What does "Effort driven" option do?

Wednesday, 22 June 2016
Hits: 2498

What does “Effort driven” option do?

1

You may wonder what does “Effort driven” option in Task Detail Form do?

1

Here I have 2 tasks.

Task A doesn’t have Effort driven check. When I assign 2 resources to it, the Work unit for each resource doesn’t change (80h for each resource). No matter how many resource I assign, each resource will get 80h.

2

Now, Task B have Effort driven check. When I assign resource to it, the Work unit for each resource change (with 2 resource assign it will get 40h for each resource). And activity duration reduce to 5 days. The more resource you assign, the less unit each resource will get.

3

SUMMARY

So, when you have kind of activity which can be reduced duration by adding more resource, use “Effort driven” option.