Here is some excerpte from paper titled "Risk Review of Recovery Schedules" presented recently in Toronto :
"Under standard CPM scheduling practice, the baseline schedule remains in effect until there are substantial changes to the plan that affect the critical path (i.e., delays). When the project experiences delay, the contractor is typically required to prepare a Recovery Schedule that demonstrates how the lost time will be recovered. As such, recovery schedules are often used when the assessment of liquidated damages is a risk issue. Typically, a revised baseline schedule is necessary when:
• The critical path changes as a result of major delays and/or scope changes,
• Delays have consumed the total float on non-critical activities and pushed them into the critical path,
• The project schedule does not accurately reflect the actual planned execution, project scope or progress of the work, or
• The project is performing major out of sequence work.
The Association for the Advancement of Cost Engineering International defines the Recovery Schedule as “A special schedule showing special efforts to recover time lost compared to the master schedule. Often a contract requirement when the projected finish date is no longer showing timely completion. (6/07)” [1].
While the construction industry is more often including recovery schedule requirements in contracts, these contracts contain a variety of conditions under which a recovery schedule is required. The following examples illustrate the varying contract conditions that define the need for a recovery schedule:
• If the project falls behind schedule more than 14 days or 10% of the remaining duration, whichever is less, for non-excusable delays;
• In the event that the Progress Schedule Update indicates that the Project, or progress towards any interim milestone, falls 20 or more work days behind schedule;
• When requested by the Owner or Engineer;
• When the owner determines that the contractor is behind any mandatory specific milestone or completion dates or any interim milestone completion date;
• When the contractor determines that the progress schedule requires revision for any reason; and,
• When departure from the existing schedule makes it apparent that the project will be late.
In addition to the “triggers” for determining the need for a recovery schedule, there are other considerations with respect to developing a recovery schedule. First, the need for a recovery schedule should consider any excusable delays or changes and all time extensions to which the Contractor is entitled. Second, the timing for submittal of the recovery schedule can also be specified. For example, some contracts require that a recovery schedule shall be submitted 14 calendar days after the monthly progress schedule update was submitted. Further, some contracts allow for the Owner to withhold progress payments until the Contractor submits a revised recovery schedule, acceptable to the Owner. When specific contract language exists, but the Contractor fails to produce an acceptable recovery schedule, there may be breach of contract issue. The refusal, failure, or neglect to take appropriate recovery action or to submit a recovery schedule could constitute evidence that the Contractor was not diligently prosecuting the work and could be considered grounds for termination. Finally, the Owner is typically entitled to direct the Contractor to prepare the recovery schedule at no extra cost to the Owner."
I hope this helps.