complete (ETC)
AACEi :
(1) In general terms, the estimated resources (i.e., work hours, costs, time, and/or materials) required to complete a scope of work.
(2) In earned value management, an estimate of the remaining costs required to complete an activity or group of activities. ETC = Estimate At Completion (EAC) - Actual cost (AC), is often used to calculate the estimated cost to complete the project or program under discussion.
PMI :
The expected cost to finish all the remaining project work.
PCI :
The value expressed in either dollars or hours developed to represent the cost of the work required to complete a task. Cobra calculates the ETC by subtracting the budgeted cost of work performed from the budget at complete. The ETC is calculated as BAC - BCWP.
Estimated Actual Costs
AACEi :
In earned value management according to the ANSI EIA 748 standard, these are cost added to cost from the accounting system to create the appropriate Actual Cost of Work Performed (ACWP). Estimated actuals are sometimes necessary to ensure the ANSI EIA 748 requirement that Budgeted Cost of Work Performed (BCWP) is on the same basis as the reported ACWP. The basis for estimated actuals is documented and reversed which in the cost is accrued in the accounting books of record. Example of records may include invoices received, material purchase orders, submitted journal vouchers.
Estimated Completion Date
AACEi :
The predicted date at which all requirements for a defined task will be completed.
Estimating
APM :
The use of a range of tools and techniques to produce estimates.
Estimating Funnel
APM :
A representation of the increasing levels of estimating accuracy that can be achieved through the phases of the life cycle.
Ethics Framework
APM :
Sets recognized standards of conduct and behavior within the P3 profession.
Event
AACEi :
(1) A point in time when certain conditions have been fulfilled, such as the start or completion of one or more activities. Graphically, it is represented by a node. An event occurs only when all work preceding it has been completed. It has zero duration.
(2) In risk management (i.e. risk event), an incident or occurrence whose nature or result could be a threat or opportunity to the outcome of the project. Syn.: Risk Event.
Event Driven
APM :
Control actions or reports that are triggered by a specific event are referred to as ‘event-driven’.
Event Name
AACEi :
An alphanumeric description of an event.
Event Number
AACEi :
A numerical description of an event for computation and identification.
Event Oriented
AACEi :
Planning approach focusing on events rather than activities.
Event Slack
AACEi :
The difference between the latest allowable date and the earliest date for an event.
Event Times
AACEi :
Time information generated through the network analysis calculation, which identifies the start and finish times for each event in the network.
Exception Report
AACEi :
A report that lists exceptions to the expected norm as progress and forecast information is compared against the plan.
Exceptions
AACEi :
Those occurrences that cause deviation from a plan, such as issues, change requests and risks. Exceptions can also refer to items that the cost variance and schedule variance exceed predefined thresholds.
Exclusive Or Relationship
AACEi :
Logical relationship indicating that only one of the possible activities can be undertaken.
Excusable Compensable Delays
AACEi :
Delays that are caused by the owner's actions or in actions. Contractor is entitled to a time extension and damage compensation for extra costs associated with the delay.
Excusable Delays
AACEi :
Delays not attributable to contractor's action or inactions. Excusable delays when founded, entitle contractor to a time extension if the completion date is affected.
Excusable Non-Compensable Delays
AACEi :
Delays that are neither contractor's nor owner's fault. The contractor is entitled to a time extension but not to damage compensation. Non-excusable delays, i.e. delays that are caused by the contractor's or its subcontractor's actions or inactions. Consequently, the contractor is not entitled to a time extension or delay damages. On the other hand, owner may be entitled to liquidated or other damages.
Execute/Executing
AACEi :
Accomplish a preconceived objective by directing and implementing activities.
PMI :
Directing, managing, performing, and accomplishing the project work; providing the deliverables; and providing work performance information.
Executing Process Groups
PMI :
Those processes performed to complete the work defined in the project management plan to satisfy the project specifications.
Exempt Employees
AACEi :
Employees exempt from overtime compensation by federal wage and hours guidelines.
Exit Criteria
AACEi :
Conditions that must be satisfied before the process element is considered complete.
Expansion
AACEi :
Any increase in the capacity of a plant facility or unit, usually by added investment. The scope of its possible application extends from the elimination of problem areas to the complete replacement of an existing facility with a larger one.
Expected Begin Date
AACEi :
Syn.: Target Start Date.
Expected Duration
AACEi :
The length of time anticipated for a particular activity in the PERT method or in Arrow or Precedence Diagramming Methods (ADM, PDM).
Expected Monitory Value (EMV) Analysis
PMI :
A statistical technique that calculates the average outcome when the future includes scenarios that may or may not happen. A common use of this technique is within decision tree analysis.
Expected Value
AACEI :
In risk analysis, the product of probability times impact; i.e., a risk weighted measure of impact. In statistical usage, synonymous with the mean.
Expected Value Method
AACEi :
In quantitative risk analysis and contingency estimating, a method that employs the product of a risk’s probability times its impact as the primary approach to quantifying risks.
Expense
AACEi :
Expenditures of short-term value, including depreciation, as opposed to land and other fixed capital.
Expert Judgment
AACEi :
(1) Opinions, advice, recommendations, or commentary proffered, usually upon request, by a person or persons recognized, either formally or informally, as having specialized knowledge or training in a specific area. [8]
(2) Deliberate discernment of a situation or proposed course of action by those whose knowledge, skills, and abilities are developed from specialized education and experience, which enable them to better understand the situation or propose an optimal course of action than could those whose professional backgrounds are not so specialized.
PMI :
Judgment provided based upon expertise in an application area, knowledge area, discipline, industry, etc., as appropriate for the activity being performed. Such expertise may be provided by any group or person with specialized education, knowledge, skill, experience, or training.
Exploit
AACEi :
In TCM risk management, a response strategy for opportunities that involves taking steps that increase the probability that the opportunity will occur.
APM :
A response to an opportunity that maximises both its probability and impact.
Exposure
AACEi :
In risk management, refers to the potential or actual impact of one or more risk events or conditions.
Exposure Window
AACEi :
In risk management, refers to the time during which there is a potential or actual impact of one or more risk events or conditions. Syn.: Risk Impact Window.
Extended Life Cycle
APM :
A life cycle model that includes the operation of outputs and realisation of benefits.
External Constraint
AACEi :
A constraint from outside the project network.
External Dependency
PMI :
A relationship between project activities and non-project activities.
Facilitated Workshops
PMI :
An elicitation technique using focused sessions that bring key cross-functional stakeholders together to define product requirements.
Facility
AACEi :
In project work, this term usually refers to the constructed environment, such as buildings, structures, infrastructure, plant, and equipment.
Factory Expense
AACEi :
Syn.: Plant Overhead.
Failure Mode And Effect Analysis (FMEA)
PMI :
An analytical procedure that evaluates potential failure modes, their causes, and their effects on system reliability and required functions.
Fair Value
AACEi :
A reasonable estimate of property value that is fair to all concerned after proper consideration.
Fallback Plan
AACEi :
Syn.: Contingency Plan.
PCI :
An alternative set of actions available if the primary plan must be abandoned.
Fast-Tracking
AACEi :
Running activities simultaneously instead of sequentially to reduce overall duration.
PMI :
A schedule compression technique where activities normally done in sequence are performed in parallel.
Fault Tree Analysis (FTA)
AACEi :
A deductive risk analysis method linking a top event to combinations of lower-level events that could cause it.
Fee
AACEi :
The charge for services as specified in a contract.
PMI :
Represents profit as part of seller compensation.
Field Cost
AACEi :
Engineering and construction costs associated with the job site rather than the home office.
Field Indirects
AACEi :
Support costs for direct work, including temporary facilities, supervision, and construction equipment.
Field Labor Overhead
AACEi :
The sum of payroll burden, temporary construction, supervision, and tools and equipment.
Field Order
AACEi :
A written order issued by the engineer directing minor work changes without price or time adjustment.
Field Supervision
AACEi :
Project site supervisory and support staff excluding general foreman.
Field Supervision Costs
AACEi :
Salaries, wages, burdens, allowances, and office costs of field supervision personnel.
FIFO (First In, First Out)
AACEi :
An inventory costing and material movement method where the earliest received items are used first.
Financial Life
AACEi :
Syn.: Venture Life.
Financial Management
APM :
The process of estimating, securing, controlling, and evaluating financial resources.
Finish Date
AACEi :
The actual or estimated completion time of an activity.
PMI :
A point in time associated with a schedule activity’s completion.
Finish Float
AACEi :
The amount of time between early finish and late finish dates.
Finish-To-Finish (FF)
AACEi :
A relationship where a successor can finish only after its predecessor finishes.
PMI :
A logical relationship where a successor cannot finish until a predecessor finishes.
Finish-To-Finish Lag
AACEi :
The minimum time between the finish of one activity and the finish of its successor.
Finish-To-Start (FS)
AACEi :
A relationship where a successor can start only after the predecessor finishes.
PMI :
The most common logical relationship in scheduling.
Finish-To-Start Lag
AACEi :
The minimum time between the finish of one activity and the start of its successor.
Finished Goods
AACEi :
Products that require no further processing and are ready for sale or use.
Firm-Fixed-Price Contract (FFP)
PMI :
A contract where the buyer pays a set price regardless of seller costs.
First Cost
AACEi :
All costs incurred to place a facility into service. Syn.: Initial Cost; Initial Investment Cost.
First Event Number
AACEi :
The earliest event number defining the start of a work package in the network.
Fishbone Diagram
PMI :
A cause-and-effect diagram used to trace an undesirable effect back to its root causes.
Fixed Cost
AACEi :
Costs independent of short-term output variations, such as overhead and administration.
Fixed Date
AACEi :
A calendar date that cannot be moved within the schedule.
Fixed Formula Method
PMI :
An earned value method assigning budget value at start and completion milestones.
Fixed Price Contract
PMI :
A contract that sets payment for a defined scope regardless of actual cost.
Fixed Price With Economic Price Adjustment (FP-EPA)
PMI :
A fixed-price contract allowing predefined price adjustments due to economic changes.
Fixed Start
AACEi :
Syn.: Imposed Start Date.
Fixed-Duration Scheduling
AACEi :
A scheduling method where duration remains constant regardless of resources assigned.
Fixed-Price-Incentive-Fee Contract
PMI :
A contract where the seller can earn incentives for meeting performance targets.
Float
AACEi :
The amount of time an activity can slip before impacting project completion.
PMI :
Also called slack.
Float Path
AACEi :
A sequence of activities sharing the same float and acting as a unit.
Float Trend Charts
AACEi :
Charts showing changes in float values over time.
Flow Diagram
AACEi :
A graphical representation of process sequence and operations.
PMI :
A diagram showing inputs, processes, and outputs.
Focus Groups
PMI :
An elicitation technique using prequalified stakeholders to gather expectations and attitudes.
Follow-On Work
AACEi :
Work expected to result from current project activities.
Forecast
AACEi :
An estimate or prediction of future conditions.
PMI :
A prediction of future project performance.
Forecasting
AACEi :
The work performed to estimate or predict future conditions and events.
Formal Reprogramming
AACEi :
Restructuring the earned value performance measurement baseline.
Forward Pass
AACEi :
Network calculation determining early start and finish dates.
PMI :
A CPM technique working forward through the schedule.
Fragnet
AACEi :
A fragment of a CPM network used for detailed control or illustrating changes.
Free Float
AACEi :
Delay allowed without impacting successor activities.
PMI :
Delay allowed without violating constraints.
Free Haul
AACEi :
The distance excavated material may be moved without additional cost.
Free Slack
AACEi :
Time a task without successors can be delayed without affecting project finish.
Fringe Benefits
AACEi :
Employee welfare benefits such as leave, insurance, and retirement.
Front End
AACEi :
Syn.: Definition Phase; Development Phase; Planning Phase.
Front End Loading (FEL)
AACEi :
Defining scope and plans to support informed project decisions.
Front End Schedule
AACEi :
An early-stage project schedule, often a bar chart.
Function
AACEi :
An expression of conceptual relationships used in modeling.
Functional Manager
PMI :
A manager responsible for a functional organizational unit.
Functional Organization
PMI :
A hierarchical organization grouped by specialization.
Functional Replacement Cost
AACEi :
The cost to acquire equivalent service potential.
Functional System
AACEi :
An assembly of components serving a primary end use.
Functional Use Area
AACEi :
The net usable area excluding circulation and support spaces.
Functional Worth
AACEi :
The lowest overall cost for performing a function.
Functional Worth, Cost Value
AACEi :
The monetary sum of all costs to produce a product or service.
Functional Worth, Exchange Value
AACEi :
The monetary amount at which a product or service can be traded.
Functional Worth, Use Value
AACEi :
The monetary measure of functional performance properties.
Functional Worth, Esteem Value
AACEi :
The monetary measure of desirability unrelated to functional performance.
Funding
APM :
The means by which capital is secured and made available.
Funding Limit Reconciliation
PMI :
The comparison of planned expenditures against funding limits.
Future Value
AACEi :
The value of a cost or benefit at a future time considering time value of money.
Future Worth
AACEi :
Syn.: Future Value.
Gantt Chart
AACEi :
A time-scaled bar chart named after Henry L. Gantt.
APM :
A graphical representation of activity against time. Variations may include information such as actual vs. planned, resource usage, and dependencies.
PMI :
A bar chart of schedule information where activities are listed on the vertical axis, dates on the horizontal axis, and durations shown as horizontal bars.
Gate
APM :
The point between phases, gates, and/or tranches where a go/no-go decision can be made about the remainder of the work.
General & Administrative Costs (G&A)
AACEi :
The fixed costs incurred in operating a business, including office, plant, equipment, staffing, and related expenses not attributable to a specific project. Syn.: Administrative Cost.
General Requirements
AACEi :
Non-technical specifications defining scope of work, payments, procedures, implementation constraints, and other contract-related conditions.
General Terms And Conditions
AACEi :
(1) Contract provisions not specific to a particular transaction but applicable to all transactions.
(2) Definitions of legal relationships, responsibilities, and administrative requirements between contracting parties.
Generally Accepted Accounting Principles (GAAP)
AACEi :
Accounting principles established by the Financial Accounting Standards Board that form the foundation for acceptable accounting practices.
Given Year
AACEi :
The year or period selected for comparison relative to a base year or base period.
Global Calendar
AACEi :
The default calendar defining the typical workweek, workdays, and holidays used for scheduling activities.
Go/No Go
APM :
A control decision determining whether work should continue or stop.
Governance
APM :
The framework of policies, processes, roles, and responsibilities used to direct and control projects, programmes, or portfolios.
Grade
PMI :
A category distinguishing items with the same functional use but differing quality requirements.
Graphical Evaluation And Review Technique (GERT)
AACEi :
A network analysis technique allowing conditional and probabilistic logic where some activities may or may not occur.
Gross Area
AACEi :
The total enclosed floor or slab area of a project measured to the exterior building envelope.
Gross Concurrency
AACEi :
A method of counting concurrent delay events based solely on contemporaneous occurrence without applying CPM principles.
Gross National Product (GNP)
AACEi :
The total national output of goods and services at market prices for a given year.
Ground Rules
PMI :
Agreed expectations regarding acceptable behavior of project team members.
Group Creativity Techniques
PMI :
Techniques used by groups of stakeholders to generate ideas.
Group Decision Making Techniques
AACEi :
Techniques used to generate, evaluate, classify, and prioritize alternatives or requirements.
Guideline
AACEi :
A recommended method of working that is customary but not mandatory.
PMI :
An official recommendation indicating policies, standards, or procedures for accomplishing objectives.
Hammock Activity
AACEi :
An aggregate or summary activity that derives its duration from the time difference between two connected points. It does not affect the schedule dates of the activities it spans.
APM :
A group of related schedule activities aggregated and displayed as a single activity.
Handover
APM :
The point in the life cycle where deliverables are handed over to the sponsor and users.
Hanger
AACEi :
An unintended break in a network path.
Hard Logic
PMI :
A relationship that is contractually required or inherent in the nature of the work.
Haul Distance
AACEi :
The average distance material is moved, measured along the most direct practical route between excavation and placement.
Health And Safety Management
APM :
The process of identifying and minimizing threats to workers and others throughout the project, programme, or portfolio life cycle.
Hedge
AACEi :
In master production scheduling, a stock quantity used to protect against demand uncertainty, incorporating both timing and quantity.
Heuristic
AACEi :
An experience-based technique used for problem solving, e.g., a rule of thumb.
Hierarchical Coding Structure
AACEi :
A multi-level coding system where each code (except the top level) has a parent code.
Hierarchical Planning
AACEi :
A planning approach where objectives are set at higher levels and progressively broken down by lower management levels.
Hierarchy (Hierarchical)
AACEi :
A ranking of items according to their logical relationships.
Highest And Best Use
AACEi :
A valuation concept identifying the most profitable likely use of a property after considering all feasible uses.
Histogram
PMI :
A bar chart used to describe the distribution, dispersion, and shape of statistical data.
Historic Records
AACEi :
Documentation from past projects used to predict trends, assess feasibility, and identify risks in future projects.
Historical Database
AACEi :
Stored records of past project experience used for planning, estimating, forecasting, validation, and benchmarking.
Historical Information
PMI :
Documents and data from prior projects, including files, correspondence, contracts, and project archives.
Holding Time
AACEi :
The time an item is non-operational to allow servicing.
Holiday
AACEi :
An otherwise valid working day designated as non-working, typically recurring annually.
Home Office Cost
AACEi :
Business operation costs not incurred at the project site but assignable to projects, such as engineering, procurement, legal, estimating, and administration.
Host Organization
APM :
The organization providing strategic direction and receiving the primary benefits of the project, programme, or portfolio.
Human Resource Management
APM :
Managing people-related activities to achieve organizational goals.
PMI :
Processes that organize, manage, and lead the project team.
Human Resource Management Plan
PMI :
A component of the project management plan describing roles, responsibilities, reporting relationships, and staff management.
Hypercritical
AACEi :
A condition where imposed dates create negative float, making the critical path impossible to meet without schedule compression.
Hypercritical Activities
AACEi :
Critical path activities with negative float, typically caused by imposed constraints or target dates.
I-J Notation
AACEi :
A system of numbering nodes in an activity-on-arrow network. The I-node is always the beginning of the activity, while the J-node is always the finish.
I-Node
AACEi :
In an activity on arrow (AOA) schedule, the node at the beginning of the activity arrow.
Iatrogenic Risk
AACEi :
In a risk analysis, an understatement of true risk caused by faulty risk analysis practices including, but not limited to: failing to identify significant threats risks and/or opportunities, assigning probability density functions to too many elements in a Monte Carlo Analysis or range estimate, incorrectly assuming independence between input elements for risk analysis simulations, and failing to adequately quantify the ranges of input elements. Syn.: Analyst-Caused Risk; Analyst-Induced Risk.
Idea/Mind Mapping
PMI :
Technique used to consolidate ideas created through individual instorming sessions into a single map to reflect commonality and differences in understanding and to generate new ideas.
Identifier
AACEi :
An alphanumeric code depicting a name or hierarchy.
Identify Stakeholders
PMI :
The process of identifying the people, groups, or organizations that could impact or be impacted by a decision, activity, or outcome of the project; and analyzing and documenting relevant information regarding their interests, involvement, interdependencies, influence, and potential impact on project success.
Idle Equipment Cost
AACEi :
The cost of equipment that remains on site ready for use but is placed in a standby basis. Ownership or rental costs are still incurred while the equipment is idle.
Idle Time
AACEi :
A time interval during which either the worker, the equipment or both do not perform useful work.
Immediate Activity
AACEi :
An activity that can be forced to start on its earliest feasible date by resource scheduling, even if that means overloading a resource.
Impact
AACEi :
Syn.: Consequence; Effect.
Impact Cost
AACEi :
Added expenses due to the indirect results of a changed condition, delay, or changes that are a consequence of the initial event. Examples of these costs are premium time, lost efficiency, and extended field and home office overhead. Syn.: Damages, Ripple.
Impact Versus Probability Rating
AACEi :
Syn.: Risk Matrix.
Imperfect Information
AACEi :
Information or data for which there exists some uncertainty.
Imperfection
AACEi :
A deviation that does not affect the use or performance of the product, process, or service. In practice, imperfections are deviations that are accepted as-is.
Imposed Date
AACEi :
(1) A predetermined calendar date set (usually externally) without regard to logical considerations of the network.
(2) A date externally assigned to an activity that establishes the earliest or latest date in which the activity is allowed to start or finish.
PMI :
A fixed date imposed on a schedule activity or schedule milestone, usually in the form of a “start no earlier than” and “finish no later than” date.
Imposed Finish Date
AACEi :
A predetermined calendar date set without regard to logical considerations of the network, fixing the end of an activity and all other activities preceding that ending node.
Imposed Start Date
AACEi :
A start date imposed on an activity by an external constraint. Syn.: Fixed Start.
Impossibility
AACEI :
An inability to meet contract requirements because it was in fact physically impossible to do so (actual impossibility).
Impracticability
AACEi :
Inability to perform because of extreme and unreasonable difficulty, expense, injury, or loss involved. This is sometimes considered practical impossibility.
Imputation (Of Price Movement)
AACEi :
The assignment of known price changes to a certain commodity on the basis of the assumed similarity of price movement.
In-Place Value
AACEi :
Value of a physical property, e.g., market value plus costs of transportation to site and installation.
In-Progress Activity
AACEi :
An activity that has been started but not completed on a given reporting/data date.
In-Progress Inventory
AACEi :
Syn.: Work-In-Process.
Incentive Fee
PMI :
A set of financial incentives related to cost, schedule, or technical performance of the seller.
Inclusive Or Relationship
AACEi :
Logical relationship indicating that at least one, but not necessarily all, of the activities have to be undertaken.
Income
AACEi :
Used interchangeably with profit. Avoid using income instead of sales revenue.
Incremental Cost (Benefit)
AACEi :
The additional cost (benefit) resulting from an increase in the investment in a project. Syn.: Marginal Cost (Benefit).
Incremental Life Cycle
PMI :
A project life cycle where the project scope is generally determined early, but time and cost estimates are routinely modified as understanding of the product increases.
Incremental Milestone Technique
AACEi :
An earned value technique that pre-assigns budget to technical milestone completions. When the milestone is completed, 100% of the assigned budget is earned.
Independent Estimate
PMI :
A process of using a third party to obtain and analyze information to support prediction of cost, schedule, or other items.
Independent Estimate At Completion (IEAC)
AACEi :
A calculation of the final estimated cost for a project based on earned value efficiency rates such as CPI and SPI.
Independent Estimate At Completion [IEAC(T)]
AACEi :
In earned schedule, the difference between the baseline project duration and the estimated project duration in time units.
Independent Event
AACEi :
An event that does not affect the probability of the occurrence of another event.
Independent Float
AACEi :
The flexibility an activity has that does not affect float on preceding or succeeding activities.
Independent Variable
AACEi :
An event or condition whose probability or impact does not depend on any other variable.
Indicated Total Cost
AACEi :
An estimated final cost based on current progress and forecast effort to complete.
Indirect Costs
AACEi :
Costs not directly attributable to an activity and allocated across the project on a predetermined basis.
Indirect Pacing
AACEi :
When a paced event lacks a logical relationship to the parent delay and coincides only due to schedule timing.
Individual Price Index
AACEi :
An index measuring price changes for a specific commodity over time.
Individual Work Plan
AACEi :
The lowest level of a technical plan defining tasks and responsibilities of an individual team member.
Inefficiency
AACEi :
A state of being less productive than planned. Syn.: Loss of Productivity/Efficiency.
Inexcusable Delays
AACEi :
Delays caused by contractor negligence, often resulting in penalties.
Inflation
AACEi :
A sustained increase in price levels or a decrease in the purchasing power of money.
Influence Diagram
AACEi :
A graphical display of the relationships among factors influencing a decision.
PMI :
A graphical representation of situations showing causal influences, time ordering of events, and other relationships among variables and outcomes.
Influencing
APM :
The act of affecting the behaviours and actions of others.
Information Gathering Techniques
PMI :
Repeatable processes used to assemble and organize data across a spectrum of sources.
Information Management
APM :
The collection, storage, dissemination, archiving and destruction of information.
PMI :
Facilities, processes, and procedures used to collect, store, and distribute information.
Infrastructure
APM :
Provides support for projects, programmes and portfolios, and is the focal point for the development and maintenance of P3 management within an organisation.
Inherent Risk
AACEi :
A risk that exists due to the nature of the asset, project, task, or situation.
Initial
APM :
The first level of a maturity model where processes are ad hoc and occasionally chaotic.
Initial Cost
AACEi :
Syn.: First Cost; Initial Investment Cost.
Initial Investment Cost
AACEi :
Syn.: First Cost; Initial Cost.
Initiation
AACEi :
The process of preparing for and starting work.
PMI :
Processes performed to define a new project or phase and obtain authorization.
Input
PMI :
Any item required by a process before it proceeds.
Input Milestones
AACEi :
Imposed target dates or events that control the plan with respect to time.
Input-Output Analysis
AACEi :
A matrix providing a quantitative framework for describing an economic unit.
Inspection
PMI :
Examining to verify conformity to specified requirements.
Inspection And Audits
PMI :
Observing contracted work or products against agreed requirements.
Intangibles
AACEi :
Factors or assets that cannot be readily evaluated quantitatively.
Integrated Assurance
APM :
The coordination of assurance activities among multiple providers.
Integrated Baseline Review (IBR)
PCI :
A review verifying technical content, budgets, schedules, and inherent risks.
Integrated Change Control
AACEi :
Reviewing, approving, and controlling changes to deliverables.
Integrated Cost/Schedule Reporting
AACEi :
Reporting that measures actual versus budget and schedule performance.
Integrated Master Schedule (IMS)
PCI :
A schedule defining tasks and milestones and mapping to the CWBS.
Integrated Product Teams (IPT)
AACEi :
Cross-functional teams responsible for segments of the WBS.
Integrative Management
APM :
Management processes integrating scope, schedule, cost, risk, and resources.
Interdependent Event
AACEi :
An event whose occurrence is related to another event.
Interest Rate
AACEi :
The ratio of interest payment to principal over time.
Interest Rate Of Return
AACEi :
Syn.: Profitability Index (PI).
Interest Rate, Compound
AACEi :
Interest earned as a percentage of the unpaid balance.
Interest Rate, Effective
AACEi :
An equivalent annual interest rate considering compounding.
Interest Rate, Nominal
AACEi :
An annual interest rate without consideration of compounding.
Interest
AACEi :
Compensation for the use of capital; time value of money.
Interface
AACEi :
A common physical or functional boundary between entities.
Interface Activity
AACEi :
An activity connecting nodes between sub-networks.
Interface Management
AACEi :
Managing coordination and responsibility across boundaries.
Interface Node
AACEi :
A common node representing logical interdependence.
Interference
AACEi :
Conduct that interrupts normal operations and performance.
Interim Dates
AACEi :
Established dates for partial completion milestones.
Interim Deliverables
AACEi :
Deliverables produced prior to the final deliverable.
Intermediate Events
AACEi :
Events necessary to complete a major milestone.
Intermediate Materials
AACEi :
Processed materials requiring further processing.
Intermediate Node
AACEi :
A node where activities both begin and end.
Internal Rate Of Return (IRR)
AACEi :
The discount rate that equalizes project costs and benefits.
Interpersonal Skills
APM :
How people relate to and interact with others.
PMI :
Ability to establish and maintain relationships.
Interrelationship Digraphs
PMI :
A quality planning tool for creative problem-solving.
Interruption
AACEi :
A stopping or hindering of normal activity flow.
Interviews
PMI :
Eliciting information from stakeholders by direct discussion.
Inventory
AACEi :
Raw materials, work-in-process, and finished goods.
Investment Appraisal
APM :
Techniques used to assess the attractiveness of an investment.
Investment Cost
AACEi :
Includes first cost and later expenditures that have substantial and enduring value (generally more than one year) for upgrading, expanding, or changing the functional use of a facility, product, or process. [1]
Investment
AACEi :
The sum of the original costs or values of the items that constitute the enterprise; used interchangeably with capital; may include expenses associated with capital outlays such as mine development.
Investor's Method
AACEi :
Syn.: Discounted Cash Flow.
Invitation For Bid (IFB)
PMI :
Generally, this term is equivalent to request for proposal. However, in some application areas, it may have a narrower or more specific meaning.
Irrefutable Logic
AACEi :
Network logic that is rational and compelling and cannot be disputed on the basis of reason.
Ishikawa Diagram
AACEi :
Diagram used to illustrate how various causes and sub-causes create a specific effect. Named after its developer Kaoru Ishikawa. Also called cause-and-effect diagram or fishbone diagram. [8]
Issue Log
PMI :
A project document used to document and monitor elements under discussion or in dispute between project stakeholders.
Issues Management
AACEi :
Management of issues that remain unresolved because they are either in dispute, are uncertain, lack information, or lack authority or commitment for their resolution.
Issue
AACEi :
In risk management, a risk that has occurred or an unplanned question or decision that needs to be addressed by a process other than risk management.
APM :
A formal issue occurs when the tolerances of delegated work are predicted to be exceeded or have been exceeded. This triggers the escalation of the issue from one level of management to the next in order to seek a solution.
PMI :
A point or matter in question or in dispute, or a point or matter that is not settled and is under discussion or over which there are opposing views or disagreements.
Iterative Life Cycle
PMI :
A project life cycle where the project scope is generally determined early in the project life cycle, but time and cost estimates are routinely modified as the project team’s understanding of the product increases. Iterations develop the product through a series of repeated cycles, while increments successively add to the functionality of the product.
J-Node
AACEi :
In an activity on arrow (AOA) schedule, the node at the end of the activity arrow.
Job
AACEi :
A group of contiguous operations related by similarity of functions that can be completed by one or more workers without interference or delay.
Joint Surveillance
PCI :
Programme surveillance conducted by the company and customer together in the same review.
Judgmental Sampling
AACEi :
A procedure of selecting the sample based on specific criteria established by sample designers. The selection of priced items and outlets is not a probability sample, i.e., it is not based on random chance.
Junior Float
AACEi :
The lowest free float of all preceding activities.
Just-In-Time
AACEi :
A “pull” logistical system driven by actual demand. The goal is to produce, provide, or deliver parts or supplies just in time for the next operation. The approach reduces stock inventories or storage costs but leaves no room for error. It is as much a managerial philosophy as it is an inventory system.
Key Activity
AACEi :
An activity that is considered of major significance. A key activity is sometimes referred to as a milestone activity.
Key Event Schedule
AACEi :
A schedule comprised of key events or milestones. These events are generally critical accomplishments planned at time intervals throughout the project and used as a basis to monitor overall project performance. The format may be either network or bar chart and may contain minimal detail at a highly summarized level. This is often referred to as a milestone schedule.
Key Events
AACEi :
Major events the achievement of which are deemed to be critical to the execution of the project. A key event is sometimes referred to as a milestone.
Key Performance
AACEi :
Performance that is critical to the project or a project system.
Key Performance Indicators (KPI)
AACEi :
Indicators that: (1) are determined at process or project initiation and listed in order of priority; (2) reflect directly on key process or project objectives (goals); and (3) provide a basis for trade-off decisions made during execution. At process or project completion, these KPIs: (1) will be the most relevant measures to confirm acceptability and success; and (2) can be reasonably measured with an acceptable level of confidence.
Syn.: Key Success Indicators (KSI).
Key Success Indicators (KSI)
AACEi :
Syn.: Key Performance Indicators (KPI).
Knowledge Management
APM :
The systematic management of information and learning. It turns personal information and experience into collective knowledge that can be widely shared throughout an organisation and a profession.
Known
AACEi :
A quantity or condition characterized by certainty.
Known-Unknown
AACEi :
An identifiable quantity or value having variability or an identifiable condition lacking certainty.
Labor
AACEi :
Effort expended by people for wages or salary. Generally classified as either direct or indirect. Direct labor is applied to meeting project objectives and is a principal element used in costing, pricing, and profit determination; indirect labor is a component of indirect cost, such as overhead or general and administrative costs. [8]
Labor Burden
AACEi :
Fringe benefits plus taxes and insurances the employer is required to pay by law based on labor payroll, on behalf of or for the benefit of labor. (In some countries, these include government retirement benefits, unemployment insurance tax, and worker's compensation).
Syn.: Payroll Burden.
Labor Cost, All In Labor
AACEi :
Gross direct wages paid to the worker, plus labor burden, plus field indirects, plus general & administrative cost, plus profit.
Labor Cost, Bare Labor
AACEi :
Gross direct wages paid to the worker.
Labor Cost, Burdened Labor
AACEi :
Gross direct wages paid to the worker, plus labor burden.
Labor Efficiency Variance
AACEi :
A cost variance can be broken into efficiency and rate variance elements. Efficiency is calculated as:
(budgeted cost of work performed rate) × (budgeted cost of work performed hours).
Labor Hour
AACEi :
A worker hour of effort.
Syn.: Work-Hour.
Labor Norm
AACEi :
Syn.: Labor Productivity Norm.
Labor Norm Preamble
AACEi :
A narrative to precisely describe the content (inclusion and exclusions), the normal conditions, the unit of measurement, and method of measurement of an activity and its applicable labor norm.
Labor Productivity
AACEi :
A measure of production output relative to labor input. In economics, industrial engineering, and earned value management, quantity/work hour measures are common (higher values reflect higher productivity or efficiency). In cost estimating, inverse measures such as work hours/quantity or unit hours are common (where lower values reflect higher productivity or efficiency). Regardless of the measure used, labor productivity (or efficiency) is improved by increasing production for a given work hour or decreasing work hours for a given production.
Labor Productivity Factor
AACEi :
A value by which a labor productivity measure for a reference project or activity is multiplied to obtain an adjusted productivity measure for the same or similar project or activity under a different set of conditions. Proper factor use requires that the user ascertain the type of labor productivity measure it will be applied against.
Syn.: Productivity Factor.
Labor Productivity Norm
AACEi :
A standard labor productivity value used as a reference for estimating, measuring, or comparing labor performance under defined conditions.
Labor Rate
AACEi :
Labor cost expressed on a per unit of labor effort basis (e.g., labor costs per labor hour).
Labor Rate Variance
AACEi :
A cost variance can be broken into efficiency and rate variance elements. Rate variance is calculated as:
(budgeted cost of work performed hours) × (budgeted cost of work performed rate – actual cost of work performed rate).
Ladder
AACEi :
In planning and scheduling, a sequence of parallel activities connected at their starts or finishes, or both. The start and finish of each succeeding activity are linked only to the start and finish of the preceding activity by lead and lag activities, which consume only time.
Ladder Activity
AACEi :
A type of activity identified in network scheduling. An arrangement in which two or more series of activities progress concurrently but in lockstep because of dependent links between the same rungs of each ladder.
Laddering
AACEi :
A method of showing the logic relationship of a set of several parallel activities with the arrow technique.
Lag
AACEi :
Time that an activity follows, or is delayed from the start or finish of its predecessor(s). Sometimes called an offset. A lag may have a negative value tied to the finish of a previous activity, reflecting a fast-track approach.
PMI :
The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.
Lag Relationship
AACEi :
The four basic types of lag relationships between activities are:
1) Finish-to-Start (FS);
2) Start-to-Finish (SF);
3) Finish-to-Finish (FF);
4) Start-to-Start (SS).
Lag Time
AACEi :
The amount of time delay between the completion of one task and the start of its successor task.
Late Finish (LF)
AACEi :
The latest date or time an activity may finish as calculated by the backward pass.
PMI :
Late Finish Date (LF): In the critical path method, the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, the project completion date, and any schedule constraints.
Late Start (LS)
AACEi :
The latest date or time an activity may start so the project may be completed on time as calculated during the backward pass.
PMI :
Late Start Date (LS): The latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic, the project completion date, and any schedule constraints.
Latest Revised Estimate
AACEi :
In earned value, the sum of the actual incurred costs plus the latest estimate-to-complete for a work package or summary item as currently reviewed and revised, or both (including applicable overhead where direct costs are specified).
Latin Hypercube Method
AACEi :
A stratified random sampling technique similar to the Monte Carlo method, which converges with fewer samples.
Laws And Regulations
AACEi :
Laws, rules, regulations, ordinances, codes and/or orders.
APM :
Law: The relevant legal duties, rights and processes that should be applied to projects, programmes and portfolios.
PMI :
Regulation: Requirements imposed by a governmental body. These requirements can establish product, process, or service characteristics, including applicable administrative provisions that have government-mandated compliance.
Lead
AACEi :
Time that an activity precedes the start of its successor(s). Lead is the opposite of Lag.
PMI :
The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Lead Duration / Lead Time
AACEi :
A duration or time by which a given task must be started before the succeeding activity can begin.
Leadership
APM :
The ability to establish vision and direction, to influence and align others towards a common purpose, and to empower and inspire people to achieve success.
Learning And Development
APM :
The continual improvement of competence at all levels of an organisation.
Learning Curve
AACEi :
A graphic representation of the progress in production effectiveness as time passes. Learning curves are useful planning tools, particularly in project-oriented industries where new products and workers are phased in frequently. The basis for the learning curve calculation is that workers perform work more quickly as experience increases.
Lessons Learned
AACEi :
A project team's learning, usually defined during closeout. Should be limited to capturing or identifying work process improvements. A finding that established policies or procedures were not followed is not a valid lesson learned.
APM :
Documented experiences that can be used to improve the future management of projects, programmes and portfolios.
PMI :
The knowledge gained during a project which shows how project events were addressed or should be addressed in the future with the purpose of improving future performance.
Lessons Learned Knowledge Base
PMI :
A store of historical information and lessons learned about both the outcomes of previous project selection decisions and previous project performance.
Letter Of Credit
AACEi :
A vehicle used in lieu of retention and purchased by the contractor from a bank for a predetermined amount of credit that the owner may draw against in the event of default in acceptance criteria by the contractor. Also applies when an owner establishes a line of credit in a foreign country to provide payment to suppliers for goods and services.
Level Finish / Schedule (FS)
AACEi :
The date when the activity is scheduled to be completed using the resource allocation process.
Level Float
AACEi :
The difference between the level finish and the late finish date.
Level Of Detail
AACEi :
The required degree of detail for estimates, accounting reports, cost reports, and schedules. It is generally constrained by the level of scope definition and should support project execution and historical data needs.
Level Of Effort (LOE)
AACEi :
Support effort that does not readily lend itself to measurement of discrete accomplishment and is generally characterized by a uniform rate of activity over a specific period of time.
PMI :
An activity that does not produce definitive end products and is measured by the passage of time.
Level Start / Schedule (SS)
AACEi :
The date the activity is scheduled to begin using the resource allocation process. This date is equal to or later than early start.
Leveling
AACEi :
Syn.: Resource Leveling; Resource Optimization.
PMI :
A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Levelized Fixed-Charge Rate
AACEi :
The ratio of uniform annual revenue requirements to the initial investment, expressed as a percent.
Levels Of Schedules
AACEi :
Schedules differentiated by degree of detail. The three main levels are Management Summary, Project Level, and Control Level.
Levels Of Schedules, Control Level Schedule (Level 3)
AACEi :
Detailed schedules showing individual work tasks, typically maintained by discipline leads or contractors and used for near-term execution and field management.
Levels Of Schedules, Management Summary Schedule (Level 1)
AACEi :
The highest-level schedule with the least detail, used by management and clients to monitor overall project status.
Levels Of Schedules, Project Level Schedule (Level 2)
AACEi :
An activity- and deliverable-centered schedule integrating engineering, procurement, and construction using network logic and CPM techniques.
Leverage (Trading On Equity)
AACEi :
The use of borrowed funds or preferred stock to increase the return on equity by earning a rate higher than the cost of the borrowed funds.
Life Cycle
AACEi :
The stages or phases occurring during the lifetime of an object or endeavor.
APM :
The inter-related phases of a project, programme or portfolio that provide a structure for governing work.
PMI :
Project Life Cycle: The series of phases a project passes through from initiation to closure.
Life Cycle Cost (LCC) Method
AACEi :
A technique of economic evaluation that sums costs of investment, replacements, operations, and maintenance over a defined study period.
Life Cycle Costing
AACEi :
Consideration of all costs from concept through disposal when designing a project’s product.
Life Cycle Value Analysis (LCVA)
AACEi :
A methodology that analyzes impacts on valuation over the life cycle of a project or asset to identify improvement opportunities.
Life Cycle, Asset Life Cycle
AACEi :
The stages of asset existence, typically including ideation, creation, operation, modification, and termination.
Syn.: Economic Life Cycle.
Life Cycle, Project Life Cycle
AACEi :
The stages or phases of project progress during the life of a project, typically including ideation, planning, execution, and closure.
Syn.: Project Life.
Life Cycle, Product Life Cycle
AACEi :
Complete history of a product through its concept, definition, production, operation, and obsolescence or disposal phases. The distinction between product life cycle and project life cycle is that the latter does not include the last two phases.
Life, Physical
AACEi :
That period of time after which a machine or facility can no longer be repaired in order to perform its design function properly.
Life, Service
AACEi :
The period of time that a machine or facility will satisfactorily perform its function without a major overhaul.
LIFO (Last In, First Out)
AACEi :
A method of determining the cost of inventory used in a product. In this method, the costs of material are transferred to the product in reverse chronological order. LIFO is used to describe the movement of goods.
LIMIT (Lot Size Inventory Management Interpolation Technique)
AACEi :
A technique for looking at the lot sizes for groups of products to determine what effect economic lot sizes will have on the total inventory and total setup costs.
Line Of Balance (LOB)
AACEi :
A graphical display of scheduled units versus actual units over a given set of critical schedule control points on a particular day. The line of balance technique is oriented towards the control of production activities.
APM :
A scheduling technique for delivery of repetitive products that shows how resource teams move from product to product rather than the detail of individual activities.
Line Of Credit
AACEi :
Generally an informal understanding between the borrower and the bank as to the maximum amount of credit that the bank will provide the borrower at any one time.
Linear Programming
AACEi :
Mathematical techniques for solving optimization problems by minimizing or maximizing a linear function subject to linear constraints.
Linear Responsibility Chart
AACEi :
A special matrix listing functions or tasks against responsible roles, indicating the level or type of responsibility at each intersection.
Linear Scheduling Method (LSM)
AACEi :
A scheduling method used primarily for horizontal and repetitive projects such as highways and pipelines, using velocity-based diagrams.
Linear Sequential Model
APM :
A type of life cycle where phases are sequential.
Link
AACEi :
A dependency between tasks that specifies when a task begins or ends relative to another task.
Linked Bar Chart
AACEi :
A bar chart drawn to show dependency links between activities or tasks.
Linked Projects
AACEi :
Multiple related projects connected at interface points, often shown using dependency-linked bar charts.
Linking Procedure
AACEi :
A procedure for connecting a new series of indexes to an old series during a link period due to changes in baskets or structure.
Liquidated Damages
AACEi :
Syn.: Damages, Liquidated.
Lmeso
AACEi :
Syn.: Cost Estimate Resource.
Load Factor
AACEi :
The ratio of average load to maximum demand, usually expressed as a percentage.
Load Leveling
AACEi :
The technique of averaging resource usage over time to ensure stable and workable deployment.
Syn.: Work Power Leveling.
Local Cost
AACEi :
The cost of local labor, equipment, taxes, insurance, and materials incorporated in a construction project using local currency.
Location Factor
AACEi :
An overall project factor used to translate project costs from one geographic location to another.
Log
PMI :
A document used to record and track selected items during project execution.
Logic
AACEi :
The relationship describing the interdependency of activity starts and finishes in a schedule network.
Logic Constraint
AACEi :
A restraint defining dependency relationships between activities in an AOA network.
Logic Diagram
AACEi :
A graphic diagram showing relationships between activities, predecessors, and successors.
Syn.: Logic Network Diagram; Network Diagram.
Logic Network
AACEi :
Syn.: Network.
Logic Network Diagram
AACEi :
Syn.: Logic Diagram; Network Diagram.
Logic Restraint
AACEi :
A dummy or constraint connection used as a logical connector that does not represent actual work.
Logic Sequencing
AACEi :
The arranging of project activities into a logical and progressive order.
Logic, Dynamic (Conditional)
AACEi :
A logic structure that allows schedule changes based on risk events or conditions.
Logic, Hard
AACEi :
Mandatory logic defined by work scope and physical constraints.
Logic, Soft
AACEi :
Logic that cannot initially be modeled in detail and evolves into hard logic as project definition improves.
PMI :
A relationship based on best practices or preferred sequencing.
Logic, Static (Fixed)
AACEi :
A logic structure that does not allow for conditional changes.
Long Lead Items
AACEi :
Components requiring the longest design or fabrication times and early funding commitment.
Long Lead Procurement
AACEi :
Early procurement of materials to accommodate long delivery periods.
Longest Path (LP)
AACEi :
The longest continuous chain of driving activities determining the earliest project completion.
Longest Path Value
AACEi :
A numeric value indicating how close an activity is to being on the longest path.
Look-Ahead Schedule
AACEi :
A short-term schedule showing near-term work required to maintain overall project progress.
Loop / Logic Loop
AACEi :
A circular dependency in a schedule network that creates a logic error.
Loss Of Productivity / Efficiency
AACEi :
Syn.: Inefficiency.
Lost Productivity
AACEi :
Syn.: Inefficiency.
Lot Batch
AACEi :
A definite quantity of product manufactured under uniform conditions.
Lot Size
AACEi :
The number of units in a lot.
Lowest Management Level (LML)
AACEi :
The lowest organizational level capable of managing dynamic project baselines.
Lowest Static Baseline (LSB)
AACEi :
The lowest relatively fixed baseline against which project success can realistically be measured.
Lump-Sum
AACEi :
The complete in-place cost of a system, subsystem, or entire project.
Maintenance And Repair Cost
AACEi :
The total of labor, material, and other related costs incurred in conducting corrective and preventative maintenance and repair on a facility, its systems and components, or both. Maintenance does not usually include items that cannot be expended within the year purchased; such items are considered fixed capital.
Major Components
AACEi :
Part of the aggregation structure of a price index (e.g., CPI components such as food, housing, transportation, health care, etc.).
Major Milestone
AACEi :
The most significant milestones in a project’s life, representing major accomplishments or decision points, usually aligned with the first level of the work breakdown structure.
Major System Acquisition Projects
AACEi :
Projects critical to fulfilling a mission, involving large resource allocations and requiring special management attention.
Majority
PMI :
Support from more than 50 percent of the members of a group.
Make-Or-Buy Analysis
PMI :
The process of analyzing whether a product should be manufactured internally or purchased externally.
Make-Or-Buy Decisions
PMI :
Decisions regarding the external purchase or internal manufacture of a product.
Manage Communication
PMI :
The process of creating, collecting, distributing, storing, retrieving, and disposing of project information in accordance with the communications management plan.
Manage Project Team
PMI :
The process of tracking team performance, providing feedback, resolving issues, and managing changes to optimize project performance.
Manage Stakeholder Engagement
PMI :
The process of working with stakeholders to meet expectations, address issues, and foster appropriate engagement throughout the project life cycle.
Managed
APM :
The fourth level of a capability maturity model where metrics are used to control and predict future performance.
Management By Exception
AACEi :
Issuance of management reports only when corrective action is required, reducing information overload but potentially delaying awareness of positive performance.
Management By Methods (MBM)
AACEi :
Level 2 of a five-level dynamic baseline model, focusing on standardized tools, frameworks, and analytical project management methods.
Management By Objectives (MBO)
AACEi :
A management approach based on mutually agreed objectives, representing Level 3 of the dynamic baseline model.
Management By Politics (MBP)
AACEi :
A potential Level 5 management model focused on governance, corporate values, and harmonizing competing agendas.
Management By Rules (MBR)
AACEi :
Level 1 of the dynamic baseline model, emphasizing adherence to organizational rules, procedures, and policies.
Management By Values (MBV)
AACEi :
Level 4 of the dynamic baseline model, where project objectives are adapted in alignment with corporate values.
Management By Walking Around (MBWA)
AACEi :
A management style emphasizing direct engagement with teams through frequent informal interaction.
Management Control Point
AACEi :
A decision point in the project life cycle where senior management approves continuation to the next phase.
Management Control Systems
AACEi :
Systems used to plan, control, and measure project cost and schedule performance.
Management Plan
APM :
A plan defining policies and principles for managing specific aspects of a project, programme, or portfolio.
Management Reserve
AACEi / APM / PMI / PCI :
Budget or funds held outside the performance measurement baseline for management control and unforeseen events.
Management Schedule Reserve (MSR)
AACEi :
A designated amount of time reserved for risks or management discretion not covered by schedule contingency.
Management Science
AACEi :
The application of mathematical and analytical methods to support decision-making in projects and operations.
Management Skills
PMI :
The ability to plan, organize, direct, and control people to achieve defined objectives.
Mandatory Dependency
AACEi / PMI :
A dependency inherent in the nature of the work or contractually required, commonly associated with hard logic.
Manpower Loading Chart
AACEi :
Histogram showing the allocation of labor by period.
Manpower Planning
AACEi :
Process of forecasting an organization's manpower needs over time, in terms of numbers and skills, and obtaining the human resources required to match an organization’s needs.
Manufacturing Cost
AACEi :
The total of variable and fixed or direct and indirect costs chargeable to the production of a given product, usually expressed per unit or per year. Transportation, distribution, R&D, selling, and corporate administrative expenses are usually excluded.
Mapi Method
AACEi :
(1) A procedure for replacement analysis sponsored by the Machinery and Allied Products Institute.
(2) A capital investment analysis method using fixed formats, charts, and graphs, explicitly including obsolescence.
Marginal Analysis
AACEi :
An economic concept concerned with incremental costs and revenues associated directly with a specific course of action.
Marginal Cost (Benefit)
AACEi :
Syn.: Incremental Cost (Benefit).
Mark-Up
AACEi :
Percentage applications in construction estimating such as overhead, profit, and other indirect costs, depending on local practice.
Market Value
AACEi :
The price agreed upon by a willing buyer and seller in a free market, with full knowledge and no compulsion.
Marketing
AACEi :
Activities related to identifying customer needs, satisfying those needs through products or services, and building buyer awareness through sales and advertising.
Marketing Cost Analysis
AACEi :
The evaluation of profitability or cost of marketing operations by customer, product, territory, or activity.
Marketing Research
AACEi :
The systematic gathering, recording, and analysis of data related to marketing problems.
PMI :
The process of gathering information from various sources to identify market capabilities.
Marketing Research, Consumer Research
AACEi :
Focused on discovering and analyzing consumer attitudes, reactions, and preferences.
Marketing Research, Market Analysis
AACEi :
The study of market size, location, nature, and characteristics.
Marketing Research, Sales Analysis (or Research)
AACEi :
Systematic study of sales data by market area, product, customer group, or territory.
Master Production Schedule (MPS)
AACEi :
A statement of what a company plans to manufacture, expressed in quantities, configurations, and dates, and used to drive material requirements planning.
Master Schedule
AACEi :
A consolidated schedule for monitoring and controlling related projects.
PMI :
A summary-level schedule identifying major deliverables and milestones.
Master Schedule Item
AACEi :
A manufacturing item selected for planning due to its critical impact on resources or downstream components.
Master Scheduler
AACEi :
The individual responsible for managing the master schedule.
Material
PMI :
The aggregate of physical resources used by an organization, including equipment, tools, machinery, and supplies.
Material Cost
AACEi :
The cost of all substantial materials required for construction or operation of a facility, including manufactured equipment.
Material Difference
AACEi :
A change that significantly affects work performance, cost, schedule, or procedures.
Material Requirements Planning (MRP)
AACEi :
A system using bills of material, inventory, and schedules to calculate and time-phase material requirements.
Matrix Diagram
PMI :
A quality management tool used to analyze relationships between factors within a matrix structure.
Matrix Organization
PMI :
An organizational structure where project and functional managers share authority.
Maturity Model
APM :
An organizational model describing evolutionary stages of process improvement.
Maximum Out-Of-Pocket Cash
AACEi :
The highest year-end negative cash balance during a project’s life.
Means And Methods
AACEi :
Syn.: Method Of Performance.
Mechanical Completion
AACEi :
Unit is essentially complete for startup operation and test run. All major work is completed. Minor work not interfering with operation may remain incomplete (e.g., punch list items). Acceptance letter will have been submitted to the client. Definition is typically contractual and should be clearly defined.
Merge Bias
AACEi :
In PERT and other deterministic schedule analysis methods, a bias introduced because parallel slack paths contributing risk at merge points are not recognized.
Merge Node
AACEi :
In a network diagram, a node at which two or more activities precede the start of a subsequent activity.
Merit Shop
AACEi :
Syn.: Open Shop.
Metalanguage (Risk)
AACEi :
A structured risk description defining cause, risk, and effect (e.g., “Due to <cause>, there is a threat/opportunity that <risk> may occur, leading to <effect>.”).
Method Of Measurement
AACEi :
The standardized procedure used to measure quantities of work in a bill of quantities (BOQ).
Method Of Performance
AACEi :
The manner in which a product or objective is accomplished, generally at the contractor’s discretion unless contractually specified. Owner-directed changes may constitute a change in method. Syn.: Means And Methods.
Methodology
PMI :
A system of practices, techniques, procedures, and rules used within a discipline.
Micro-Scheduling
AACEi :
Scheduling of activities with durations less than one day.
Milestone
AACEi :
A zero-duration event used to denote a specific point in time for reference or measurement.
APM :
A key event selected for its importance in the schedule.
PMI :
A significant point or event in a project, program, or portfolio.
Milestone Dictionary
AACEi :
A description of the criteria required to satisfy each milestone.
Milestone Flag
AACEi :
A numeric code used to identify an event as a milestone.
Milestone Level
AACEi :
The level of management at which an event is considered a key milestone.
Milestone List
PMI :
A list identifying all project milestones and indicating whether they are mandatory or optional.
Milestone Plan
AACEi :
A plan consisting solely of milestones that highlight key project events.
Milestone Report
AACEi :
A report showing allowable dates, expected dates, completion dates, and slack for milestone events.
Milestone Schedule
AACEi :
A summary schedule composed of key events used to monitor overall project performance.
PMI :
A summary-level schedule identifying major milestones.
Milestone, Payment
AACEi :
Milestones upon which contractual payments become due.
Misrepresentation
AACEi :
Inaccurate factual information provided by either contracting party, even if unintentional. Syn.: Superior Knowledge.
Mitigation
AACEi :
A risk response strategy intended to reduce the probability or impact of a threat, and a contractual duty to minimize damages.
Mitigation Of Damages
AACEi :
Actions taken to avoid, reduce, or lessen damages and delays resulting from an event.
Mobilization
APM :
Establishing organizational and technical infrastructures to put project resources in place.
Model Pricing
AACEi :
Techniques using models to depict cost relationships, supported by mathematics and computer analysis.
Modeling
AACEi :
Creation of physical or mathematical representations to reflect system behavior; cost estimates and schedules are modeling practices, not exact predictions.
Modification, Bilateral
AACEi :
A contract modification mutually agreed upon by both parties.
Modification, Unilateral
AACEi :
A contract modification issued by the owner without contractor agreement on time or price.
Monetary Equivalents
AACEi :
Valuation of non-financial objectives (e.g., safety, environmental) in monetary terms for decision-making.
Monitor and Control Project Work
PMI :
The process of tracking, reviewing, and reporting progress against performance objectives in the project management plan.
Monitoring
AACEi :
Periodic gathering, validating, and analyzing data on contract status to determine existing or potential problems. Typically accomplished via contractor reports on schedule, labor, cost, and technical status; on-site inspections and other methods may be used as needed.
PMI :
Collect project performance data per the plan, produce performance measures, and report and disseminate performance information.
Monitoring And Controlling Process Group
PMI :
Processes required to track, review, and regulate project progress and performance; identify areas where plan changes are needed; and initiate the corresponding changes.
Monte Carlo Simulation
AACEi :
A computer sampling technique using pseudo-random numbers to simulate a range of possible outcomes.
APM :
A technique to estimate the likely range of outcomes by simulating a process under randomly selected conditions multiple times.
PMI :
Generates hundreds or thousands of probable performance outcomes based on probability distributions for cost and schedule, then aggregates them to produce a project-level probability distribution.
Month-To-Month Price Index
AACEi :
A price index for a given month using the preceding month as the base period.
Monthly Guide Schedule
AACEi :
A detailed two-month schedule used to plan work sequences or analyze an area. Prepared “as needed” or in critical areas. Syn.: Short-Term Activities.
Most Likely Time
AACEi :
The most realistic estimate of activity duration under normal conditions. Used in probabilistic scheduling.
PMI :
An estimate of the most probable activity duration considering all known influencing variables.
Most Likely Value
AACEi :
In risk analysis, usually refers to the mode of a distribution. For multimodal, uniform, or complex distributions, it may reflect the estimator’s judgment.
Moving Average
AACEi :
Smoothing a time series by replacing each value with the mean of itself and adjacent values.
MRP
AACEi :
Syn.: Material Requirements Planning (MRP).
MRP II
AACEi :
Syn.: Manufacturing Resource Planning (MRP II).
Multi-Criteria Decision Analysis
PMI :
A decision matrix technique providing a systematic approach for establishing criteria (risk, uncertainty, valuation) to evaluate and rank multiple alternatives.
Multi-Project Scheduling
AACEi :
Technique to consolidate multiple CPM project schedules into a master schedule to monitor and control an overall program.
Multiple Finish Network
AACEi :
A network containing more than one finish activity or finish event.
Multiple Start Network
AACEi :
A network containing more than one start activity or start event.
Multiple Straight-Line Depreciation Method
AACEi :
Depreciation method using two or more straight-line rates. Typically, ¾ of the asset cost is depreciated in the first half of its service life, and the remaining ¼ in the second half.
Must Finish
AACEi :
The date an activity must finish by; it is a constraint date.
Must Finish By Date
AACEi :
Date used in scheduling software to calculate project completion. Without it, project end dates float to natural completion.
Must Start
AACEi :
The date an activity must start by; it is a constraint date.
Near-Critical Activity
AACEi :
A schedule activity with minimal total float relative to the critical path(s) and at risk of becoming critical. The float threshold considered near-critical is project-dependent.
PMI :
A schedule activity or path with low total float; the threshold is subject to expert judgment.
Near-Critical Path
AACEi :
An activity or sequence of activities that is almost critical or at risk of becoming critical if delayed. Identification may be based on total float, longest path, or multiple critical paths.
Near-Term Activities
AACEi :
Activities planned to begin, be in progress, or be completed within a short time frame such as 30, 60, or 90 days.
Negative Float
AACEi :
(1) The amount of time by which an activity’s early date exceeds its late date.
(2) The time by which an activity or path duration must be reduced to meet a constrained date.
Negative Lag
AACEi :
A lag with a negative value; generally discouraged in scheduling practice.
Negligence
AACEi :
Failure to exercise the degree of care expected of an average, prudent professional under similar circumstances.
Negotiated Settlements
AACEi :
The process of resolving all outstanding issues, claims, and disputes through negotiation.
Negotiation
APM :
A discussion between parties aimed at reaching agreement.
PMI :
The process of resolving disputes through consultations between involved parties.
Net Area
AACEi :
In building construction, the usable area exclusive of partitions, mechanical spaces, and other encroachments.
Net Benefits (Savings)
AACEi :
The difference between total benefits and total costs.
Net Present Value
AACEi :
Syn.: Present Value; Present Worth.
Net Profit, Percent Of Sales
AACEi :
The ratio of annual profits to total sales, used as a comparative profitability indicator.
Net Purchases (Concept Of)
AACEi :
Sales proceeds of used commodities are deducted from reported expenditures within the same commodity group.
Network
AACEi :
A series of activities and events showing sequence and interdependencies required to complete a project. Syn.: Logic Network.
PMI :
A graphical representation of logical relationships among schedule activities.
Network Analysis
AACEi :
Determining early/late start and finish dates using forward and backward CPM calculations. Syn.: Project Network Analysis.
APM :
Collective term for network analysis methods including CPM, PERT, and critical chain.
PMI :
Technique for identifying early and late dates for uncompleted schedule activities.
Network Diagram
AACEi :
Syn.: Logic Diagram; Logic Network Diagram.
APM :
A model of activities and their dependencies using nodes and links.
Network Float
AACEi :
Total float values present across activity chains in a CPM network.
Network Interface
AACEi :
An activity or event common to two or more network diagrams.
Network Logic
AACEi :
The collection of dependencies forming a project network diagram.
PMI :
The collection of schedule activity dependencies in a network diagram.
Network Open End
AACEi :
A condition where an activity (other than start or finish) lacks a predecessor or successor.
Network Path
AACEi :
Any continuous chain of connected activities in a network.
PMI :
A continuous sequence of logically related schedule activities.
Network Planning
AACEi :
Planning technique that structures project activities and their dependencies using network logic.
Network Scheduling
AACEi :
Scheduling method where activities are arranged by logical relationships to identify critical paths and float.
Networking
PMI :
Establishing professional relationships within or across organizations.
Node
AACEi :
In AOA scheduling, an event marking the start or finish of an activity.
PMI :
A junction point connecting dependency relationships in a schedule network.
Nominal Discount Rate
AACEi :
Interest rate reflecting both inflation and real earning power; used when costs are expressed in current dollars.
Nominal Group Technique
PMI :
A structured brainstorming technique using voting to rank or prioritize ideas.
Non-Cash
AACEi :
Tangible commodities drawn from inventory and not replaced.
Non-Critical Activities Or Work Items
AACEi :
Activities with positive float that may be delayed within limits without affecting overall project duration.
Non-Durable Goods
AACEi :
Goods whose serviceability is generally limited to less than three years, such as perishable and semi-durable goods.
Non-Excusable Delays
AACEi :
(1) Delays caused by the contractor or subcontractor, for which no time extension or delay damages are allowed and for which the owner may claim damages.
(2) Delays for which a party assumes the risk of cost and consequences and that are commonly used as a defense against time extension or delay claims.
Non-Exempt Employees
AACEi :
Employees who are not exempt from overtime compensation under federal wage and hour regulations.
Non-Splittable Activity
AACEi :
An activity that must be completed without interruption once started; resources should not be reassigned.
Non-Work Unit
AACEi :
A calendar-defined time unit during which work is not scheduled.
Nonconformance Work
PMI :
Work performed to address errors or failures resulting from activities not done correctly the first time; ideally minimized in effective quality systems.
Normal Weather
AACEi :
Weather conditions expected for a given location and period based on historical records, including typical adverse and non-adverse conditions.
Normalization
AACEi :
In data management, the process of adjusting data to conform to a common standard such as time, currency, or location.
Not Earlier Than
AACEi :
A scheduling restriction indicating an activity may not start or finish before a specified date.
Not Later Than
AACEi :
A scheduling restriction indicating an activity may not start or finish after a specified date.
Notice Of Award
AACEi :
Written notification from the owner accepting a bid and stating that the contract will be executed once stated conditions are met.
Notice To Proceed (NTP)
AACEi :
Formal authorization directing a contractor or supplier to begin work or a defined phase of work; may include a Limited Notice To Proceed (LNTP).
Objective
AACEi :
Something one wants to get done; a specific statement of quality, quantity, and time. In contract/procurement management, it defines the method and service or resource to be procured. In time management, it is a predetermined result toward which effort is directed.
APM :
Predetermined results toward which effort is directed, defined in terms of outputs, outcomes, and/or benefits.
PMI :
Something toward which work is directed, such as a purpose to be achieved, result to be obtained, product to be produced, or service to be performed.
Objective Event
AACEi :
An event that signifies completion of a path through the network; a network may have more than one objective event.
Observations
PMI :
A technique that provides a direct way of viewing individuals in their environment while performing their jobs, tasks, or processes.
Obsolescence
AACEi :
(1) The condition of being out of date, resulting in loss of value due to newer developments.
(2) A decrease in asset value caused by new, more economical methods, processes, or machinery.
(3) Loss of usefulness or worth due to superior or more economical alternatives.
Occurred Risk
AACEi :
A risk event or condition identified during risk assessment that actually occurred.
Offsites
AACEi :
Facilities outside process unit battery limits, such as storage, utilities, substations, administrative buildings, rail tracks, and yards.
Omission
AACEi :
Any part of a system that has been left out in design, construction, or fabrication, requiring evaluation and corrective action.
On-Stream Factor
AACEi :
The ratio of actual operating days to total calendar days per year.
Open Shop
AACEi :
A condition where union and non-union contractors may work, with no union agreement in place. Syn.: Merit Shop.
Open-Ended Activities
AACEi :
CPM activities lacking a predecessor or successor, other than the first and last activities, which can break network logic and distort float calculations.
Operating Cost
AACEi :
Expenses incurred during normal facility operations, including labor, materials, utilities, fuel, maintenance, taxes, and related costs.
Operation
AACEi :
Ongoing activities that utilize strategic assets for a defined function or purpose.
Operation Management
APM :
The management of activities that create an organisation’s core services or products.
Operation Phase
AACEi :
The period during which a completed deliverable is used and maintained for its intended purpose, forming part of the asset life cycle.
Operations Research (OR)
AACEi :
Quantitative analysis of operations using mathematical models to support objective management decision-making.
Opportunity
AACEi :
An uncertain event that could improve results or the likelihood of achieving objectives.
APM :
A positive risk event with beneficial effects on objectives.
PMI :
A risk that would have a positive effect on one or more project objectives.
Opportunity Cost Of Capital
AACEi :
The rate of return available from the next best investment of comparable risk.
Opportunity Costs
AACEi :
The value of the best alternative forgone when a choice is made.
Optimising
APM :
The highest maturity level where continuous improvement is enabled through quantitative feedback and innovation.
Optimistic Duration
AACEi :
The shortest of the three duration estimates used in PERT analysis.
Optimistic Time Estimate
AACEi :
The minimum time required if everything proceeds exceptionally well.
PMI :
The shortest possible activity duration considering all known variables.
Optimum Plant Size
AACEi :
The plant capacity that best balances economies of scale against the cost of excess capacity.
Order Of Magnitude Estimate
AACEi :
An estimate prepared with little or no project definition.
Organization
APM :
The management structure and organisational environment in which a project, programme, or portfolio operates.
Organization Breakdown Structure (OBS)
AACEi :
A hierarchical structure defining organizational responsibility for managing scope within the WBS.
PMI :
A hierarchical representation showing relationships between project activities and performing organizational units.
PCI :
A structure identifying the organisational unit responsible for each part of an investment.
Organizational Codes
AACEi :
Numerical or alphabetized characters specified by the user for the system to associate with an activity for sorting and categorization.
Organizational Process Assets
PMI :
Plans, processes, policies, procedures, and knowledge bases that are specific to and used by the performing organization.
Organizational Project Management Maturity
PMI :
The level of an organization’s capability to deliver desired strategic outcomes in a predictable, controllable, and reliable manner.
Original Duration
AACEi :
The first estimate of the time required to execute an activity, typically expressed in hours, days, or weeks.
Out-Of-Sequence Progress
AACEi :
Progress reported when predecessor activities defined in the logic have not yet been completed. Scheduling software may handle this using configurable calculation options.
Outcome
APM :
The changed circumstances or behavior that results from the use of an output.
Outlier
AACEi :
A value that lies at the extreme outer range of values in a sample or population.
Output
AACEi :
Goods, services, or other results created by a process.
APM :
The tangible or intangible product typically delivered by a project.
PMI :
A product, result, or service generated by a process, which may serve as an input to a successor process.
Over Target Baseline (OTB)
AACEi :
In earned value management (ANSI EIA-748), an adjusted performance measurement baseline created when the original PMB is no longer realistic, typically due to a large variance between EAC and BAC. The resulting PMB may exceed the contract budget base.
Over Target Schedule (OTS)
AACEi :
In earned value management, a condition where the schedule is rebaselined to a finish date later than the contractual requirement due to significant forecast variance.
Overhaul
AACEi :
The distance transported in excess of the stated haul distance for excavated material.
Overhead
AACEi :
Costs inherent in performing operations that cannot be directly charged to a specific product, work item, or asset and must be allocated or treated as business expenses.
Overload
AACEi :
In planning and resource management, the amount by which required resources exceed available resource limits.
Overplan (Underplan)
AACEi :
The difference between planned cost to date and the latest revised estimate of cost to date. An underplan exists when planned cost exceeds the revised estimate; an overplan exists when the revised estimate exceeds planned cost.
Overrun (Underrun)
AACEi :
The difference between actual costs incurred and the estimated or earned value of the work performed. Higher actual costs indicate an overrun; lower costs indicate an underrun.
Owner
AACEi :
The entity or individual with whom the contractor has entered into an agreement and for whom the work is performed.
Owner Furnished Fixtures & Equipment (OFFE)
AACEi :
Items supplied by the owner that become part of the contractor’s work. Timing, quality, and interfaces of OFFE frequently impact schedule and performance.
P3 Assurance
AACEi :
The process of providing confidence to stakeholders that projects, programmes, and portfolios will achieve their scope, time, cost, and quality objectives, and realize their benefits.
P3 Management
APM :
The collective term for project, programme, and portfolio management.
P3 Management Team
APM :
A collective term for those involved in the sponsorship and day-to-day management of a project, programme, or portfolio.
Parallel Activities
AACEi :
Two or more activities that can be performed at the same time, allowing a project to be completed faster than if activities were sequential.
Parallel Lifecycle
APM :
A life cycle in which phases are conducted in parallel.
Parametric Estimate
AACEi :
An estimating approach using probabilistic algorithms or cost estimating relationships based on abstracted scope parameters, such as factors, unit costs, or cost models.
APM :
An estimating technique that uses statistical relationships between historical data and other variables.
PMI :
An estimating technique that uses an algorithm based on historical data and project parameters.
Parametric Risk Analysis
AACEi :
Risk analysis methods using parametric estimating where inputs are risk drivers and outputs quantify risk, typically applied to systemic risks.
Parent
AACEi :
A higher-level element within a hierarchical structure.
Parent Activity
AACEi :
A task within the work breakdown structure that contains subordinate child tasks.
Pareto Diagram
AACEi :
A histogram arranged by frequency of occurrence showing how many results were generated by each identified cause.
PMI :
A histogram ordered by frequency of occurrence that displays the contribution of each cause.
Pareto’s Law
AACEi :
Syn.: Eighty-Twenty Rule.
Partial Utilization
AACEi :
Placing a portion of the work into service for its intended purpose before reaching full substantial completion.
Path
AACEi :
A continuous chain of activities within a network.
Path Convergence
AACEi :
A condition where multiple CPM activities precede a shared event.
PMI :
A relationship in which a schedule activity has more than one predecessor.
Path Divergence
AACEi :
A condition where multiple CPM activities succeed a shared event.
PMI :
A relationship in which a schedule activity has more than one successor.
Path Float
AACEi :
Syn.: Float; Slack.
Payback Method
AACEi :
An economic evaluation technique that determines the time required for cumulative benefits to recover the initial investment.
Payment Systems
PMI :
The system used to provide, track, and manage supplier invoices and payments.
Payoff (Payback) Period
AACEi :
Syn.: Payout Time.
Payout Time
AACEi :
The time required to recover the original fixed investment from profit and depreciation, typically based on projected sales.
Payroll Burden
AACEi :
Syn.: Labor Burden.
PDM
AACEi :
Syn.: Precedence Diagramming Method (PDM).
PDM Arrow
AACEi :
A graphical symbol in PDM networks representing lag relationships between work items.
PDM Finish To Finish Relationship
AACEi :
A relationship that restricts the finish of an activity until a specified duration after another activity finishes.
PDM Finish To Start Relationship
AACEi :
The standard relationship where a successor activity starts only after the predecessor finishes.
PDM Start To Finish Relationship
AACEi :
A relationship that restricts the finish of an activity until a specified duration after another activity starts.
PDM Start To Start Relationship
AACEi :
This relationship restricts the start of a work item until a specified duration following the start of the preceding work item.
Percent Complete
AACEi :
An estimate of the percentage complete for an element as of a specific data date.
1) In scheduling, completed duration divided by total duration.
2) In earned value, technical work completed compared to total technical scope.
3) Earned value percent complete = BCWP / BAC.
4) Percent complete as spent = ACWP / EAC.
PMI :
An estimate expressed as a percentage of the work completed on an activity or WBS component.
Percent On Diminishing Value
AACEi :
Syn.: Declining Balance Depreciation.
Perfect (And Imperfect) Information
AACEi :
Perfect information is data known to be absolutely correct with no uncertainty. Imperfect information contains uncertainty.
Perform Integrated Change Control
PMI :
The process of reviewing, approving, and managing changes to deliverables, documents, organizational process assets, and the project management plan, and communicating outcomes.
Performance Based Management System (PBMS)
PCI :
A system that integrates performance measures and metrics with investment planning to effectively manage investments, programs, and projects.
Performance Measurement Baseline (PMB)
AACEi :
The time-phased budget plan against which project or contract performance is measured. PMB plus management reserve equals the contract budget base unless an OTB is implemented.
PMI :
An approved integrated scope-schedule-cost plan used to measure and manage project performance, including contingency reserve but excluding management reserve.
PCI :
The time-phased budget plan formed by scheduled cost accounts and applicable indirect budgets, frozen and controlled through formal change management.
Performance Measurement System
AACEi :
An organization’s defined processes and quantitative tools used to monitor, measure, and report performance against defined objectives.
Performance Reporting
PMI :
The physical or electronic representation of work performance information intended to support decisions, actions, or awareness.
Performance Reviews
PMI :
A technique used to compare and analyze actual project performance against baselines.
Performing Organization
PMI :
The enterprise whose personnel are directly involved in executing the project or program work.
PERT (Program / Project Evaluation and Review Technique)
AACEi :
A probabilistic planning technique used with CPM that estimates activity durations using optimistic, pessimistic, and most-likely scenarios.
PERT Analysis
AACEi :
An evaluation method using best-case, expected-case, and worst-case scenarios to estimate outcomes.
APM :
A network analysis technique calculating schedule standard deviations using three-point estimates.
PMI :
An estimating technique using a weighted average of optimistic, pessimistic, and most likely estimates.
PERT Chart
AACEi :
A flowchart showing tasks and dependencies, not necessarily based on probabilistic durations.
Pessimistic Time Estimate
AACEi :
The maximum expected activity duration under adverse conditions.
PMI :
The longest possible duration considering known risk factors.
Phantom Float
AACEi :
The difference between theoretical remaining float and actual remaining float.
Phase
AACEi :
A major period in the life of a project or asset.
APM :
A major subdivision of a life cycle.
PMI :
A collection of related activities ending with one or more deliverables.
Phase Gate
PMI :
A review point at the end of a phase to decide whether to continue, modify, or terminate a project or program.
Phased Construction
AACEi :
Construction that begins before final design completion to achieve earlier beneficial use.
Physical Percentage Complete
AACEi :
The percentage of technical work scope completed as of a specific date, independent of cost or hours expended.
Physical Progress
AACEi :
Status of work based on predefined measures of completed physical scope.
Physical Restraint
AACEi :
A condition where physical completion of one activity is required before another can begin.
Plan
AACEi :
A formalized intended course of action forming the basis for project controls and execution.
Plan-Do-Check-Act (PDCA) Cycle
AACEi :
A continuous improvement methodology forming the foundation of Total Cost Management.
Planned Adverse Weather Day
AACEi :
The expected number of days affected by adverse weather, based on historical data.
Planned Cost
AACEi :
The approved estimated cost for scheduled work forming part of the total project commitment.
Planned Duration (PD)
AACEi :
The planned schedule duration expressed in time units.
Planned Duration of Work Remaining (PDWR)
AACEi :
The unearned portion of planned project duration.
Planned Value (PV)
AACEi :
The budgeted cost for scheduled work as of a given date (BCWS).
PMI :
The authorized budget assigned to scheduled work.
PCI :
Budget assignment per reporting period for each work component.
Planner
AACEi :
A project controls professional responsible for planning, scheduling, and progress tracking.
Planning
AACEi :
The process of defining objectives, activities, resources, responsibilities, and integrated plans to achieve project goals.
APM :
Determines what will be delivered, how, when, at what cost, and by whom.
Planning Horizon
AACEi :
The future time span for which plans are generated, covering cumulative lead times.
Planning Package
AACEi :
A logical aggregation of work within a cost account, typically representing far-term effort that can be identified and budgeted early, but later detailed into work packages, level of effort (LOE), or apportioned effort.
PMI :
A work breakdown structure component below the control account with known work content but without detailed schedule activities.
Planning Phase
AACEi :
Syn.: Definition Phase; Development Phase; Front End.
Planning Process Group
PMI :
Processes used to establish scope, refine objectives, and define actions required to achieve project goals.
Planning Session
AACEi :
A meeting of key project team members to define scope and establish manageable control segments.
Plant Overhead
AACEi :
Costs not directly attributable to a specific production unit and allocated on an equitable basis. Includes management salaries, payroll, purchasing, and accounting.
Syn.: Factory Expense.
Plug Date
AACEi :
A constraint date assigned to an activity defining the earliest or latest allowable start or finish.
Syn.: Constraint Date.
Plurality
PMI :
A decision-making method where the option with the largest number of votes wins, even without a majority.
Point Estimate
AACEi :
Syn.: Base Estimate; Single Point Estimate.
Policy
AACEi :
A definitive organizational position that guides consistent decision-making and defines authority and accountability.
PMI :
A structured pattern of principles governing organizational conduct.
Portfolio
AACEi :
A group of projects, programs, or assets managed together to achieve strategic objectives and synergies.
APM :
A grouping of an organisation’s projects and programmes managed at an organisational or functional level.
PMI :
Projects, programs, subportfolios, and operations managed as a group to achieve strategic objectives.
Portfolio Management
AACEi :
The direction and oversight of grouped assets for strategic benefit; part of strategic asset management in TCM.
APM :
Selection, prioritisation, and control of projects and programmes aligned to strategy and delivery capacity.
PMI :
Centralized management of one or more portfolios to achieve strategic objectives.
Positive Float
AACEi :
Time available for non-critical activities without affecting total project duration.
Practice
PMI :
A professional or management activity contributing to process execution using specific tools and techniques.
Precedence Diagramming Method (PDM)
AACEi :
A network technique placing activities on nodes, allowing multiple relationship types with leads and lags.
PMI :
A scheduling technique using nodes and logical relationships to show activity sequencing.
Precedence Network
APM :
A network diagram where activities are shown as nodes and dependencies as arrows.
Precedence Relationship
PMI :
A logical relationship between activities; often used interchangeably with dependency.
Preceding Event
AACEi :
Syn.: Beginning Event; Predecessor Event; Starting Event.
Precision
PMI :
A measure of exactness within a quality management system.
Preconstruction CPM
AACEi :
A construction schedule developed during design prior to contract award.
Predecessor
AACEi :
An activity that immediately precedes another activity.
Predecessor Activity
AACEi :
An activity that must be completed before a successor can begin.
PMI :
An activity that logically comes before a dependent activity.
Predecessor Event
AACEi :
Syn.: Beginning Event; Preceding Event; Starting Event.
Predictive Life Cycle
PMI :
A life cycle where scope, time, and cost are determined early and changes are tightly controlled.
Preferential Logic
AACEi :
Contractor-imposed sequencing beyond contractual requirements, often carrying negative connotations.
PMI :
A relationship based on preferred sequencing derived from best practices.
Preferred Logic
PMI :
A relationship established based on desired sequencing or best practices.
Preliminary CPM Plan
AACEi :
A CPM analysis performed before contract award to establish a reasonable construction duration.
Preliminary Engineering
AACEi :
Design-related services performed during project evaluation and definition phases.
Prescriptive
AACEi :
Laid down as a guide, direction, or rule of action. Usually implies detailed step-by-step instructions to be followed without questioning—describing what is to be done rather than how it is done (descriptive).
Present Value
AACEi :
The value of a future benefit or cost discounted to a base time. Also refers to an investment comparison method using a known interest rate to select the alternative with the highest present value.
Syn.: Net Present Value; Present Worth.
Present Value Factor
AACEi :
(1) The discount factor used to convert future values to present values.
(2) A mathematical expression known as the present value of an annuity of one.
(3) A formula used in compound interest economic analysis.
Present Worth
AACEi :
Syn.: Net Present Value; Present Value.
Present Worth Factor
AACEi :
Syn.: Present Value Factor.
Prevention
AACEi :
Quality activities used to avoid deviations, including system development, audits, feasibility studies, supplier evaluations, and certification.
Preventive Action
PMI :
An intentional activity ensuring future project performance aligns with the project management plan.
Price
AACEi :
The monetary amount exchanged for a product or service; its primary function is rationing supply among buyers.
Price Index
AACEi :
A number relating the price of an item at one time to its price at a specified base time.
Pricing
AACEi :
The determination of the amount charged after costing, considering business objectives such as profit and market conditions. Pricing follows costing and precedes budgeting.
Pricing, Forward
AACEi :
Estimation of work cost prior to performance; commonly used for pricing proposed change orders.
Pricing, Retrospective
AACEi :
Pricing of work after it has been completed.
Primary Classification
AACEi :
Classification of commodities by commodity type.
Prime Contractor
AACEi :
The principal contractor performing a contract for an owner.
Prince2
APM :
A project management methodology meaning Projects in Controlled Environments.
Prioritise
APM :
The portfolio life cycle phase where priorities are set based on strategic metrics.
Prioritization Matrices
PMI :
A quality planning tool for evaluating alternatives and defining implementation priorities.
Proactive
AACEi :
Acting in anticipation of future problems, needs, or changes.
Probabilistic Dependencies
AACEi :
Activity dependencies that represent alternative logic paths with assigned probabilities.
Probabilistic Network
AACEi :
A network with alternative paths where probabilities replace deterministic relationships.
Probabilistic Risk Assessment
AACEi :
A quantitative process providing probabilistic information for evaluating risk.
Probability and Impact Matrix
PMI :
A grid mapping risk probability against impact on project objectives.
Probability of Underrun (or Overrun)
AACEi :
The chance that cost or time will be less or greater than a given value based on risk model outcomes.
Procedure
AACEi :
A prescribed method for performing work.
PMI :
A defined sequence of steps used to execute a process consistently.
Process
AACEi :
A set of steps required to achieve an output.
PMI :
A systematic series of activities transforming inputs into outputs.
Process Analysis
PMI :
Analysis performed according to the process improvement plan to identify enhancements.
Process Control
AACEi :
Managing a process to a proven standard.
Process Decision Program Charts (PDPC)
PMI :
A tool used to relate a goal to the steps required to achieve it.
Process Design
AACEi :
Design of management or technical processes in organizational or industrial contexts.
Process Improvement Plan
PMI :
A subsidiary plan describing steps to analyze and enhance process value.
Procurement
AACEi :
Establishing contractual relationships to acquire goods and services to meet project objectives.
APM :
Acquisition of external products or services for a project, programme, or portfolio.
Procurement Audits
PMI :
Reviews of contracts and contracting processes for effectiveness and compliance.
Procurement Documents
PMI :
Documents used in bid and proposal activities, including IFBs, RFPs, RFQs, and responses.
Procurement Management Plan
PMI :
A plan describing how goods and services will be acquired externally.
Procurement Performance Reviews
PMI :
Structured reviews of seller performance against contractual requirements.
Procurement Statement of Work
PMI :
A detailed description of procurement requirements enabling seller evaluation.
Product
AACEi :
Tangible or intangible output of a process.
APM :
A tangible or intangible project output; synonymous with deliverable.
PMI :
A quantifiable artifact produced as an end item or component.
Product Analysis
PMI :
A scope definition tool involving analysis of product use, characteristics, and requirements.
Product Breakdown Structure (PBS)
AACEi :
A structure that identifies required products and deliverables, displayed hierarchically.
Product Life Cycle
PMI :
The series of phases representing the evolution of a product from concept through delivery, growth, maturity, and retirement.
Product Scope
PMI :
The features and functions that characterize a product, service, or result.
Product Scope Description
PMI :
The documented narrative description of the product scope.
Production Plan
AACEi :
The agreed-upon strategy resulting from the production planning function.
Production Planning
AACEi :
The function of setting manufacturing or construction output levels to meet management objectives while stabilizing the workforce.
Production Rate
AACEi :
The amount of work accomplished per unit of time.
Production Schedule
AACEi :
(1) A manufacturing authorization to produce a specified quantity of an item.
(2) A short-interval project schedule used to plan and coordinate activities.
Productivity
AACEi :
A measure of output relative to input. Productivity improves by increasing output for a given input or reducing input for a given output.
Syn.: Efficiency.
Productivity Factor
AACEi :
Syn.: Labor Productivity Factor.
Professionalism
APM :
The application of specialized knowledge and adherence to professional standards within a field.
Profit Element
AACEi :
A quantified component of a profitability model that favorably impacts the bottom line.
Syn.: Profit Item.
Profit Item
AACEi :
Syn.: Profit Element.
Profit Margin
AACEi :
A ratio of profit to total cost or revenue, varying by industry type.
Profit, Gross Profit
AACEi :
Earnings after direct and project indirect costs are deducted from sales revenue.
Profit, Net Profit
AACEi :
Earnings after miscellaneous income, expenses, and taxes are subtracted from operating profit.
Profit, Operating Profit
AACEi :
Earnings after selling, administrative, and depreciation expenses are deducted from gross profit.
Profitability
AACEi :
A measure of excess income over expenditure during a given period.
Profitability Analysis
AACEi :
Evaluation of project, product, or service economics over a defined time frame.
Profitability Index (PI)
AACEi :
A discounted cash flow method reflecting time and value of money; also known as internal rate of return.
Program
AACEi :
A grouping of related projects managed toward a common strategic goal.
APM :
A group of related projects and change activities delivering beneficial change.
PMI :
Related projects and activities managed to obtain benefits unavailable individually.
Program Management
AACEi :
Management of related projects to achieve broad organizational objectives.
APM :
Coordinated management of projects and change initiatives.
PMI :
Application of knowledge and tools to realize program benefits.
Program Manager
AACEi :
An individual responsible for planning, directing, and controlling program objectives.
Programme Surveillance
PCI :
Review of a programme’s application of approved earned value management processes.
Progress
AACEi :
Advancement toward completion or the measured status of partially completed work.
Progress Date
AACEi :
The reference date used to calculate and assess project progress.
Progress Line
AACEi :
A Gantt chart representation showing schedule performance at a specific progress date.
Progress Measurement
AACEi :
Measurement of completed work for progress assessment and payment determination.
Progress Milestones
AACEi :
Milestones used as the basis for earning and measuring progress.
Progress Override
AACEi :
Scheduling logic that ignores predecessor constraints for out-of-sequence progress.
Progress Report
AACEi :
A report summarizing project status, costs, performance, and key issues at a cutoff date.
Progress Trend
AACEi :
Syn.: Trend.
Progressive Elaboration
PMI :
Iterative development of project plans as information becomes more detailed and accurate.
Project
AACEi :
A temporary endeavor with defined objectives, time, and cost constraints.
APM :
A unique, transient endeavor undertaken to achieve planned objectives.
PMI :
A temporary endeavor creating a unique product, service, or result.
Project Boundary
AACEi :
Defines project interaction limits with internal and external activities.
Project Calendar
AACEi :
Defines global project working and non-working periods.
PMI :
Identifies working days and shifts for scheduled activities.
Project Code
AACEi :
A symbolic coding system representing hierarchical subdivisions of project scope.
Project Communication Management
PMI :
Includes the processes required to ensure timely and appropriate planning, collection, creation, distribution, storage, retrieval, management, control, monitoring, and disposition of project information.
Project Control
AACEi :
A management process for controlling the investment of resources through project execution, including planning baselines, performance measurement, comparison to plans, and corrective action.
Project Cost Management
PMI :
Processes involved in planning, estimating, budgeting, financing, funding, managing, and controlling costs to complete the project within the approved budget.
Project Definition
AACEi :
The process of thoroughly exploring all aspects of a proposed project and their relationships to performance, time, and cost.
Project Duration
AACEi :
The elapsed time from project start to project finish, including any contractually imposed duration.
Project Finish Date (Schedule)
AACEi :
The latest scheduled calendar finish date of all project activities.
Project Float
AACEi :
The time between early project completion and contractual completion date; may be internalized into network float.
Project Funding Requirements
PMI :
Forecast project costs derived from the cost baseline, including projected expenditures and anticipated liabilities.
Project Governance
PMI :
The framework aligning project objectives with organizational strategy, distinct from organizational governance.
Project Initiation
PMI :
The process that results in authorization to begin a new project.
Project Integration Management
PMI :
Processes and activities required to identify, define, combine, unify, and coordinate project management activities.
Project Life
AACEi :
Syn.: Life Cycle, Project Life Cycle.
Project Management
AACEi :
The coordination of skills, knowledge, planning, scheduling, directing, controlling, and monitoring to achieve project objectives.
APM :
Application of processes, methods, knowledge, skills, and experience to achieve project objectives.
PMI :
Application of knowledge, skills, tools, and techniques to meet project requirements.
Project Management Body of Knowledge
PMI :
The complete collection of knowledge within the profession of project management, including traditional and emerging practices.
Project Management Information System
PMI :
An information system used to gather, integrate, and disseminate project management outputs throughout the project life cycle.
Project Management Knowledge Area
PMI :
An identified area of project management defined by its knowledge requirements and component processes.
Project Management Plan
APM :
The output of the definition phase of a project or programme.
PMI :
The document describing how the project will be executed, monitored, and controlled.
Project Management Process Group
PMI :
A logical grouping of project management inputs, tools, techniques, and outputs, not project phases.
Project Management Software
AACEi :
Computer applications designed to support planning and control of project resources, costs, and schedules.
Project Management Staff
PMI :
Project team members who perform project management activities.
Project Management System
PMI :
The aggregation of processes, tools, methodologies, resources, and procedures used to manage a project.
Project Management Team
PMI :
Project team members directly involved in project management activities.
Project Manager
AACEi :
The individual assigned responsibility and authority for planning, controlling, and reporting project work.
PMI :
The person assigned to lead the team and achieve project objectives.
Project Network Analysis
AACEi :
Syn.: Network Analysis.
Project Office
AACEi :
Organization responsible for administration of the project management system and project support.
PMI :
Project Management Office (PMO): An organizational structure standardizing project governance.
Project Organization Chart
PMI :
A graphical depiction of project team members and their relationships.
Project Phases
AACEi :
The main elements of a project life cycle.
PMI :
A collection of logically related activities culminating in deliverables.
Project Plan
AACEi :
The primary document guiding project activities from initiation through completion.
Project Procurement Management
PMI :
Processes required to acquire products, services, or results from outside the project team.
Project Quality Management
PMI :
Processes that determine quality policies, objectives, and responsibilities to meet project needs.
Project Scope Statement
PMI :
Description of project scope, major deliverables, assumptions, and constraints.
Project Start Date
AACEi :
The scheduled start date used as the basis for network calculations.
Project Team
PMI :
Individuals who support the project manager in achieving project objectives.
Project Team Directory
PMI :
A documented list of project team members, roles, and contact information.
Project Time
AACEi :
The time dimension within which a project is planned and executed.
Project Time Management
PMI :
Processes required to manage timely completion of the project.
Project Work Breakdown Structure (PWBS)
AACEi :
A project-specific summary WBS identifying elements unique to the project.
Project-Based Organizations (PBOs)
PMI :
Organizations that perform the majority of their work through projects.
Projected Finish Date
AACEi :
The current estimate of the calendar date when an activity or project will be completed.
Projected Start Date
AACEi :
The current estimate of the calendar date when an activity or project will begin.
Projection
AACEi :
An extension of a series, or any set of values, beyond the range of the observed data.
Projectized Organization
PMI :
Any organizational structure in which the project manager has full authority to assign priorities, apply resources, and direct the work of persons assigned to the project.
Prompt List
AACEi :
A Risk Breakdown Structure (RBS) or similar document used as a checklist during risk identification, monitoring, and other risk management steps.
Proposal Evaluation Technique
PMI :
The process of reviewing proposals provided by suppliers to support contract award decisions.
Proposal Schedule
AACEi :
The first schedule issued on a project; accompanies either the client's request or the contractor's proposal.
Proposed Base Contract Price
AACEi :
The sum total of the individual total price amounts for items of work designated as base bid items on the schedule of prices (excluding alternates, if any).
Proposed Change Order
AACEi :
A form furnished by the owner or engineer for authorizing, estimating, or notifying changes in contract work, price, or time. When signed, it may or may not fully adjust contract terms but signals incorporation into a subsequent change order.
Proposed Combined Contract Price
AACEi :
The sum of the proposed base contract price and all alternate bid items listed on the bid form (excluding additional alternates, if any).
Prototypes
PMI :
A method to obtain early feedback by providing a working model of the expected product before actual construction.
Provider
APM :
A person or company that provides goods or services.
Provider Selection Management
AACEi :
Processes for identifying and selecting management providers through the P3 life cycle.
Punchlist
AACEi :
A list generated by the owner, architect, engineer, or contractor of items yet to be completed. Also called a "but" list (items not yet complete).
Pure Price Change
AACEi :
Change in the price of a particular commodity not attributable to changes in quality or quantity.
Qualification Submittals
AACEi :
Data pertaining to a bidder's qualifications which shall be submitted as set forth in the instructions to bidders.
Qualifications & Assumptions
AACEi :
Items not completely defined in the project documents for which the estimator uses judgment in developing the estimate.
PMI :
Perform Qualitative Risk Analysis: The process of prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact.
Quality
AACEi :
Conformance to established requirements (not a degree of goodness).
APM :
The fitness for purpose or the degree of conformance of the outputs of a process or the process itself.
PMI :
The degree to which a set of inherent characteristics fulfills requirements.
Quality Acceptance Criteria
AACEi :
Specified limits placed on characteristics of a product, process, or service defined by codes, standards, or other requirement documents.
Quality Activities
AACEi :
Activities directly associated with appraisal, training, and prevention.
Quality Appraisal
AACEi :
Activities employed to determine whether a product, process, or service conforms to established requirements, including design review, specification review, other documentation review, constructability review, materials inspection/tests, personnel testing, quality status documentation, and post-project reviews.
Quality Assurance
AACEi :
Planned or systematic actions necessary to provide adequate confidence that a product, process, or service will conform to established requirements.
PMI :
Perform Quality Assurance: Auditing the quality requirements and the results from quality control measurements to ensure appropriate quality standards and operational definitions are used.
Quality Audit
AACEi :
A formal, independent examination with intent to verify conformance with established processes and acceptance criteria. Does not include surveillance or inspection for process control or product acceptance.
PMI :
A structured, independent process to determine if project activities comply with organizational and project policies, processes, and procedures.
Quality Checklist
PMI :
A structured tool used to verify that a set of required steps has been performed.
Quality Conformance
AACEi :
Quality management activities associated with appraisal, training, and prevention adapted to achieve zero deviations from established requirements.
Quality Control
AACEi :
Inspection, test, evaluation, or other actions to verify that a product, process, or service conforms to established requirements and specifications.
PMI :
Control Quality: Monitoring and recording results of quality activities to assess performance and recommend necessary changes.
Quality Control Measurement
PMI :
The documented results of control quality activities.
Quality Corrective Action
AACEi :
Measures taken to rectify conditions adverse to quality and prevent repetition. Includes rework and remedial actions for nonconformance deviations.
Quality Function Deployment (QFD)
PMI :
A facilitated workshop technique that helps determine critical characteristics for new product development.
Quality Management
AACEi :
Optimization of quality activities involved in producing a product, process, or service, including appraisal, training, and prevention.
APM :
A discipline ensuring outputs, benefits, and processes meet stakeholder requirements and are fit for purpose.
Quality Management And Control Tools
AACEi :
A type of quality planning tools used to link and sequence identified activities.
Quality Management Costs
AACEi :
The sum of costs associated with appraisal, training, and prevention activities.
Quality Management Plan
PMI :
A component of the project or program management plan describing how an organization’s quality policies will be implemented.
Quality Management System
PMI :
The organizational framework providing the policies, processes, procedures, and resources required to implement the quality management plan.
Quality Metrics
PMI :
A description of a project or product attribute and how to measure it.
Quality Nonconformance
AACEi :
A deviation severe enough to consider rejection of the product, process, or service. May require corrective action or acceptance with deviation.
Quality Performance Tracking System
AACEi :
A management tool providing data for quantitative analysis of quality aspects by systematically collecting and classifying costs of quality.
Quality Policy
PMI :
A policy specific to Project Quality Management, establishing the principles governing the organization’s actions in implementing its quality management system.
Quality Requirement
PMI :
A condition or capability used to assess conformance by validating the acceptability of an attribute for the quality of a result.
Quantification
AACEi :
Translating project scope into resource quantities suitable for costing. In construction, a take-off is a specific type of quantification listing material quantities from drawings.
Quantitative Risk Analysis
AACEi :
Risk analysis estimating numerical values (probabilistic) on risk outcomes using probabilities and impact values directly.
PMI :
Perform Quantitative Risk Analysis: Numerically analyzing the effect of identified risks on overall project objectives.
Quantitative Risk Analysis And Modelling Techniques
PMI :
Commonly used techniques for event-oriented and project-oriented quantitative analysis approaches.
Quantity Survey
AACEi :
Standard methods of measuring all labor and materials required for a project, building, or structure, itemized in a book or bill of quantities.
Quantity Surveying
AACEi :
A formalized method, usually monthly, detailing actual progress and units of work performed against a bill of quantities. Common in unit price contracts and international civil works projects.
Quantity Surveyor
AACEi :
In the UK and elsewhere, prepares bills of quantities for bidders. Professionally licensed and trained, responsible for establishing accurate quantities for all bidders.
Questionnaires And Surveys
PMI :
Written sets of questions designed to quickly accumulate information from many respondents.
Raci
AACEi :
Acronym for a chart or matrix indicating which individuals on a team are responsible, accountable, consulted, and informed regarding identified project deliverables.
PMI :
A common type of responsibility assignment matrix that uses responsible, accountable, consult, and inform statuses to define stakeholder involvement in project activities.
Racsi
AACEi :
Acronym for a chart or matrix indicating which individuals are responsible, accountable, consulted, supporting, and informed regarding identified project deliverables.
Ramp
AACEi :
Acronym for Risk Analysis and Management for Projects.
Range
AACEi :
The absolute difference between the maximum and minimum (or some stated confidence interval) values in a set; the simplest measure of dispersion of a distribution.
Range Estimating
AACEi :
(1) A formalized risk analysis technology that combines Pareto’s law, heuristics for probabilistic ranges, and Monte Carlo Simulation for rapid decision-making.
(2) A generic term for: a) estimating a variable as a probabilistic range; b) applying Monte Carlo Simulation to model variables; c) a synonym for stochastic or probabilistic estimating.
Range Of Accuracy
AACEi :
Syn.: Accuracy Range.
Rate Of Return
AACEi :
Syn.: Profitability Index (PI).
Raw Materials
AACEi :
Syn.: Crude Materials.
Re-Baselining
AACEi :
Process whereby the project’s costs, schedule, or resources are replanned due to changes in objectives, deliverables, or original scope. Often needed due to poor project definition or control. Re-baselining is not a substitute for best practices and typically involves reassessing the project control process.
Re-Usable Resource
APM :
A resource that, when no longer needed, becomes available for other uses, including accommodation, machines, test equipment, and personnel.
Real Discount Rate
AACEi :
The rate of interest reflecting the portion of the time value of money related to real earning power. Used in discount formulas or to select discount factors when future benefits and costs are in constant dollars.
Real Dollars
AACEi :
Syn.: Constant Dollars.
Real Estate
AACEi :
Physical land and appurtenances, including structures affixed thereto. In some states, synonymous with real property.
Real Property
AACEi :
Refers to the interests, benefits, and rights inherent in ownership of physical real estate. It is the bundle of rights associated with real estate ownership.
Reasonableness Standard
AACEi :
Costs that do not exceed those incurred by a prudent contractor or generally accepted costs. Factors include ordinary and necessary costs and restraints imposed by law, contract, or sound business practices.
Rebasing
AACEi :
Conversion of a price index from one time base to another.
Recovery Schedule
AACEi :
A schedule showing special efforts to recover lost time relative to the master schedule. Often a contract requirement when timely completion is in doubt.
Records Management System
PMI :
A set of processes, control functions, and tools consolidated to record and retain project information.
Recycle
AACEi :
Revisiting partially or fully completed activities to perform additional work due to a change.
Reduce
AACEi :
In risk management, a response strategy to mitigate threats by reducing probability and/or impact.
APM :
A response to a threat that reduces its probability, impact, or both.
Regression Analysis
PMI :
An analytic technique examining input variables relative to output results to develop a mathematical or statistical relationship.
Reject
APM :
A response to an opportunity where no action is taken.
Relationship
AACEi :
A logical connection between two activities.
Relationship Float
AACEi :
Relationship free float: lag increase required to delay a successor activity. Relationship total float: lag increase needed to delay project completion or violate a late target.
Relative Total Float
AACEi :
The difference between total float of one activity or path versus another, regardless of logical linkage.
Remaining Available Resources
AACEi :
The difference between resource availability and level schedule requirements, computed from the resource allocation process.
Remaining Duration
AACEi :
Estimated time remaining to complete an in-progress activity, not based solely on percent complete.
Remaining Float (RF)
AACEi :
The difference between early finish and late finish.
Remeasurement
AACEi :
A contract type, commonly in Europe, using quantity surveys for periodic progress payment, placing more cost risk on the owner than lump sum or milestone compensation.
Rental (Leased) Equipment Cost
AACEi :
The charge by the equipment owner (lessor) to a lessee for use. Evidenced by rental invoices.
Repeatable
APM :
The second level in a typical maturity model, where basic processes are established and discipline exists to repeat earlier successes.
Replacement
AACEi :
A facility proposed to take the place of an existing facility without increasing capacity, due to obsolescence or deterioration.
Replacement Cost
AACEi :
(1) Cost of replacing productive capacity of existing property to achieve most economical service at current prices.
(2) Facility component replacement costs in the capital budget expected during the study period.
Replacement Value
AACEi :
Value of an item based on replacing it in new condition with another item giving same service capacity, adjusted for physical deterioration.
Replanning
AACEi :
A change in the original plan requiring reevaluation and modifications.
Replanning, External Replanning
AACEi :
Customer-directed contract changes via change order requiring plan modification, subject to baseline change control.
Replanning, Internal Replanning
AACEi :
A change in the original plan within contract scope to compensate for cost, schedule, or technical issues making the original plan unrealistic.
Reports
APM :
1. Presentation of information in an appropriate format (e.g., Management Report).
2. Written or verbal record, summary, or detailed account.
Reporing System
PMI :
Facilities, processes, and procedures used to generate, consolidate, and distribute reports from information management systems to stakeholders.
Reproduction Cost
AACEi :
Cost of reproducing substantially identical items or facilities at a specified price level.
Reprogramming
AACEi : A comprehensive replanning of the efforts remaining in the contract resulting in a revised total allocated budget which exceeds the contract budget base. (Also defined as an over target baseline.)
Repudiation
AACEi : Syn.: Anticipatory Breach.
Request For Information (RFI)
PMI : A type of procurement document whereby the buyer requests a potential seller to provide various pieces of information related to a product or service or seller capability.
Request For Proposal
PMI : A type of procurement document used to request proposals from prospective sellers of products or services. In some application areas, it may have a narrower or more specific meaning.
Request For Quotation (RFQ)
PMI : A type of procurement document used to request price quotations from prospective sellers of common or standard products or services. Sometimes used in place of request for proposal and, in some application areas, it may have a narrower or more specific meaning.
Required Completion Date
AACEi : The required date of completion assigned to a specific activity or project.
Required Return
AACEi : The minimum return or profit necessary to justify an investment. It is often termed interest, expected return or profit, or charge for the use of capital.
Requirement
AACEi : (1) An established requisite characteristic of a product, process, or service. A characteristic is a physical or chemical property, a dimension, a temperature, a pressure, or any other specification used to define the nature of a product, process, or service.
(2) A negotiated set of measurable customer wants and needs.
PMI : A condition or capability that is required to be present in a product, service, or result to satisfy a contract or other formally imposed specification.
Requirement Documentation
PMI : A description of how individual requirements meet the business need for the project.
Requirement Management
APM : The process of capturing, assessing and justifying stakeholders’ wants and needs.
Requirement Management Plan
PMI : A component of the project or program management plan that describes how requirements will be analyzed, documented, and managed.
Requirements Traceability Matrix
PMI : A grid that links product requirements from their origin to the deliverables that satisfy them.
Resale Value
AACEi : The monetary sum expected from the disposal of an asset at the end of its economic life, its useful life, or at the end of the study period.
Reschedule
AACEi : (1) In construction, the process of changing the duration and/or dates of an existing schedule in response to externally imposed conditions or progress.
(2) In manufacturing, the process of changing order or operation due dates, usually as a result of their being out of phase with when they are needed.
Research Expense
AACEi : Those continuing expenses required to provide and maintain the facilities to develop new products and improve present products.
Reserve
AACEi : Syn.: Management Reserve; Reserve Allowance.
PMI : A provision in the project management plan to mitigate cost and/or schedule risk. Often used with a modifier (e.g., management reserve, contingency reserve) to provide further detail on what types of risk are meant to be mitigated.
Reserve Allowance
AACEi : Syn.: Management Reserve; Reserve.
Reserve Analysis
AACEi : An analytical technique to determine the essential features and relationships of components in the project management plan to establish a reserve for the schedule duration, budget, estimated cost, or funds for a project.
Reserve Stock
AACEi : Syn.: Safety Stock.
Resident Engineer
AACEi : The authorized representative of the engineer who is assigned to the site or any part thereof whose duties are ordinarily set forth in the contract documents and/or the engineer's agreement with the owner.
Residual Risk
AACEi : That portion of risks that remain after risk responses are implemented in full or in part.
PMI : A risk that remains after risk responses have been implemented.
Resource
AACEi : Any consumable, except time, required to accomplish an activity. From a total cost and asset management perspective, resources may include any real or potential investment in strategic assets including time, monetary, human, and physical. A resource becomes a cost when it is invested or consumed in an activity or project.
APM : All those items required to undertake work including people, finance and materials.
PMI : Skilled human resources (specific disciplines either individually or in crews or teams), equipment, services, supplies, commodities, material, budgets, or funds.
Resource Aggregation
AACEi : Summation of the requirements for each resource, and for each time period.
Resource Allocation
APM : The process by which resources are attributed to activities.
Resource Allocation Plan (RAP)
AACEi : Scheduling of activities in a network with knowledge of certain resource constraints and requirements. This process adjusts activity level start and finish dates to conform to resource availability and use.
Resource Availability Date
AACEi : Calendar date when a resource pool becomes available for a given resource.
Resource Availability Pool
AACEi : The extent to which resources are available to meet the project's needs.
APM : Resource Availability: The level of availability of a resource, which may vary over time.
Resource Breakdown Structure
PMI : A hierarchical representation of resources by category and type.
Resource Calendar
AACEi : 1) Calendar or database used to model available resources, which is then used by project management software for resource leveling analysis.
2) Calendar denoting when a resource or resource pool is available for work on a project.
PMI : A calendar that identifies the working days and shifts on which each specific resource is available.
Resource Code
AACEi : Code used to identify a given resource type.
Resource Constraint
AACEi : The limitations on available resources.
Resource Description
AACEi : The longest chain of activities in the schedule when limited resources are taken into consideration in addition to CPM duration and logic considerations. This may be accomplished by adding preferential “soft” logic, manual or automatic resource leveling, or just physically practiced on the field without prior planning.
Resource Description
AACEi : The actual name or identification associated with a resource code.
Resource Driven Task Duration
AACEi : Task duration that is driven by constrained resources.
Resource Group
AACEi : A set of resources that share some characteristics and that is categorized by a group name, such as job function, skill or contractor.
Resource Histogram
AACEi : A graphic display of the amount of resource required as a function of time on a graph. Individual, summary, incremental, and cumulative resource curve levels can be shown. Syn.: Resource Plot.
PMI : A bar chart showing the amount of time that a resource is scheduled to work over a series of time periods. Resource availability may be depicted as a line for comparison purposes. Contrasting bars may show actual amounts of resources used as the project progresses.
Resource Level
AACEi : A specified quantity of resource units required by an activity per time unit.
Resource Leveling
AACEi : Any form of network analysis in which scheduling decisions are driven by resource management concerns (e.g., limited resource availability or difficult to manage changes in resource levels). Syn.: Leveling; Resource Optimization.
APM : A scheduling calculation that delays activities such that resource usage is kept below specified limits. It is also known as resource limited scheduling.
PMI : A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Resource Limited Scheduling
AACEi : A schedule of activities so that a pre-imposed resource availability level (constant or variable) is not exceeded in any given project time unit.
Resource Loading/Resource Allocation
AACEi : The process of allocating or defining, through the use of resource calendars, the resources to be used on given activities.
Resource Optimization
AACEi : Syn.: Leveling; Resource Leveling.
PMI : Resource Optimization Technique: A technique that is used to adjust the start and finish dates of activities that adjust planned resource use to be equal to or less than resource availability.
Resource Planning
AACEi : The process of ascertaining future resource requirements for an organization or a scope of work and developing plans to meet those requirements.
Resource Plot
AACEi : Syn.: Resource Histogram.
Resource Requirements Planning
AACEi : In manufacturing, the process of converting the production plan and/or the master production schedule into the impact on key resources, such as labor, machine hours, storage, standard cost dollars, shipping dollars, inventory levels, etc.
Resource Smoothing
AACEi : Process of rescheduling activities such that the requirement for resources does not exceed resource limits. Smoothing is a type of resource leveling, except that the project completion date may not be delayed. Activities may only be delayed within their float.
PMI : A technique which adjusts the activities of a schedule model such that the requirement for resources on the project do not exceed certain predefined resource limits.
Resource Thresholds
AACEi : In resource-limited scheduling it is possible to specify that a particular resource may be exceeded, if necessary, by an amount not to exceed the specified threshold for that resource.
Resource Management
AACEi : The acquisition and deployment of the internal and external resources required to deliver the project, programme or portfolio.
Resource Scheduling
APM : A collection of techniques used to calculate the resources required to deliver the work and when they will be required.
Responsibility
AACEi : Originates when one accepts the assignment to perform assigned duties and activities. The acceptance creates a liability for which the assignee is held answerable for and to the assignor. It constitutes an obligation or accountability for performance.
PMI : An assignment that can be delegated within a project management plan such that the assigned resource incurs a duty to perform the requirements of the assignment.
Responsibility Assignment Matrix (RAM)
AACEi : Depicts the intersection of the WBS and the OBS. The OBS relates the Work Breakdown Structure (WBS) element to the organization and the named individual who is responsible for the assigned scope of a control account.
APM : A diagram or chart showing assigned responsibilities for elements of work. It is created by combining the work breakdown structure with the organisational breakdown structure.
PMI : A grid that shows the project resources assigned to each work package.
PCI : The RAM correlates the work required by a Contract Work Breakdown Structure (CWBS) element to the functional organisation responsible for accomplishing the assigned tasks. The responsibility assignment matrix is created by intersecting the CWBS with the programme organisational Breakdown Structure (OBS). This intersection identifies the cost account.
Responsibility Code
AACEi : System of applying an alphanumeric tag to an activity for grouping, sorting and summarization purposes. The responsibility code generally identifies the entity responsible for performing the coded activities.
Responsible Organization
AACEi : The organization responsible for management of a work package.
Rest Day
AACEi : A day where no work is scheduled on an activity or the project.
Restraint
AACEi : Syn.: Constraint.
Result
PMI : An output from performing project management processes and activities. Results include outcomes (e.g., integrated systems, revised process, restructured organization, tests, trained personnel, etc.) and documents (e.g., policies, plans, studies, procedures, specifications, reports, etc.). Contrast with product. See also deliverable.
Retainage
AACEi : Syn.: Retention.
Retained Logic
AACEi : One of two types of logic used to handle activities that occur out of sequence. When used, scheduling software schedules the remaining duration of an out-of-sequence activity according to current network logic after its predecessors.
Retention
AACEi : Usually refers to a percent of contract value retained by the purchaser until work is finished and testing of equipment is satisfactorily completed. Syn.: Retainage.
Retirement Of Debt
AACEi : The termination of a debt obligation by appropriate settlement with the lender. It is understood to be in full amount unless partial settlement is specified.
Return On Average Investment
AACEi : The ratio of annual profits to the average book value of fixed capital, with or without working capital. This method has some advantages over the return-on-original-investment method. Depreciation is always considered; terminal recoveries are accounted for. However, the method does not account for the timing of cash flow and yields answers that are considerably higher than those obtained by the return-on-original-investment and profitability index methods. Results may be deceiving when compared, say, against the company's cost of capital.
Return On Original Investment
AACEi : The ratio of expected average annual after tax profit (during the earning life) to total investment (working capital included). It is similar in usefulness and limitations to payoff period.
Return On Rate Base
AACEi : For a public utility, that monetary sum established by the proper regulatory authority as a basis for determining the charges to customers and the "fair return" to the owners of the utility.
Reverse Scheduling
AACEi : Method in which project completion date is fixed and task duration and dependency information is used to compute corresponding project start date.
Reviews
APM : A review is a critical evaluation of a deliverable, business case or P3 management process.
Revision
AACEi : In the context of planning and scheduling, a change in the network logic, activity duration, resources availability or resources demand which requires network recalculation and drawing correction(s).
Rework
AACEi : (1) Correction of defective work. May take place before, during or after inspection or testing.
(2) Action taken to ensure that a defective or nonconforming item complies with requirements or specifications.
PMI : Action taken to bring a defective or nonconforming component into compliance with requirements or specifications.
Ripple Effect
AACEi : The multiplying effect of change(s) and/or productivity impacts to upstream work that may have an adverse impact on the subsequent work to be performed.
Risk
AACEi : (1) An ambiguous term that can mean any of the following: a) All uncertainty (threats + opportunities); b) Undesirable outcomes (uncertainty = risks + opportunities); c) The net impact or effect of uncertainty (threats opportunities). The convention used should be clearly stated to avoid misunderstanding.
(2) Probability of an undesirable outcome.
(3) In total cost management, an uncertain event or condition that could affect a project objective or business goal.
APM : The potential of an action or event to impact on the achievement of objectives.
PMI : An uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives.
Risk (Impact) Compounding
AACEi : The concept that the combined impact of multiple risk events or condition occurrence differs from the impact of their individual occurrence. The risk events may be dependent or independent. Syn.: Compound Risk.
Risk Acceptance Criteria
AACEi : Criteria used to help define when the risk profile of a project or business initiative is acceptable to the decision makers and consequently risk treatment can cease.
PMI : Risk Acceptance: A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Risk Allocation
AACEi : In risk treatment, the process of transferring threats or sharing opportunities between parties, most commonly expressed in association with the contracting process.
Risk Analysis
AACEi : A risk management process step (part of risk assessment) and methodology for qualitatively and/or quantitatively screening, evaluating and otherwise analyzing risks to support risk treatment and control.
APM : An assessment and synthesis of risk events to gain an understanding of their individual significance and their combined impact on objectives.
Risk Appetite
AACEi : A component of the risk management plan that expresses the risk management objective in terms of a confidence interval or level for selected outcome measures.
APM : The tendency of an individual or group to take risk in a given situation.
PMI : The degree of uncertainty an entity is willing to take on, in anticipation of a reward.
Risk Assessment
AACEi : In TCM, a risk management process step, which includes the identification and analysis of risks.
Risk Attitude
APM : The response of an individual or group to a given uncertain situation.
Risk Audits
PMI : Examination and documentation of the effectiveness of risk responses in dealing with identified risks and their root causes, as well as the effectiveness of the risk management process.
Risk Averse
AACEi : Having little or no risk tolerance.
Risk Based Inspection
AACEi : Risk management as applied to maintenance projects with a focus on risk-based planning of inspections.
Risk Breakdown Structure (RBS)
AACEi : A framework or taxonomy to aid risk identification and for organizing and ordering risk types throughout the risk management process. Syn.: RBS; Risk Taxonomy;
PMI : A hierarchical representation of risks according to their risk categories.
Risk Categorization
PMI : Organization by sources of risk (e.g., using the RBS), the area of the project affected (e.g., using the WBS), or other useful category (e.g., project phase) to determine the areas of the project most exposed to the effects of uncertainty.
Risk Containment
AACEi : Syn.: Risk Safeguard.
Risk Context
APM : Describes the institutional and individual environment, attitudes and behaviours that affect the way risk arises and the way it should be managed.
Risk Control
AACEi : A risk management process step which includes the implementation of the risk response plan.
PMI : Control Risk: The process of implementing risk response plans, tracking identified risks, monitoring residual risks, identifying new risks, and evaluating risk process effectiveness throughout the project.
Risk Data Quality Assessment
PMI : Technique to evaluate the degree to which the data about risks is useful for risk management.
Risk Drivers
AACEi : Events or circumstances that may influence or cause uncertainty in asset or project performance. Syn.: Risk Factors.
Risk Efficiency
APM : The principle of risk-taking to achieve the minimum level of exposure to risk for a given level of expected return.
Risk Event
AACEi : Syn.: Event.
APM : An uncertain event or set of circumstances that would, if it occurred, have an effect on the achievement of one or more objectives.
Risk Factors
AACEi : Syn.: Risk Drivers.
Risk Identification
AACEi : A risk management process step (part of risk assessment) for identifying and describing risks for risk analysis and subsequent steps.
PMI : Identify Risk: The process of determining which risks may affect the project and documenting their characteristics.
Risk Impact Window
AACEi : Syn.: Exposure Window.
Risk Management
AACEi : A process for managing asset and project risks. In TCM, the process includes risk planning, risk assessment, risk treatment and risk control.
APM : A process that allows individual risk events and overall risk to be understood and managed proactively, optimising success by minimising threats and maximising opportunities.
PMI : Project Risk Management: Project Risk Management includes the processes of conducting risk management planning, identification, analysis, response planning, and controlling risk on a project.
Risk Management Audit
AACEi : An independent and documented quality assurance process to measure and assess compliance with risk management requirements and plans.
Risk Management Maturity
AACEi : Refers to the state of development and competency an organization has in risk management strategies, processes, methods, and tools.
Risk Management Plan
AACEi : The plan established by the asset planning or project team for carrying out risk assessment, risk treatment and risk control efforts.
PMI : A component of the project, program, or portfolio management plan that describes how risk management activities will be structured and performed.
Risk Management Team
AACEi : A select group of project team members that will be responsible for the completion and acceptance of the qualitative analysis once risks are identified.
Risk Matrix
AACEi : A method used in qualitative risk analysis to rate or rank the severity of risks in terms of their combined impact (or consequence) to some output measure that is at risk and the risk’s probability of occurrence. The matrix has impact on one axis and probability on the other with each intersecting node given predetermined severity rating designations (e.g., high, moderate, low). Syn.: Impact Versus Probability Rating.
Risk Mitigation
AACEi : A somewhat ambiguous term that typically includes any risk treatment action to reduce, transfer or eliminate a threat.
PMI : A risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.
Risk Owner
AACEi : A person(s) or entity charged with planning and implementing a specific risk response.
Risk Perception
AACEi : Subjective attitudes, judgments and biases of an asset or project stakeholder concerning the characteristics, probability and/or impact of a risk. This affects the establishment or expression of more objective risk policy, appetite and/or tolerances.
Risk Planning
AACEi : In TCM, a process for planning risk management throughout the asset or project life cycle.
Risk Policy
AACEi : In decision making, refers to the enterprise’s or decision maker’s established and preferably documented risk tolerance and general approach to treatment of risk in decision analysis.
Risk Profile
AACEi : A general term that refers to either qualitative or quantitative measures or indicators that describe the risk exposure and/or severity associated with an asset or project alternative or business initiative.
Risk Reassessment
PMI : Risk reassessment is the identification of new risks, reassessment of current risks, and the closing of risks that are outdated.
Risk Register
AACEi : A formal record of identified risks, typically including additional summary information as regards assessment, treatment and control of the risks. The content may be qualitative, quantitative or both.
APM : A document listing identified risk events and their corresponding planned responses.
PMI : A document in which the results of risk analysis and risk response planning are recorded.
Risk Response
AACEi : Strategies or actions identified and planned in the risk treatment process to address risks.
APM : An action or set of actions to reduce the probability or impact of a threat, or to increase the probability or impact of an opportunity.
Risk Safeguard
AACEi : An existing attribute or condition of an enterprise, asset or project scope (physical, planning or procedural) that may have risk treatment functionality. Syn.: Risk Containment.
Risk Screening
AACEi : In risk assessment, steps to prioritize identified risks for risk treatment and/or quantitative risk analysis (e.g., ranking by score or impact versus probability matrix).
Risk Sources
AACEi : A somewhat ambiguous term to describe categories used in risk identification and risk breakdown structures to describe process steps, stakeholders, organizational entities, environments, or other origins of risk causation.
PMI : Risk Category: A group of potential causes of risk.
Risk Taxonomy
AACEi : Syn.: RBS; Risk Breakdown Structure (RBS).
Risk Techniques
APM : Used to identify, assess and plan responses to individual risks and overall risk.
Risk Threshold
AACEi : A risk impact measure or indicator beyond which a risk response must be planned or a contingent response taken.
PMI : Measure of the level of uncertainty or the level of impact at which a stakeholder may have a specific interest. Below that risk threshold, the organization will accept the risk. Above that risk threshold, the organization will not tolerate the risk.
Risk Tolerance
AACEi : Refers to the ability or willingness of an asset or project stakeholder to accept potential risk impacts; the evaluation of risk tolerance guides risk treatment planning.
PMI : The degree, amount, or volume of risk that an organization or individual will withstand.
Risk Transference
PMI : A risk response strategy whereby the project team shifts the impact of a threat to a third party, together with ownership of the response.
Risk Treatment
AACEi : In TCM, a risk management process for identifying, evaluating, and selecting responses to identified risks.
Risk Trigger
AACEi : A measurable or observable event or condition that is a precursor to or indicator of a risk’s occurrence. Typically leads to initiation of a planned risk response.
Risk Types
AACEi : A means of characterizing risk for use in risk assessment by the type of risk.
Risk Urgency Assessment
PMI : Review and determination of the timing of actions that may need to occur sooner than other risk items.
Risk, External
AACEi : A risk taxonomy designation for a risk that is not caused by and/or not in the direct control of the stakeholders or project team.
Risk, Internal
AACEi : A risk taxonomy designation for a risk that is caused by and/or in the direct control of the stakeholders or project team.
Risk, Project-Specific
AACEi : A risk taxonomy designation used to classify project risks for the purposes of selecting a quantification method (i.e., contingency determination). Project-specific risks are uncertainties (threats or opportunities) related to events, actions, and other conditions that are specific to the scope of a project (e.g., weather, soil conditions, etc.). The impacts of project-specific risks are more or less unique to a project. In this taxonomy usage, it is the opposite of “systemic” risks.
Risk, Systemic
AACEi : A risk taxonomy designation used to classify project risks for the purposes of selecting a quantification method (i.e., contingency determination). Systemic risks are uncertainties (threats or opportunities) that are an artifact of an industry, company or project system, culture, strategy, complexity, technology, or similar over-arching characteristics. In this taxonomy usage, it is the opposite of “project-specific” risks.
Risk-Adjusted Critical Path
AACEi : Undeveloped theory that proposes using non-deterministic activity durations when considering the determination of the critical path.
Role
PMI : A defined function to be performed by a project team member, such as testing, filing, inspecting, or coding.
Rolling Wave Planning
AACEi : Refers to the process of maintaining detail short work packages for the near term and planning packages for the longer term. Typically this is accomplished for set periods (e.g., every 6 months) or to the next program level significant milestone. The purpose is to always have a discrete plan for the near term.
APM : The process whereby short term work is planned in detail and longer term work is planned in outline only.
PMI : An iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level.
Root Cause Analysis
PMI : An analytical technique used to determine the basic underlying reason that causes a variance or a defect or a risk. A root cause may underlie more than one variance or defect or risk.
Royalties
AACEi : Payments a company receives to allow others to use a design or concept the company has researched and developed to commercialization. Generally, one of two types:
1) Paid-up royalties where a lump sum payment is made; and
2) Running royalties where continuous payments are made, usually based on actual production or revenues.
Rubber Baseline
AACEi : An ambiguous term meaning a non-stable performance measurement baseline (PMB) plan. In a negative context it can refer to:
1) A baseline that is frequently single point adjusted to eliminate earned value management variances.
2) A baseline that is frequently changed to avoid variances rather than for technical performance reasons.
Rules Of Credit
AACEi : In project control, a procedure according to which the progress on project activities shall be measured.
S-Curve
AACEi : (1) In the context of risk management, a cumulative distribution of the probability of values in a defined range produced by quantitative risk analysis.
(2) In the context of project control, a cumulative distribution of costs, labor hours, progress, or other quantities plotted against time.
APM : A graphic display of cumulative costs, labour hours or other quantities, plotted against time.
Safety Stock
AACEi : The average amount of stock on hand when a replenishment quantity is received. Its purpose is to protect against the uncertainty in demand and in the length of the replenishment lead time. Safety stock and cycle stock are the two main components of any inventory. Syn.: Reserve Stock.
Safety Time
AACEi : In a time series planning system, material is frequently ordered to arrive ahead of the forecast requirement date to protect against forecast error. The difference between the forecast requirement date and the planned in-stock date is safety time.
Sales
AACEi : Orders booked by customers.
Sales Forecast
AACEi : A prediction or estimate of sales, in dollars or physical units, for a specified future period under a proposed marketing plan or program and under an assumed set of economic and other forces outside the unit for which the forecast is made. The forecast may be for a specified item of merchandise or for an entire line.
Sales Price
AACEi : The revenue received for a unit of a product. Gross sales price is the total amount paid. Net sales are gross sales less returns, discounts, freight and allowances. Plant netbacks are net sales less selling, administrative and research expenses. Syn.: Selling Price.
Sales Profile
AACEi : The growth or decline of historical or forecast sales volume, by years.
Sales Revenue
AACEi : Revenue received as a result of sales, but not necessarily during the same time period.
Salvage Value
AACEi : (1) The market value of a machine or facility at any point in time (normally an estimate of an asset's net market value at the end of its estimated life).
(2) The value of an asset, assigned for tax computation purposes, which is expected to remain at the end of the depreciation period.
Savings-To-Investment Ratio (SIR)
AACEi : Either the ratio of present value savings to present value investment costs, or the ratio of annual value savings to annual value investment costs. [1]
Scaling Factor
AACEi : Syn.: Capacity Factor; Capacity Utilization Factor.
Scatter Diagram
PMI : A correlation chart that uses a regression line to explain or to predict how the change in an independent variable will change a dependent variable.
Scenario
AACEi : A description of specific events and conditions and their probable outcomes. Usually limited to likely or probable scenarios versus all possible ones. Frequently, “most likely,” “best case,” and “worst case” scenarios are used to define the most probable outcome and the range of outcomes.
Scenario Analysis
AACEi : Methods to assess a range of events, conditions, and outcomes employing specific scenarios. An alternative to simulation methods for assessing ranges.
Schedule
AACEi : (1) A description of when each activity in a project can be accomplished and must be finished so as to be completed timely. The simplest of schedules depict in bar chart format the start and finish of activities of a given duration. More complex schedules, general in CPM format, include schedule logic and show the critical path and floats associated with each activity.
(2) A time sequence of activities and events that represent an operating timetable. The schedule specifies the relative beginning and ending times of activities and the occurrence times of events. A schedule may be presented on a calendar framework or on an elapsed time scale.
APM : A timetable showing the forecast start and finish dates for activities or events within a project, programme or portfolio.
PMI : Project Schedule: An output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources.
Schedule Baseline
AACEi : In earned value, the baseline start and completion dates used for integration with work authorization and costs. It is considered the time element of the performance measurement baseline (PMB).
PMI : The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
Schedule Buffer
AACEi : Syn.: Schedule Contingency.
Schedule Compression
AACEi : A method of schedule analysis used to shorten the critical path of the schedule. This may be accomplished by re-sequencing work, employing greater resources to accomplish more work in a given time, or otherwise reducing the duration of critical path activities. The need for schedule compression may come about because of the owner’s desire to complete early, make up for delays, or to accommodate added work.
PMI : Techniques used to shorten the schedule duration without reducing the project scope.
Schedule Contingency
AACEi : (1) Duration added to a schedule activity to allow for the probability of possible or unforeseen events. Use in this manner is not recommended as the contingency is hidden and may be misused.
(2) A unique activity used to model specific float available to a project phase. Used in this manner gives ownership of float to those activities and or responsibility entity.
(3) The amount of time added to specific activities of a project (or program) schedule to mitigate (dampen/buffer) the effects of risks or uncertainties identified or associated with specific elements of that schedule. Syn.: Schedule Buffer.
Schedule Data
PMI : The collection of information for describing and controlling the schedule.
Schedule Decompression
AACEi : The opposite of schedule compression and results in lengthening the critical path. The need to reduce costs, work within limited resource constraints, and eliminate the use of overtime are some of the reasons for schedule decompression.
Schedule Graphics
AACEi : Presentation charts and images used to communicate schedule progress and highlight areas of concern. Usually supplements the schedule report. Schedule graphics can include bar charts, time scaled logic diagrams, fragnets, etc.
Schedule Management
APM : The process of developing, maintaining and communicating schedules for time and resource.
Schedule Management Plan
PMI : A component of the project management plan that establishes the criteria and the activities for developing, monitoring, and controlling the schedule.
PCI : The Schedule Management Plan defines scope, purpose, and policy; participant roles and responsibilities; objectives; processes and procedures; organisational responsibilities and relationships; tools; reporting requirements; and related documents. It guides the overall implementation of schedule development and management over time.
Schedule Margin (SM)
AACEi : Schedule margin or schedule reserve are interchangeable terms meaning duration added to a schedule activity to allow for the probability of possible or unforeseen events. It is typically based on a schedule risk assessment and is measured in the unit of the schedule (typically days). For earned value management, schedule margin is usually limited to logical end points within the schedule. Schedule margin acts as a buffer between the baseline activities and the project end date. It may be considered management reserve (MR) in time units. Syn.: Schedule Reserve.
Schedule Model
AACEi : A mathematical representation of a schedule that can be used in modeling. A CPM schedule network is the most common schedule model.
PMI : A representation of the plan for executing the project’s activities including durations, dependencies, and other planning information, used to produce a project schedule along with other scheduling artifacts.
Schedule Network Templates
PMI : A set of activities and relationships that have been established that can be used repeatedly for a particular application area or an aspect of the project where a prescribed sequence is desired.
Schedule Of Values
AACEi : A detailed statement furnished by a construction contractor, builder, or others, apportioning the contract value into work packages. It is used as the basis for submitting and reviewing progress payments.
Schedule Percent Complete
AACEi : The proportion of an activity or all the project’s activities that has been completed.
PMI : A measure of schedule efficiency expressed as the ratio of earned value to planned value.
PCI : Ratio of work accomplished versus work planned, for a specified time period. The SPI is an efficiency rating for work accomplishment, comparing work accomplished to what should have been accomplished.
Schedule Performance Index [SPI(T)]
AACEi : A time-based performance index determined by earned schedule (the accomplished value in time increments) divided by the actual time increments that have elapsed.
Schedule Refinement
AACEi : Rework, redefinition or modification of the logic or data that may have previously been developed in the planning process as required to properly input milestones, restraints and priorities.
Schedule Report
AACEi : A periodic report outlining progress, highlighting significant progress of activities on the critical path and areas of concern that may require corrective action. A schedule report typically includes a narrative, tabular listings by various sorts, and time scaled CPM diagrams.
Schedule Reserve
AACEi : Syn.: Schedule Margin (SM).
Schedule Revision
AACEi : In the context of scheduling, a change in the network logic or in resources which requires redrawing part or the entire network.
Schedule Risk
AACEi : The risks (threats, opportunities, or both) the team might encounter in meeting the deadlines for the final deliverable or affecting any activity, milestone or element of the schedule plan.
Schedule Sensitivity
AACEi : Identifies and ranks the tasks most likely to influence the project duration/finish.
Schedule Slip
AACEi : Slippage in the final completion date of a project.
Schedule Traceability
AACEi : A broad term meaning the coding necessary in the schedule to show integration with work authorization, budgeting, accounting, and other earned value management components. Traceability demonstrates the completeness of the schedule content.
Schedule Update
AACEi : Process of updating progress as of a data date and reporting that progress.
Schedule Variance (SV)
AACEi : (1) Difference between projected start/finish dates and actual or revised start/finish dates.
(2) The difference between the earned value and scheduled value. Schedule variance = budgeted cost of work performed (BCWP) - budgeted cost of work scheduled (BCWS). A negative cost variance indicates that the activity(ies) is running behind schedule.
PMI : A measure of schedule performance expressed as the difference between the earned value and the planned value.
PCI : The difference between the budgeted cost of work performed and the budgeted cost of work scheduled at any point in time (BCWP-BCWS).
Schedule Variance [SV(T)]
AACEi : The time difference between the earned schedule (the accomplished value in time increments through a planned period) and the actual time increments that have elapsed.
Schedule Work Unit
AACEi : A calendar time unit when work may be performed on an activity.
Scheduled Completion Date
AACEi : A date assigned for completion of activity or accomplishment of an event for purposes of meeting specified schedule requirements.
Scheduled Dates
AACEi : The start, intermediate, or final dates imposed by contract or other means that impact the project schedule.
Scheduled Event Time
AACEi : In PERT, an arbitrary schedule time that can be introduced at any event but is usually only used at a certain milestone or the last event.
Scheduling
AACEi : (1) Assignment of desired start and finish times to each activity in the project within overall time cycle required for completion according to plan.
(2) Process of converting a general or outline plan for a project into a time-based schedule based on available resources and time constraints. Syn.: Diagramming (Schedule).
Scheduling Rules
AACEi : Basic rules that are spelled out ahead of time so that they can be used consistently in a scheduling system.
Scheduling Techniques
AACEi : Systems and processes available for determination and presentation (modeling) of a project plan. Examples include arrow diagramming, logic networks, bar charts, PERT, trending, etc. using a variety of software.
Scheduling Tool
PMI : A tool that provides schedule component names, definitions, structural relationships, and formats that support the application of a scheduling method.
Scope
AACEi : The sum of all that is to be or has been invested in and delivered by the performance of an activity or project. In project planning, the scope is usually documented (i.e., the scope document), but it may be verbally or otherwise communicated and relied upon. Generally limited to that which is agreed to by the stakeholders in an activity or project (i.e., if not agreed to, it is “out of scope”). In contracting and procurement practice, includes all that an enterprise is contractually committed to perform or deliver. Syn.: Project Scope.
APM : The totality of the outputs, outcomes and benefits and the work required to produce them.
PMI : Project Scope: The work performed to deliver a product, service, or result with the specified features and functions. Scope: The sum of the products, services, and results to be provided as a project.
Scope Baseline
PMI : The approved version of a scope statement, work breakdown structure (WBS), and its associated WBS dictionary, that can be changed only through formal change control procedures and is used as a basis for comparison.
Scope Change
AACEi : Syn.: Change In Scope.
PMI : Any change to the project scope. A scope change almost always requires an adjustment to the project cost or schedule.
Scope Creep
AACEi : Gradual progressive change (usually additions to) of the project's scope such that it is not noticed by project management team or customer. Typically occurs when the customer identifies additional, sometimes minor, requirements that, when added together, may collectively result in a significant scope change, resulting in cost and schedule overruns. [8]
PMI : The uncontrolled expansion to product or project scope without adjustments to time, cost, and resources.
Scope Definition
AACEi : Division of the major deliverables into smaller, more manageable components to:
1) Improve the accuracy of cost, time, and resource estimates;
2) Define a baseline for performance measurement and control; and
3) Facilitate clear responsibility assignments.
PMI : Define Scope: The process of developing a detailed description of the project and product.
Scope Management
AACEi : The process whereby outputs, outcomes and benefits are identified, defined and controlled.
PMI : Project Scope Management: Project Scope Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
Seasonal Commodities
AACEi : Commodities which are normally available in the market-place only in a given season of the year.
Seasonal Variation
AACEi : That movement in many economics series which tends to repeat itself within periods of a year.
Secondary Float (SF)
AACEi : Same as total float, except that it is calculated from a schedule date upon an intermediate event.
Secondary Risks
AACEi : Risks that occur from actions taken to treat other risks.
Secular Trend
AACEi : The smooth or regular movement of a long-term time series trend over a fairly long period of time.
Security
APM : The identification, assessment and mitigation of the risks posed to information, assets and people.
Selected Sellers
PMI : The sellers which have been selected to provide a contracted set of services or products.
Seller
PMI : A provider or supplier of products, services, or results to an organization.
Seller Proposal
PMI : Formal responses from sellers to a request for proposal or other procurement document specifying the price, commercial terms of sale, and technical specifications or capabilities the seller will do for the requesting organization that, if accepted, would bind the seller to perform the resulting agreement.
Selling Expense
AACEi : The total expense involved in marketing the products in question. This normally includes direct selling costs, advertising, and customer service.
Selling Price
AACEi : Syn.: Sales Price.
Sensitivity
AACEi : The relative magnitude of the change in one or more elements of an engineering economy, estimate, schedule, risk or other planning analysis that will reverse a decision among alternatives. More generally, it is the degree to which a change in an element of a model affects the outcome.
Sensitivity Analysis
AACEi : A test of the outcome of an analysis by altering one or more parameters from an initially assumed value(s). [1]
PMI : A quantitative risk analysis and modeling technique used to help determine which risks have the most potential impact on the project. It examines the extent to which the uncertainty of each project element affects the objective being examined when all other uncertain elements are held at their baseline values. The typical display of results is in the form of a tornado diagram.
Sentimental Value
AACEi : A value associated with an individual's personal desire, usually related to a prior personal relationship.
PMI : Sequence Activities: The process of identifying and documenting relationships among the project activities.
Sequence
AACEi : A change in the order of work initially specified or planned by the contractor. If this change is ordered by the owner and results in additional cost to the contractor, the contractor may be entitled to recovery under the changes clause.
Service Worth Value
AACEi : Earning value, assuming the rates and/or prices charged are just equal to the reasonable worth to customers of the services and/or commodities sold.
Serviceability
AACEi : A measure of the degree to which servicing of an item will be accomplished within a given time under specified conditions.
Servicing
AACEi : The replenishment of consumables needed to keep an item in operating condition, but not including any other preventive maintenance or any corrective maintenance.
Setting
APM : The relationship of the project, programme or portfolio with its host organisation.
Seven Basic Quality Tools
PMI : A standard toolkit used by quality management professionals who are responsible for planning, monitoring, and controlling the issues related to quality in an organization.
Severe Weather
AACEi : A weather event, which is in itself severe and can be of violent nature. If the average weather over time is significantly different from the normal then it is said to be other than normal. In either case, if such weather affects the job and causes a delay, it may be excusable and form the basis for a contract adjustment for time and possibly money once all relevant contract clauses are considered.
Shall
AACEi : Use of the word 'shall' in contract language means that 'you must', as opposed to ‘may’.
Share
AACEi : In TCM risk management, a risk response strategy for opportunities that involves sharing the risk with a third party who is better able to manage it.
APM : A response to an opportunity that increases its probability, impact or both by sharing the risk with a third party.
Shifting Base
AACEi : Changing the point of reference of an index number series from one time reference period to another.
Shop Drawings
AACEi : All drawings, diagrams, illustrations, schedules and other data which are specifically prepared by or for the contractor to illustrate some portion of the work and all illustrations, brochures, standard schedules, performance charts, instructions, diagrams and other information prepared by a supplier and submitted by the contractor to illustrate material or equipment for some portion of the work.
Shop Order Number
AACEi : Syn.: Account number.
Shop Planning
AACEi : The coordination of material handling, material availability, the setup and tooling availability so that a job can be done on a particular machine.
Short-Term Activities
AACEi : Syn.: Monthly Guide Schedule.
Shutdown Point
AACEi : The production level at which it becomes less expensive to close the plant and pay remaining fixed expenses out-of-pocket rather than continue operations; that is, the plant cannot meet its variable expense.
Significant Variances
AACEi : Those differences between planned and actual performance which exceed established thresholds and which require further review, analysis and action.
Simple Interest
AACEi : (1) Interest that is not compounded is not added to the income-producing investment or loan.
(2) The interest charges under the condition that interest in any time period is only charged on the principal.
Simple Payback Period (SPP)
AACEi : The time required for the cumulative benefits from an investment to pay back the investment cost and other accrued costs, not considering the time value of money. [1]
Simulation
AACEi : Application of a physical or mathematical model to observe and predict probable performance of the actual item or phenomenon to which it relates.
PMI : A simulation uses a project model that translates the uncertainties specified at a detailed level into their potential impact on objectives that are expressed at the level of the total project. Project simulations use computer models and estimates of risk, usually expressed as a probability distribution of possible costs or durations at a detailed work level, and are typically performed using Monte Carlo analysis.
Single Point Estimate
AACEi : Syn.: Base Estimate; Point Estimate.
Sinking Fund
AACEi : (1) A fund accumulated by periodic deposits and reserved exclusively for a specific purpose, such as retirement of a debt or replacement of a property.
(2) A fund created by making periodic deposits (usually equal) at compound interest in order to accumulate a given sum at a given future time for some specific purpose.
Site Preparation
AACEi : An act involving grading, landscaping, drainage, installation of roads and siding, of an area of ground upon which anything previously located had been cleared so as to make the area free of obstructions, entanglements or possible collisions with the positioning or placing of anything new or planned.
Slack
AACEi : Syn.: Float; Path Float.
Slack Paths
AACEi : The sequences of activities and events that do not lie on the critical path or paths.
Slack Time
AACEi : The difference in calendar time between the scheduled due date for a job and the estimated completion date. If a job is to be completed ahead of schedule, it is said to have slack time; if it is likely to be completed behind schedule, it is said to have negative slack time. Slack time can be used to calculate job priorities using methods such as the critical ratio. In the critical path method, total slack is the amount of time a job may be delayed in starting without necessarily delaying the project completion time. Free slack is the amount of time a job may be delayed in starting without delaying the start of any other job in the project.
Slip Chart
AACEi : A pictorial representation of the predicted completion dates of milestones. Also referred to as trend chart.
APM : A pictorial representation of the predicted completion dates of milestones or activities compared to their planned completion dates.
Slippage
AACEi : Amount of time a task has been delayed from its original baseline plan. Slippage is the difference between scheduled start or finish date for a task and baseline start or finish date. Slippage can occur when a baseline plan is set and actual dates subsequently entered for tasks are later than baseline dates, or actual durations are longer than baseline durations.
Smoothing
AACEi : In resource-scheduling, refers to an option that modifies the way time-limited (and resource-limited with thresholds) scheduling works. Objective is to minimize the extent that each resource availability is exceeded. Standard algorithm gives itself the maximum flexibility to achieve this by making use of any excess already incurred. Smoothing option modifies this so that it will not use excess for a particular activity unless necessary in order to schedule that activity within its total float.
Solutions Development
APM : The process of determining the best way of satisfying requirements.
Source Selection Criteria
PMI : A set of attributes desired by the buyer which a seller is required to meet or exceed to be selected for a contract.
Specification Limit
PMI : The area, on either side of the centerline, or mean, of data plotted on a control chart that meets the customer’s requirements for a product or service. This area may be greater than or less than the area defined by the control limits.
Specification Tree
AACEi : A graphic portrayal arranged to illustrate interrelationships of hardware and/or software performance/design requirements specifications. Normally, this portrayal is in the form of a “family tree” subdivision of specifications, with each lower level specification applicable to a hardware/software item that is part of a higher level item. [7]
Specification(S)
AACEi : (1) A detailed, exact statement of particulars, especially a statement prescribing materials, dimensions, and quality of work for something to be built, installed, or manufactured.
(2) A document that prescribes the requirements with which the product or services has to conform.
PMI : A document that specifies, in a complete, precise, verifiable manner, the requirements, design, behavior, or other characteristics of a system, component, product, result, or service and the procedures for determining whether these provisions have been satisfied. Examples are: requirement specification, design specification, product specification, and test specification.
Specification, Design
AACEi : A design specification providing a detailed written and/or graphic presentation of the required properties of a product, material, or piece of equipment, and prescribing the procedure for its fabrication, erection, and installation.
Specification, Performance
AACEi : A statement of required results, verifiable as meeting stipulated criteria, and generally free of instruction as to the method of accomplishment.
Spiral Life Cycle
APM : A life cycle model that combines features of both iterative development and the waterfall method.
Split Task
AACEi : A task divided into two or more portions, with time gaps between one portion and another that indicate an interruption in work on the task.
Splittable Activity
AACEi : Activity that can be interrupted in order to allow temporary transfer of its resources to another activity.
Splitting
AACEi : Dividing (i.e., splitting) an activity of stated scope, description and schedule into two or more activities which are rescoped and rescheduled. The sum of the split activities is normally the total of the original.
Sponsoring Organization
PMI : The entity responsible for providing the project’s sponsor and a conduit for project funding or other project resources.
Sponsorship
APM :
An important senior management role. The sponsor is accountable for ensuring that the work is governed effectively and delivers the objectives that meet identified needs.
PMI :
Sponsor: A person or group who provides resources and support for the project, program, or portfolio and is accountable for enabling success.
Spot Market Price Index
AACEi :
Daily index used as a measure of price movements of sensitive basic commodities whose markets are to be presumed to be among the first to be influenced by changes in economic conditions. It serves as one early indicator of impending changes in business activity.
Sprint
APM :
A regular repeatable work cycle in Agile development. Also known as an ‘iteration’.
Staffing Management Plan
PMI :
A component of the human resource plan that describes when and how project team members will be acquired and how long they will be needed.
Stage
APM :
A sub-division of the development phase of a project created to facilitate approval gates at suitable points in the life cycle.
Stage Of Processing
AACEi :
A commodity's intermediate position in the value-added channel of production.
Stakeholder
AACEi :
Decision makers, people or organizations that can affect or be affected by a decision.
APM :
The organisations or people who have an interest or role in the project, programme or portfolio, or are impacted by it.
PMI :
An individual, group, or organization who may affect, be affected by, or perceive itself to be affected by a decision, activity, or outcome of a project.
Stakeholder Analysis
AACEi :
A process used to determine the degree of interest, influence and attitude of stakeholders toward a particular asset, project or business objective.
PMI :
A technique of systematically gathering and analyzing quantitative and qualitative information to determine whose interests should be taken into account throughout the project.
Stakeholder Management
APM :
The systematic identification, analysis, planning and implementation of actions designed to engage with stakeholders.
PMI :
Project Stakeholder Management: Project Stakeholder Management includes the processes required to identify all people or organizations impacted by the project, analyzing stakeholder expectations and impact on the project, and developing appropriate management strategies for effectively engaging stakeholders in project decisions and execution.
Stakeholder Register
PMI :
A project document including the identification, assessment, and classification of project stakeholders.
Stand Alone
AACEi :
A system that performs its function requiring little or no assistance from interfacing systems.
Standard
AACEi :
A specific statement of the rules and constraints governing the naming, contents, and operations of deliverables. The rules and constraints are designed to support specific objectives.
PMI :
A document that provides, for common and repeated use, rules, guidelines, or characteristics for activities or their results, aimed at the achievement of the optimum degree of order in a given context.
Standard Network Diagram
AACEi :
A predefined network intended to be used more than one time in any given project.
Standard Operating Procedure
AACEi :
Detailed step-by-step instructions for repetitive operations. Examples are aircraft takeoff and landing procedures.
Standard Time
AACEi :
A measure of the time it should take a qualified worker to perform a particular task.
Start Date
PMI :
A point in time associated with a schedule activity’s start, usually qualified by one of the following: actual, planned, estimated, scheduled, early, late, target, baseline, or current.
Start Event Of A Project
AACEi :
Event with succeeding, but no preceding activities. There may be more than one start event.
Start Float
AACEi :
Amount of excess time an activity has between its early start and late start dates.
Start-To-Finish (SF)
AACEi :
A relationship in which the successor activity depends upon and can finish only after the predecessor activity starts. The predecessor must start first and then the successor can finish.
APM :
A dependency in an activity-on-node network. It indicates that one activity cannot finish until another activity has started.
PMI :
A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Start-To-Start (SS)
AACEi :
A relationship between activities in which the start of a successor activity depends on the start of its predecessor. The predecessor must start prior to the successor starting.
APM :
A dependency in an activity-on-node network. It indicates that one activity cannot start until another activity has started.
PMI :
A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Start-To-Start Lag
AACEi :
Minimum amount of time that must pass between the start of one activity and the start of its successor(s). May be expressed in terms of duration or percentage.
Starting Event
AACEi :
Syn.: Beginning Event; Preceding Event; Predecessor Event.
Startup
AACEi :
The project activities (or phase) that take place between commissioning and the achievement of steady-state operation. In some usage, the term startup may include both commissioning (i.e., testing after mechanical completion) and startup (it may then be referred to as ‘startup and testing’); one must take care to ascertain what the user of this term means. Production may not be at planned capacity or quality at the end of the phase.
Startup Costs
AACEi :
Extra operating costs to bring the plant on stream incurred between the completion of construction and beginning of normal operations. In addition to the difference between actual operating costs during that period and normal costs, it also includes employee training, equipment tests, process adjustments, salaries and travel expense of temporary labor, staff and consultants, report writing, post-startup monitoring and associated overhead. Additional capital required to correct plant problems may be included. Startup costs are sometimes capitalized.
Statement Of Work (SOW)
AACEi :
A narrative description of the work to be performed.
APM :
An annex to the main body of a contract that defines the detail of deliverables, timescales and management procedures.
PMI :
A narrative description of products, services, or results to be delivered by the project.
PCI :
A description of product and service to be procured under contract; a statement of requirements.
Static Risk
AACEi :
Risk for which the characteristics, probability and/or impact do not change over time or with the occurrence of preceding events.
Statistical Sampling
PMI :
Choosing part of a population of interest for inspection.
Status Date
AACEi :
The date that the schedule is statused through, earned value is calculated through, and actual costs are integrated with. In earned value, is also the date that variance analysis and baseline control is maintained against.
Status Line
AACEi :
A vertical line on a time-scaled schedule indicating the point in time (date) on which the status of the project is reported. Often referred to as the time now line.
Status Report
AACEi :
(1) Description of where the project currently stands; part of the performance reporting process.
(2) Formal report on the input, issues, and actions resulting from a status meeting.
Statusing
AACEi :
Indicating on the schedule the most current project status.
Status
AACEi :
(1) Comparison of actual progress against the plan to determine variance and corrective action.
(2) An instantaneous snapshot of the then current conditions.
Stock And Bond Value
AACEi :
A special form of market value for enterprises, which can be owned through possession of their securities. Stock and bond value is the sum of: 1) The par values in dollars of the different issues of bonds multiplied by the corresponding ratios of the market price to the par value; and 2) The number of shares of each issue of stock multiplied by the corresponding market price in dollars per share.
Stop Work Order
AACEi :
Request for interim stoppage of work due to non-conformance, or funding or technical limitations.
Straight-Line Depreciation
AACEi :
Method of depreciation whereby the amount to be recovered (written off) is spread uniformly over the estimated life of the asset in terms of time periods or units of output.
Strategic Asset
AACEi :
Any unique physical or intellectual property that is of long term or ongoing value to the enterprise. As used in total cost management, it most commonly includes capital or fixed assets, but may include intangible assets. Excludes cash and purely financial assets. Strategic assets are created by the investment of resources through projects.
Strategic Asset Management
AACEi :
A subprocess of the total cost management (TCM) process that includes the management of the total life cycle cost investment of resources in an enterprise’s portfolio of strategic assets. Excludes, but integrated with, the project control process.
Strategic Management
APM :
The identification, selection and implementation of an organisation’s long term goals and objectives.
Strategic Risk
AACEi :
(1) A risk for which the potential impact threatens a project objective, even if the probability of occurrence is low or risk matrix severity rating is within screening thresholds. In projects, these risks are generally funded through management reserves.
(2) A risk that has a significant potential impact on enterprise, portfolio or other higher objectives or plans beyond the project level.
Strategy
AACEi :
Action plan to set the direction for the coordinated use of resources through programs, projects, policies, procedures, and organizational design and establishment of performance standards.
Stretching
AACEi :
In resource scheduling it is possible to specify that an activity duration may be stretched if this results in an earlier scheduled finish date. This means that the specified duration may be increased, while the specified resource profile is reduced proportionally.
Study Period
AACEi :
The length of time over which an investment is analyzed. Syn.: Time Horizon.
Subcontract
AACEi :
A contract that assigns some of the obligations of a prior contract to another party.
Subcontractor
AACEi :
One that enters into a subcontract and assumes some of the obligations of the primary contractor.
Subindex
AACEi :
A price index for a sub-aggregate of a given basket of commodities.
Subject Matter Expert (SME)
PCI :
The Subject Matter Expert is the individual(s) who exhibits the highest level of expertise in performing a specialised job, task, or skill within the organisation.
Subnetwork
AACEi :
Syn.: Fragent.
PMI :
A subdivision (fragment) of a project schedule network diagram, usually representing a subproject or a work package. Often used to illustrate or study some potential or proposed schedule condition, such as changes in preferential schedule logic or project scope.
Subnetwork Float
AACEi :
Total float on a fragnet when it is extracted from the overall network. This is relevant in dealing with delay issues particular to a certain subcontractor or a supplier responsible for only a part of the overall project.
Subproject
AACEi :
(1) A smaller project within a larger one. Often used to segregate into components that are more manageable.
(2) Component of a project. Often contracted out to an external enterprise or another functional unit in the performing organization.
APM :
A group of activities represented as a single activity in a higher level of the same project.
PMI :
A smaller portion of the overall project created when a project is subdivided into more manageable components or pieces.
Substantial Completion
AACEi :
(1) Work (or a specified part thereof) which has progressed to the point where in the opinion of the engineer, as evidenced by the engineer's definitive certificate of substantial completion, it is sufficiently complete, in accordance with the contract documents, so that the work (or specified part) can be utilized for the purposes for which it is intended; or if there be no such certificate issued, when final payment is due in accordance with the general conditions. Substantial completion of the work, or specified part thereof, may be achieved either upon completion of pre-operational testing or startup testing, depending upon the requirements of the contract documents. The terms substantially complete and substantially completed as applied to any work refer to substantial completion thereof.
(2) For an activity, when the work is generally completed with the exception of minor remedial work, thus allowing any successor activities to start unimpeded. For a project this is the point where the work is complete and the owner can start using the project for its intended purpose. The only remaining work would be categorized as punch list work.
(3) The time when the facility is available to operate safely for the intended purpose.
Substantial Performance
AACEi :
Considered to be reached when:
1) The work or a substantial part of it is ready for use or is being used for the purpose intended;
2) The work to be done under the contract can be completed or corrected at a cost of not more than, say, 1% to 3% of the contract price depending on the size of the contract; and
3) Is so certified by a certificate of substantial performance issued by client or its consultant.
Subsystem
AACEi :
An aggregation of component items (hardware and software) performing some distinguishable portion of the function of the total system of which it is a part. Normally, a subsystem could be considered a system in itself if it were not an integral part of the larger system.
Subtask
AACEi :
Portion of a task or work element.
Success Criteria
APM :
The qualitative or quantitative measures by which the success of P3 management is judged.
Success Factors And Maturity
APM :
Management practices that, when implemented, will increase the likelihood of success of a project, programme or portfolio. The degree to which these practices are established and embedded within an organisation indicates its level of maturity.
Success Tree Analysis (STA)
AACEi :
A risk analysis method used to evaluate risk opportunities employing a success tree which shows the combination of successful events leading to the success of parent event.
Successor
AACEi :
An activity that immediately succeeds another activity.
Successor Activity
AACEi :
An activity, which logically follows the accomplishment of part or all of a given activity.
PMI :
A dependent activity that logically comes after another activity in a schedule.
Successor Event
AACEi :
The event that signifies the completion of an activity.
Sum-Of-Digits Method
AACEi :
A method of computing depreciation in which the amount for any year is based on the ratio: (years of remaining life)/(1+2+3+...+n), where n is the total anticipated life. Syn.: Sum-Of-The-Years-Digits Method.
Sum-Of-The-Years-Digits Method
AACEi :
Syn.: Sum-Of-Digits Method.
Summary Activity
PMI :
A group of related schedule activities aggregated and displayed as a single activity.
Summary Item
AACEi :
An item appearing in the work breakdown structure.
Summary Level Planning Package (SLPP)
AACEi :
An optional budget level above the control account and below the reporting level to the owner. SLPPs have scope, schedule, and budget and are limited to significant outer year periods. They are allocated to control accounts and converted to planning packages at the earliest opportunity.
Summary Network
AACEi :
A summarization of the CPM network for presentation purposes. This network is not computed.
Summary Number
AACEi :
A number that identifies an item in the work breakdown structure.
Summary Schedule
AACEi :
A single page, usually time-scaled, project schedule. Typically included in management level progress reports. In earned value, it can be reconciled with the performance measurement baseline (PMB) schedule.
Summary Task
AACEi :
A task that consists of a logical group of tasks, called subtasks. Primarily used for reporting purposes.
Sunk Cost
AACEi :
A cost that has already been incurred and which should not be considered in making a new investment decision.
APM :
Costs that are unavoidable, even if the remaining work is terminated.
Super-Critical Activity
AACEi :
An activity that is behind schedule is considered to be super-critical. It has been delayed to a point where its float is calculated to be a negative value.
Superior Knowledge
AACEi :
Syn.: Misrepresentation.
Supplementary Conditions
AACEi :
The part of the contract documents which amends or supplements the general conditions.
Supplier
AACEi :
A manufacturer, fabricator, distributor or vendor.
PCI :
An organisation or entity, either internal to a company or external to it, from which goods or services are required to complete a programme. Typically, suppliers are subcontractors or sub-tier contractors.
Surety
AACEi :
A bonding company licensed to conduct business which guarantees the owner that the contract will be completed (performance bond) and that subcontractors and suppliers will be paid (payment bond).
Surveillance
AACEi :
A term used in an earned value management system (e.g. EVMS or C/SCSC) to mean the monitoring of continued compliance with an approved/validated management control system.
Suspension Of Work, Constructive
AACEi :
An act or failure to act by the owner, or the owner's representative, which is not a directed suspension of work or work stoppage, but which has the effect of delaying, interrupting, or suspending all or a portion of the work.
Suspension Of Work, Directed
AACEi :
Actions resulting from an order of the owner to delay, interrupt, or suspend any or all portions of the work for a given period of time, for the convenience of the owner.
Sustainability
APM :
An environmental, social and economically integrated approach to development that meets present needs without compromising the environment for future generations.
Swot
AACEi :
Acronym for a qualitative risk identification and assessment technique that reviews strengths, weaknesses, opportunities and threats.
PMI :
Analysis of strengths, weaknesses, opportunities, and threats of an organization, project, or option.
System Concept Document
AACEi :
Syn.: Concept Definition Document.
Systems Dynamics
AACEi :
Methods for studying the behavior of complex systems with feedback loops (e.g., chains of cause and effect).
Systems Studies
AACEi :
The development and application of methods and techniques for analyzing and assessing programs, activities and projects to review and assess efforts to date and to determine future courses and directions. These studies include cost/benefit analysis, environmental impact analysis, assessment of the likelihood of technical success, forecasts of possible futures resulting from specific actions, and guidance for energy program planning and implementation.
System Surveillance
PCI :
Cross-program EVMS surveillance used to assess the capability to achieve the earned value guidelines. Note: System surveillance may be a summarisation of the programme's surveillance results rather than separate surveillance reviews.
Tactical Risk
AACEi :
Risk for which the potential impact does not significantly threaten an overall project objective or have a significant potential impact on enterprise, portfolio or other higher objectives or plans beyond the project level.
Tailor
PMI :
The act of carefully selecting process and related inputs and outputs contained within the PMBOK® Guide to determine a subset of specific processes that will be included within a project’s overall management approach.
Take-Off
AACEi :
A specific type of quantification that is a measurement and listing of quantities of materials from drawings in order to support the estimate costing process and/or to support the material procurement process.
Tangibles
AACEi :
Things that can be quantitatively measured or valued, such as items of cost and physical assets.
Target
AACEi :
A measurement set for performance. In a project management sense it typically refers to a project goal expressed in time or cost.
Target Date
AACEi :
Date imposed on an activity or project by the user or client that constrains or otherwise modifies the network analysis. There are two types: Target Start Dates, and Target Finish Dates.
Target Finish Date
AACEi :
A target date where the date imposed is on the finish date.
Target Plan
AACEi :
The target plan prioritized by critical total float taken from the current schedule.
Target Reporting
AACEi :
A method of reporting the current schedule against some established baseline schedule and the computations of variances between them.
Target Schedule
AACEi :
A schedule devised or selected as an objective measure against which actual performance can be gauged.
Target Start Date
AACEi :
A target date where the date imposed is on the start date.
Task
AACEi :
(1) A cohesive, individual unit of work that is part of the total work needed to accomplish a project.
(2) Well-defined component of project work; a discrete work item. There are usually multiple tasks for one activity.
Task Monitor
AACEi :
The individual assigned the monitoring responsibility for a major effort within the program.
Task Types
AACEi :
Characterization of task by resource requirement, responsibility, discipline, jurisdiction, function, etc.
Taxes Payable
AACEi :
Tax accruals due within a year.
Technical Performance Measurement
AACEi :
A general term referring to the technical plan measurements of the program/project. Examples include Software Engineering Institute (SEI) metrics, technical plans, and specifications. These may be used in earned value as the integration points with the schedule.
Technique
PMI :
A defined systematic procedure employed by a human resource to perform an activity to produce a product or result or deliver a service, and that may employ one or more tools.
Template
AACEi :
(1) A guideline for a document outline and its contents, used to record work activities, discussions, findings, and specifications to help achieve a common understanding. Care must be taken to ensure normal planning and schedule quality processes are not bypassed.
(2) A document whose required content is predetermined and format pre-structured to speed completion with accuracy and uniformity.
PMI :
A partially complete document in a predefined format that provides a defined structure for collecting, organizing, and presenting information and data.
Temporary Construction Cost
AACEi :
Includes costs of erecting, operating, and dismantling non-permanent facilities, such as offices, workshops, etc., and providing associated services such as utilities.
Termination
AACEi :
Actions by the owner, in accordance with contract clauses, to end, in whole or in part, the services of the contractor. Termination may be for the convenience of the owner or for default by the contractor.
APM :
The decommissioning and disposal of a deliverable at the end of its useful life.
Terms Of Payment
AACEi :
Defines a specific time schedule for payment of goods and services and usually forms the basis for any contract price adjustments on those contracts that are subject to escalation.
Theory Of Constraints (TOC)
AACEi :
A four-step management philosophy by Dr. Eli Goldratt involving: 1) Identifying the system's constraints; 2) Exploiting those constraints; 3) Subordinating other processes to the constraints; 4) Elevating the constraints. In project management, the key constraint is typically the critical path, and TOC is applied via critical chain scheduling.
Third Party Claim
AACEi :
In TCM risk management, an uncertainty that, if it occurs, will have an adverse impact on an objective or objectives. In some usage, risks are considered synonymous with threats.
APM :
A negative risk event that will have a detrimental effect on the objectives.
PMI :
A risk that would have a negative effect on one or more project objectives.
Three-Point Estimate
APM :
An estimate in which optimistic, most likely, and pessimistic values are given.
PMI :
A technique to estimate cost or duration by averaging optimistic, pessimistic, and most likely estimates when there is uncertainty with individual activity estimates.
Threshold
PMI :
A cost, time, quality, technical, or resource value used as a parameter. Crossing the threshold should trigger some action, such as generating an exception report.
Tied Activity
AACEi :
An activity that must start within a specified time or immediately after its predecessor's completion or start.
Time And Material Contract (T&M)
PMI :
A hybrid contract with aspects of both cost-reimbursable and fixed-price contracts. Unit rates may be preset, and total value may grow or be limited depending on agreement, making it a flexible arrangement.
Time Box
APM :
Control actions or reports that are triggered by the passage of a defined interval (e.g., monthly) and are referred to as ‘time-driven’.
Time Chainage
APM :
A form of graphical schedule that shows activity in relation to physical location as well as time.
Time Extension
AACEi :
An increase in contract time by modification or change order to complete an item of work. An excusable delay generally entitles a contractor to a time extension. Depending upon contract terms, the time extension may or may not be compensated.
Time Horizon
AACEi :
Synonym: Study Period.
Time Is Of The Essence
AACEi :
Contract requirement that completion of the work within the time limits in the contract is essential. Failure to do so is a breach for which the injured party is entitled to damages.
Time Line
AACEi :
Schedule line showing key dates and planned events.
Time Now
AACEi :
Current calendar date from which a network analysis, report, or update is being made.
Time Now Line
AACEi :
The point in time that the network analysis is based upon. May or may not be the data date.
Time Phasing
AACEi :
Strategic pacing of project and overlapping between different activities or blocks of activities. Examples include rapid application development prototyping, concurrent engineering, simultaneous design, fast track, and phased hand-over. Properly executed, phasing and overlapping can significantly improve performance.
Time Scheduling
APM :
A collection of techniques used to develop and present schedules that show when work will be performed.
Time Unit
AACEi :
A unit of measure used in a scheduling calendar when modeling an activity duration, usually expressed in hours, days, or weeks, but can also be shifts or minutes.
Time Value Of Money
AACEi :
(1) The time-dependent value of money stemming from changes in purchasing power and real earning potential of investments.
(2) The cumulative effect of elapsed time on the money value of an event, based on the earning power of invested funds.
(3) The expected interest rate that capital should or will earn.
Time-Constrained Scheduling
AACEi :
Network schedule calculations constrained by the time allowed to complete the project rather than available resources.
Time-Driven
APM :
Control actions or reports that are triggered by the passage of a defined interval (e.g., monthly).
Time-Limited Resource Scheduling
AACEi :
Production of scheduled dates in which resource constraints may be relaxed to avoid any delay in project completion.
Time-Limited Scheduling
AACEi :
Scheduling activities so predetermined resource pools are not exceeded unless further delay would delay the project. Activities can start at their late start date even if resource limits are exceeded.
Time-Scaled CPM
AACEi :
A plotted CPM network where activity lengths indicate duration. Float and dummy activities are usually shown with dashed lines.
Time-Scaled Logic/Network Drawing (Or Diagram)
AACEi :
A project network diagram drawn so the position of each activity represents its expected start and finish date. Essentially a Gantt chart with network logic depicted.
Time-Scaled Schedule Network Diagram
PMI :
A project schedule network diagram drawn so the position and length of each activity represents its duration. Essentially, a bar chart that includes schedule network logic.
To Complete Performance Index (TCPI)
AACEi :
A metric calculating the future efficiency needed to meet a target. Variations include:
1) Budgeted Base: (BAC - BCWP)/(BAC - ACWP), limited when EAC ≠ BAC.
2) EAC Base: (BAC - BCWP)/(EAC - ACWP), more commonly used, comparable with CPI.
PMI :
Measure of cost performance required with remaining resources to meet a management goal, expressed as ratio of cost to finish remaining work to remaining budget.
Tolerance
APM :
A permissible variation in performance parameters.
PMI :
The quantified description of acceptable variation for a quality requirement.
Tool
PMI :
Something tangible, such as a template or software program, used to perform an activity to produce a product or result.
Tornado Chart
AACEi :
In risk management, a graphical bar chart ranking key risk drivers in descending order of impact or severity.
PMI :
Tornado Diagram: A special bar chart used in sensitivity analysis to compare relative importance of variables.
Total Allocated Budget (TAB)
AACEi :
The total budget for the project. TAB = PMB + Management Reserve (MR). Without an over target baseline (OTB), TAB = Contract Budget Base (CBB).
Total Cost Bidding
AACEi :
A method to establish purchase price of movable equipment, guaranteeing maintenance limits and repurchase price.
Total Cost Management (TCM)
AACEi :
The effective application of professional and technical expertise to plan and control resources, costs, profitability, and risks throughout the life cycle of any enterprise, program, facility, project, product, or service. Achieved through cost engineering and management principles, proven methodologies, and technology.
Total Float (TF)
AACEi :
(1) Maximum number of work periods an activity can be delayed without delaying project completion.
(2) Delay allowed for activity start/finish without affecting project finish date. Float may be negative, zero, or positive.
(3) Amount of time a task can be delayed without delaying project finish.
APM :
Time by which an activity may be delayed without affecting overall duration.
PMI :
Amount of time a schedule activity can be delayed from its early start date without delaying project finish or violating a schedule constraint.
Total Quality Management (TQM)
AACEi :
The consistent, integrated orchestration of an organization's processes and activities to achieve continuous improvement in processes and products.
Traceability
AACEi :
In earned value, traceability consists of two required relationships in the schedule: horizontal and vertical traceability.
Traceability, Horizontal Traceability
AACEi :
A scheduling term indicating that tasks at lower levels are consistent with higher levels. All tasks at the lowest schedule level should align with higher-level schedule timeframes, typically ensured via relationships or integration milestones.
Tracking
AACEi :
A form of monitoring applied to project activities.
Tranche
APM :
A sub-division of the delivery phase of a programme, created to facilitate approval gates at suitable points in the life cycle.
Transfer
AACEi :
In TCM risk management, a risk response strategy that involves transferring a threat to a competent third party better able to manage it.
APM :
A response to a threat that reduces its probability, impact, or both by transferring the risk to a third party.
Transfer Price
AACEi :
A term used in economic analysis in the mineral processing industries to assign a value to raw materials when the same company handles both mining and processing. Usually equal to fair market value.
Tree Diagram
PMI :
A systematic diagram of a decomposition hierarchy used to visualize parent-to-child relationships in a structured set of rules.
Trend
AACEi :
In project control, a general tendency of events, conditions, or performance. In change management, a trend is the first indication of potential change and may later be identified as a deviation (usually not reimbursable) or a change (typically reimbursable). Synonym: Progress Trend.
Trend Analyses
AACEi :
Mathematical methods for studying trends based on past project history, allowing adjustments or predictions of cost and schedule. Regression analysis may be used for trend prediction.
PMI :
An analytical technique using mathematical models to forecast future outcomes based on historical results, determining variance from a baseline of budget, cost, schedule, or scope.
Trend Line
AACEi :
A line on a schedule or chart showing the pattern of progress over time, e.g., from one measurement period to the next.
Trend Monitoring
AACEi :
A system for tracking estimated cost, schedule, and resources versus planned values for a project.
Trend Reports
AACEi :
Indicators of variations in project control parameters compared to planned objectives or measures.
Trending
AACEi :
A review of current progress compared to last reported progress, often displayed graphically to determine if corrective actions are needed to achieve the baseline plan.
Trigger Condition
PMI :
An event or situation indicating that a risk is about to occur.
Turnover
AACEi :
Synonym: Delivery.
Turnover Ratio
AACEi :
The ratio of annual sales to investment. Including working capital is preferable. It is sometimes used to estimate facilities cost for new products. The product of turnover ratio and profit margin gives a return-on-investment measure. Typical values are around 1.0 for many chemical plants.
Unanimity
PMI :
Agreement by everyone in the group on a single course of action.
Unbalancing
AACEi :
A technique used in the pricing process to allocate estimated costs to accounts whose definitions do not fully reflect the nature of the cost being allocated. The purpose is to achieve a desired business result such as improved cash flow, for example by allocating more overhead costs to early project activities.
Uncertainty
AACEi :
(1) The total range of events that may happen and produce risks (including both threats and opportunities) affecting a project (Uncertainty = Threats + Opportunities).
(2) All events, both positive and negative, whose probabilities of occurrence are neither 0% nor 100%.
Underground Facilities
AACEi :
All pipelines, conduits, ducts, cables, wires, utility access-ways, vaults, tanks, tunnels, or other such facilities installed underground to furnish services such as electricity, gas, communications, water, sewage, or control systems.
Undistributed Budget (UB)
AACEi :
In earned value management, the amount of budget temporarily held before distribution to lower levels of the performance measurement baseline (PMB). UB is part of the PMB and is not scheduled but has scope, schedule, and budget integration.
PCI :
Budget applicable to contract effort not yet identified to specific cost accounts or work packages.
Union
AACEi :
An organization of wage earners formed to serve members’ interests regarding compensation and working conditions.
Unit Cost
AACEi :
The cost of a given unit of a product or service.
Unit Hours
AACEi :
Work hours per unit of production.
Unjust Enrichment Doctrine
AACEi :
The legal principle that one person should not be allowed to profit unfairly at the expense of another.
Unknown-Unknown
AACEi :
A quantity, value, or condition that cannot be identified or foreseen; unknowable.
Unlimited Schedule
AACEi :
An infinite schedule produced without resource constraints.
Unusually Adverse Weather Day
AACEi :
The number of adverse weather days impacting a project beyond what was originally planned, used to determine excusable time extensions.
Update
AACEi :
To revise an estimate, schedule, or other planning deliverable to reflect the most current project information.
Update Date
AACEi :
Synonyms: As-Of Date; Data Date.
Updating
AACEi :
The regular review, analysis, evaluation, and reporting of project progress, including recomputation of estimates or schedules.
Useful Life
AACEi :
The period over which an investment is considered to meet its original objective.
User
AACEi :
The consumer of a service or product, sometimes but not always the project owner.
PMI :
The group of people intended to receive benefits or operate outputs.
Validate Scope
PMI :
The process of formalizing acceptance of the completed project deliverables.
Validated Deliverables
PMI :
Deliverables that are the result of executing the quality control process to determine correctness.
Validation
AACEi :
Testing to confirm that a product or service satisfies user or stakeholder needs. Note the difference from verification.
PMI :
The assurance that a product, service, or system meets the needs of the customer and other identified stakeholders. Often involves acceptance and suitability with external customers.
Valuation Or Appraisal
AACEi :
The art of estimating the fair-exchange value of specific properties.
APM :
Value is defined as the ratio of satisfaction of requirements over use of resources.
Value Added By Distribution
AACEi :
The portion of product or service value resulting from distribution activities, including time and place utility.
Value Added By Marketing
AACEi :
The portion of value resulting from marketing activities, such as economies of scale and increased buyer awareness.
Value Effective
AACEi :
Describes decisions that optimize value received and maximize return on investment.
Value Engineering
AACEi :
A practice focused on achieving the lowest life-cycle cost or greatest value while meeting performance criteria.
APM :
Optimising conceptual, technical, and operational aspects of deliverables.
PMI :
An approach to optimize project life cycle costs, improve quality, save time, and use resources effectively.
Value Engineering Cost Avoidance
AACEi :
A decrease in the estimated overall cost for accomplishing a function.
Value Engineering Cost Reduction
AACEi :
A decrease in the committed or established overall cost for accomplishing a function.
Value Engineering Job Plan
AACEi :
A formal, step-by-step procedure used to identify and implement value engineering solutions.
Value For Money Ratio
APM :
The ratio of monetary and non-monetary benefits to the resources invested.
Value Management
APM :
A structured approach to defining and optimizing value to an organisation.
Value Of Perfect Information
AACEi :
A measure of what a decision maker should invest to reduce uncertainty in decision or risk drivers.
Value Of Work Performed To Date
AACEi :
The planned cost for completed work.
Value Tree
APM :
A graphical representation showing relationships between value-driving factors.
Variable Costs
AACEi :
Costs that vary with production output, such as raw materials, utilities, and variable labor.
Variance
AACEi :
The difference between expected and actual results.
PMI :
A technique for determining the cause and degree of deviation from baseline performance.
Variance Analysis
AACEi :
Analysis of cost, schedule, labor, material, and unit variances, including BCWP, ACWP, and BCWS comparisons.
PMI :
A technique for determining the cause and degree of difference between baseline and actual performance.
Variance At Completion (VAC)
AACEi :
The difference between budget or schedule at completion and the estimate at completion.
PMI :
The projected budget surplus or deficit at completion.
PCI :
The algebraic difference between Budget at Complete and Estimate at Complete.
Variance At Completion [VAC(T)]
AACEi :
The difference between baseline and estimated project duration.
Variance Threshold
AACEi :
The variance level at which formal variance analysis and reporting is required.
Variation
PMI :
An actual condition that differs from the baseline plan.
Variation In Estimated Quantity
AACEi :
The difference between estimated and actual quantities required, typically adjusted when exceeding 15 percent.
Velocity
PMI :
A measure of a team’s productivity rate used for forecasting future work.
Velocity Diagram
AACEi :
A graphical presentation of production schedules showing the relationship between work crew or equipment output and time.
Venture Life
AACEi :
The total time span during which expenditures or reimbursements related to a venture occur, including research and development, construction, production, and liquidation periods. Synonym: Financial Life.
Venture Worth
AACEi :
The present worth of cash flows above an acceptable minimum rate, discounted at the average rate of earnings.
Verification
AACEi :
Testing to confirm that a product or service meets specifications.
PMI :
The evaluation of whether a product, service, or system complies with requirements, specifications, regulations, or imposed conditions. Often an internal process.
Vertical Event Numbering
AACEi :
The assignment of event numbers in vertical order.
Voice Of Customer
PMI :
A planning technique used to translate customer requirements into appropriate technical requirements across project development phases.
Wage Rate
AACEi :
Synonym: Labor Cost.
Watch List
AACEi :
In risk control, a list of risk triggers and/or risks to be tracked or monitored; may refer to a usage of a risk register.
Waterfall Method
APM :
A type of life cycle where phases are sequential.
WBS Dictionary
AACEi :
A document describing each WBS element, including statement of work, work content, and basis of estimate. It may include responsible organization and contract references.
PMI :
A document providing detailed deliverable, activity, and scheduling information for each WBS component.
Weather Day
AACEi :
A work day stopped or significantly hindered due to a weather event.
Weather Event
AACEi :
A storm or significant weather condition that stops or appreciably hinders work, including rain, flooding, snow, ice, extreme temperatures, high winds, humidity, or preparatory actions for such events.
Weather Preparation Day
AACEi :
A day when work progress ceases or is significantly impeded while preparing for an upcoming weather event.
Weather Recovery Day
AACEi :
A day when work cannot resume due to after-effects of a weather event, including restoring conditions to pre-event status.
Weighted Milestone Method
PMI :
An earned value method dividing a work package into measurable segments, each ending with a weighted milestone.
Weights
AACEi :
Numerical modifiers used to infer the importance of commodities in an aggregative index.
What-If Scenario Analysis
PMI :
The process of evaluating scenarios to predict their effects on project objectives.
Work
AACEi :
All labor, materials, equipment, services, and obligations required to complete construction in accordance with contract documents.
Work Authorization
PMI :
Formal permission and direction to begin work on a specific activity, work package, or control account.
Work Authorization Document
PCI :
An internal contractor document defining authorized task work, deliverables, associated budget, and approving signatures.
Work Authorization System
PMI :
A subsystem defining how project work is formally authorized, tracked, and approved.
Work Breakdown Structure (WBS)
AACEi :
A hierarchical, product-oriented framework organizing and defining all project work.
PMI :
A hierarchical decomposition of the total scope of work into manageable components.
Work Breakdown Structure (WBS), Contract Work Breakdown Structure (CWBS)
AACEi :
A WBS defining products or services to be furnished under contract, derived from selected project WBS elements.
Work Breakdown Structure (WBS), Project Work Breakdown Structure (PWBS)
AACEi :
A summary WBS tailored by project management to the specific project.
Work Breakdown Structure Element
AACEi :
An individual item within the WBS hierarchy, at any level.
Work Breakdown Structure Levels
AACEi :
The hierarchical configuration of a WBS establishing indenture relationships.
Work Category
AACEi :
A division of work based on distinct characteristics such as trade or discipline.
Work Directive Change
AACEi :
A written directive ordering a change in work, typically incorporated later into a formal change order.
Work Flow
AACEi :
The relationship of activities from start to finish, considering all activity dependencies.
Work Item
AACEi :
(1) The precedence notation equivalent of an activity.
(2) A clearly identifiable portion of the project.
Work Package
AACEi :
A defined segment of work with assigned scope, schedule, and resources.
APM :
A group of related activities defined at the same WBS level.
PMI :
The lowest WBS level for which cost and duration can be estimated and managed.
Work Pattern
AACEi :
An established and recognizable flow of work.
Work Performance Data
PMI :
The raw observations and measurements identified during activities being performed to carry out the project work.
Work Performance Information
PMI :
The performance data collected from various controlling processes, analyzed in context and integrated based on relationships across areas.
Work Performance Report
PMI :
The physical or electronic representation of work performance information compiled in project documents, intended to generate decisions, actions, or awareness.
Work Power Leveling
AACEi :
Synonym: Load Leveling.
Work Sampling
AACEi :
A direct method of measuring and monitoring labor productivity to minimize wasted effort and optimize work processes through statistical assessment.
Work Site
AACEi :
The area designated in the contract where the facility is to be constructed.
Work Unit
AACEi :
A unit of time used to estimate the duration of activities.
Work-In-Process
AACEi :
(1) In manufacturing, product in various stages of completion throughout the factory.
(2) In projects, product or deliverables in various stages of completion.
Synonym: In-Progress Inventory.
Workaround
AACEi :
(1) An alternative, unplanned solution to a negative event.
(2) Ad hoc action to overcome unexpected conditions to avoid delays.
PMI :
A response to a threat that has occurred for which no effective prior response was planned.
Workday
AACEi :
Any day when work can be scheduled, excluding rest days and holidays.
Worker
AACEi :
A defined role describing the behavior and responsibilities of an individual carrying out project work.
Workhour
AACEi :
Synonym: Labor Hour.
Workhour Analysis
AACEi :
An analysis of planned versus actual staffing used to determine progress, productivity, and labor utilization.
Working Calendar
AACEi :
The total calendar dates covering all project activities from start to finish.
Workload Factor
AACEi :
The amount of work assigned or expected from a worker expressed as a multiplier of standard productivity.
Workweek
AACEi :
The calendar defining the number of workdays in a typical week.
Worth
AACEi :
The value of an item or facility determined by return on investment relative to the amount invested.
Written Amendment
AACEi :
A written modification to a contract addressing non-technical or non-engineering aspects.
Yield
AACEi :
The ratio of return or profit over the associated investment, expressed as a percentage or decimal, usually on an annual basis.
Zero Float
AACEi :
A condition where there is no excess time between activities. An activity with zero float is considered a critical activity. If the duration of any critical activity is increased (the activity slips), the project finish date will slip. An activity has zero float when the early and late start/finish dates equal each other. Activities with zero float are considered to be on the critical path(s) of the project even when there are activities with negative float.