Suretrack : a problem while updating schedule

  • Page:
  • 1

Suretrack : a problem while updating schedule

OFFLINE

Suretrack : a problem while updating schedule

22 June 2010 10:08
Im facing a problem doing the schedule update for a project. Im using SureTrak and when Im entering the % completion for an activity its changing the original durations of other activities. I made sure I havent check marked the " link remaining duration and percent completion" option but still. Its weird because Its happening in certain activities only. Im able to successfully update most of the activities w/o any change in original duration.
OFFLINE

Re: Suretrack : a problem while updating schedule

22 June 2010 10:10
Check if that activity is a resource driven type or might be having a hard constraint. This cases usually affect the original duration during an update.
  • Page:
  • 1