When I create a copy of my current schedule in P6 and save it as target schedule, next week, when I update the schedule and compare their finish dates with last week, the activities that have started, show different finish dates and different variances than what I should expect.
My column titles are Start, Finish, BL1 Start, BL1 Finish, Variance BL1 Finish.
Any suggestions??