Some of the above industrial projects may have from 2000 to 5000 drawings depending upon the type. P&IDs
almost always have multiple issues, i.e. Heat & Material balance, Unit Operations Equipment,
Hydraulics, Control etc. They typically pass from Process engineering to Instrument engineering and to piping or plant design.
I have seen P&IDs with 4 to 8 different issues for different purposes. The same applies to electrical single lines, as they pass back and forth between electrical design, protection, or instrumentation and control, equipment sizing, wire diagrams, loop function diagrams etc.
Architectural drawings also have multiple disciplines back and forth passes beyond the 20% conceptual, 80% design.
Other issues to consider are drawings that issue to procurement, receipt of prelim vendor drawings for review, issued for correction, issued for design, issued for review of final design, issued for fabrication, final drawings issued for construction.
I typically do not include all of the above Level 4 Detail in a schedule. I prefer getting all of the disciplines together to agree on types, numbers, back and forth passes, and then use this information to create a drawing schedule or index (in excel format) that records where the drawings are currently, along with the next steps. I weight or allocate hrs to each drawing and then spread the values among the steps.
Finally, all drawings must pass through document control, and document control cannot be owned or managed by engineering. As the drawings are received, the doc control tabulates hrs or weight earned. The total tally becomes one type of basis for reporting engineering progress by discipline.
How you manage this process can have a significant impact of design time and cost.