Reasons for Project Delays
1. Lack of Clarity in Scope of Works
2. Major discrepancies on project documents - Drawings, Specs, Contract Documents
3. Changes made midway on the Project by Client needing revised design during construction stage
4. Selection of the right consultant and selecting the key design staff on the project is a key requirement.
5. Selection of Contractors on basis of L-1 criteria rather than thru detailed rating systems considering other key parameters - past performance, quality of service, time completion, no. claim oriented, relationships with other contractor/subcontractor on works are attitude towards interface issues.
6. Manufacturer tight Delivery Schedules and previous commitments to other contracts, especially when you have specialized works - Polycrete pipes and manholes in middle east.
7. Project Financing Issues
8. Adverse Climatic Conditions- Cyclone Gonu and Phet affecting Omans projects.
9. Delays in authority approvals, getting permits during project commencement
10. Delays associated with Infrastructure works in heavy Congested Traffic Areas
11. During project operations delays in authority reviews, supply of substation transformers, and final inspections on Building projects.
-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------