Basis of Schedule Memoradum

  • Page:
  • 1

Basis of Schedule Memoradum

OFFLINE
Joined On:
30 Sep 2017

Basis of Schedule Memoradum

31 October 2012 8:12
I am working on a proposal and part of the proposal was to turn in a Basis of Schedule Memorandum. Ive been in this business for 19 years and have never had to do one of those. Are there any examples of past projects or templates out there that i could use as a go by?
OFFLINE

Re: Basis of Schedule Memoradum

2 November 2012 5:12
Hi there,I think it means the Schedule basis and assumptions document which list all the assumptions made to build the schedule. It also lists the client issued specific milestones and constraints identified on contract document. I doubt anyone would be able to provide this document as most of the ocassions it is company confidential. If you wish external company to do this for you, i can recommend one.