Is the contract programme part of the contract documents??

  • Page:
  • 1

Is the contract programme part of the contract documents??

OFFLINE
Joined On:
30 Sep 2017

Is the contract programme part of the contract documents??

24 March 2010 1:02
There may be a simple answer to this but it may not be as simple as it sounds. Can you inforce a programme either to the client or subcontractor a programme, design by you, onto other parties??
OFFLINE

Re: Is the contract programme part of the contract documents??

24 March 2010 1:05
Ideally, contract program must be a part of contract document atleast at level I/II. There has to be contract schedule with milestone clearly identified. On enforcing the dates, it all depends on the circumstances and related contract clauses.
OFFLINE
Joined On:
30 Sep 2017

Re: Is the contract programme part of the contract documents??

24 March 2010 1:07
good point. so it is not the programme (schedule) that is in the documents it is milestone dates that are in the documents. At the end of the day the client is interested in the completion of milestones, for possible plant installation by others. What Im getting at is the client cannot hold you to the schedule just the milstone dates. I have been looking at some old EOT case files and the judge is not interested in the schedule just the required dates. I would be interested in your opinion???
OFFLINE
Joined On:
30 Sep 2017

Re: Is the contract programme part of the contract documents??

24 March 2010 1:09
The Level I or milestone summary schedule (MSS) is usually a part of contract. MSS includes both intermediate & completion milestones along with access dates between various contractors. Detailed schedules generally are not a part of contract as it’s a dynamic document. For ex., you may plan with certain philosophy and when it comes to implementation you choose other, but whats important is you stick to agreed dates. For EOT claims, importance of detailed schedules cant be ignored. Its important to analysis the critical path to identify the ownership of delays and for the same both the planned Level II/III and current schedule comes handy. For instance although dates as per contract schedule could not be met however there could be a critical task which was kept on hold for which contractor may not be responsible instead the other party was culprit. I think its not possible to define every level II/III critical interrelated-task in contract document and that’s where the schedules has a greater role & cant be ignored. In the nutshell, when it comes to EOT claims leading to arbitration it all comes down to the way contract has been formed. Having said that, with right backup of historical data (schedules, meeting notes etc.), argument can be made to justify your case. Hope this helps,