As long as your schedule is logically driven, activities can become critical & non critical depends upon the progress you make. Once you schedule (F9 in P3/6) the job after updates, it will recalculate the critical path (CP) and your TF (total float) for each task would/may change. Hope this helps, however feel free for any further query.
Regards,