Extended Days

  • Page:
  • 1

Extended Days

OFFLINE
Joined On:
30 Sep 2017

Extended Days

22 June 2010 9:24
In MS Project durations for activities which are not resource dependent (such as preheating a furnace) can be entered as e days(6e). How we do it in Suretrak or P3?
OFFLINE

Re: Extended Days

22 June 2010 9:29
by creating a 24-7 calendar and assigning it to the activity. That way activities that dont depend upon resourcing such as concrete curing, filling a reservoir with water, emptying a tank, drying out a newly insulated furnace etc. can be calculated using the correct duration.