Cost Loaded schedule !

  • Page:
  • 1

Cost Loaded schedule !

OFFLINE
Joined On:
30 Sep 2017

Cost Loaded schedule !

12 April 2010 7:15
Whats meant by a cost - loaded primavera schedule ?
OFFLINE
Joined On:
30 Sep 2017

Re: Cost Loaded schedule !

13 April 2010 2:21
Cost loaded schedules are ideal to get your cash-outflow however you never have enough & accurate info to support it . Theoretically, you can load cost (different types) to each activity in P6 in the similar fashion you load resources to it. This helps in analysing the cash expenditure over the period of time and thus help in preparing project cashflow. You can also update actual cost expended to each task to see the cost variance at activity level which comes very handy for analysing various cost trends and analysis on project.. Now enter the real world, we never have sufficient cost information at level 3/4 activities and hence building cost loaded schedules is not worth the efforts. I understand ERP Oracle financials has an integration facility with P6 which allows a direct feed of cost data to P6 however have never tried personally so cant comment on this. Hope this helps,
OFFLINE

Re: Cost Loaded schedule !

18 October 2010 1:35
adding to the above reply, i am using the integration facility between ERP Oracle financials and P6. but the drawback is, we cant load cost at activity level in ERP (it is always at WBS level) and after transferring the cost to P6, it goes to User defined field in P6 which cant be rolled up and hence will not solve the actual purpose cost loaded schedule. Regards
OFFLINE
Joined On:
30 Sep 2017

Re: Cost Loaded schedule !

2 December 2010 9:02
In the Middle east in all projects there is a requirement of getting a detailed cost loading exercise done by properly assigning he weighted distributed bill values to the individual CPM activities. The benefits that arise by doing this cost loading right and in details are: 1. Value of Work Done upto the reporting period is attained as soon as you get the progress update on the cpm per the agreed frequency of updates. 2. Cash Flow requirements needed for the forth comming months for the Client for necessary arrangements 3. What if analysis : As Contractor, if you want to target say 2 Million USD instead of 1.5 Million USD from the expected Spread Forecast, you can conduct a what if analysis by getting portion of work sections planned for forthcomming months for which you get the necessary additional resource requirements also from the loaded resource histogram spreads 4. As a Contractor it is important to compare - How much was supposed to be done (Planned Value) to How much has been done (Earned Value) to get the Schedule Variance and then further as contractor getting the job done in itself is not enough, to get it done at a profit (how much has been spent to get the earned value- Actual Cost) is more important, Cost Variance  calculation followed by the Forecasts on Estimate to Complete, Estimate at Completion, and Expected Variance at Completion can all be possible only following a detailed comprehensive cost loading exercise. It helps to get the Cost Loading exercise to be done with due care and in good detail. Further while making progress updates one aspect mostly overlooked is getting a redundancy check done on the relationships so that the forecasts depict the true works forthcomming in remaining time spread. The Lookahead need be as true as possible for the forecast estimates on remaining work, resource and earning forecast to make real sense and the forecast spread analysis be done properly.
  • Page:
  • 1