This is a place for Registered Users to share their technical view and opinions in form of blogs which they think might be useful to the greater PCO community. We invite prolific writers to share their insights and witticisms, but remind all contributors to be mindful of any copyright rules. ProjectControlsOnline will not be held responsible for any breach in rights and responsible users will be held accounted for the same.

How does "Resource curve" work?

Jun 22
How does “Resource curve” work?   Let say we have an activity with 100 days duration and 100 labor units. By default it use Linear spread. It mean, when you reach 5% of duration (5th day in this example) you have 5% of total unit (5 unit in this exam..
Hits: 3515

What does "Effort driven" option do?

Jun 22
What does “Effort driven” option do? You may wonder what does “Effort driven” option in Task Detail Form do? Here I have 2 tasks. Task A doesn’t have Effort driven check. When I assign 2 resources to it, the Work unit for each resour..
Hits: 2702

Create critical path for "any activity"

Jun 22
Create critical path for “any activity” In Primavera when we use the default “Critical” filter, it will show the critical path for the whole project (for the last activity). How about if we want to show critical path for an activity which is som..
Hits: 5320

Can not filter on Start or Finish date

Jun 21
Can not filter on Start or Finish date You have a very simple project. You want to show only activity which finish on 25-Jan-16. As usual, you create an filter like this: Then… SURPRISE. It’s a blank screen. A big “WHY” quest..
Hits: 2276

Remove relationship for multiple activities

Jun 21
Remove relationship for multiple activities You have a group of activities which need to be removed all relationship Instead of going to each activity and click the Remove button, you can select all activity -> right click ->  Assign -> Click on either Pr..
Hits: 3384

Does it matter calculating the total float from the start dates or finish dates in P6?

Jun 21
Does it matter calculating the total float from the start dates or finish dates in P6? We were taught that the total float is the amount of time that the activity can be delayed without affecting the overall project duration. And the calculation of the total float is the difference ..
Hits: 4597

Open Microsoft Project file and a blank screen appear

Jun 21
Open Microsoft Project file and a blank screen appear When you work with Microsoft Project 2010 in 2 monitor, you finish working, save the file and then next day you open a project file and a blank screen appear like this: What the he**, where is my project? At first I..
Hits: 4812

Can not import Layout

Jun 21
Can not import Layout Your colleague send you Primavera XER file and Layout file. After you import project successfully, you click on Layout -> Open -> Import -> Select the layout. And this error appear: You may think “Wow, this layout file must be damaged. I n..
Hits: 2689

How to backup and restore Primavera P6 SQL database

Jun 21
How to backup: Go to Start -> SQL Server Management Studio Enter Login information. The default username is “sa” and password is “Prima123Vera” Select the database, right-click, go to Task -> Back Up Click on “Add” button ..
Hits: 9581

How to backup and restore Primavera P6 Oracle Express (XE) database

Jun 21
How to backup: From the command prompt (go to ‘Start’ > ‘Run’ > type ‘cmd’ and click ‘OK’) using the format below exp system/<password>@XE full=y file=<path>\xedump.dmp log=<path>\exp_xedump.log Where: <pa..
Hits: 6373