Importing Activities

OFFLINE

Importing Activities

2 March 2012 10:44
I am a Mechanical Specialty subcontractor attempting to imnport my activities into the GCs existing schedule.  For example, for Level-1 Rough-In MEP which is the GCs activitiy, I have activities A-Z that need to be successors of the Rough-IN activity.  I have multiple floors of the building that are similar, so I am hoping I can export to excel, and copy and past the data to the next floor while changing the activity codes and then import back to P6.  At this point, when I import back to P6, it puts the new activities into the first floor intead of the second floor.  Please Help I have 10k more activities to add!