Blogs

Welcome to PCO Blogs

This is a place for Registered Users to share their technical view and opinions in form of blogs which they think might be useful to the greater PCO community. We invite prolific writers to share their insights and witticisms, but remind all contributors to be mindful of any copyright rules. ProjectControlsOnline will not be held responsible for any breach in rights and responsible users will be held accounted for the same.

Schedule up-dating

Nov 13
Contracts specify how a contractor’s entitlement to an extension of the project completion date due an event attributable to Company shall be determined: The completion date is extended by the impact of the event, as demonstrated by the schedule logic, on the completion date. There will th..
Hits: 2112

The Engineering Workflow in a nutshell - Exercise

Nov 13
This is the synoptic showing the sequence of Engineering tasks... with some blanks for you to fill ! Make yourself a print at: https://docs.google.com/open?id=1NCljb-7ytKCDZkwooXm3JXPxyGj7r6XzsUIvNR2dFgml8FPGlWM0hFjm7nLf Herebelow is the link to the solution... don't look at it befor..
Hits: 1772

Understanding the Project Controls Model

Aug 01
Understating the subject of Project Controls model – Definition- The traditional view of Project Controls as seen widely has been cost & schedule during the project execution phase. Although this view is persuasive in industry, I believe an effective Project Controls process can ..
Hits: 6882

Capital Cost Optimization On Gas Fired Power Projects Through Standardization

Jan 26
A: Introduction The cost of power supplied to the end consumer comprises of components like cost of setting up the plant, operational cost, cost of transmission and cost of distribution. If the cost of power supplied to a consumer were to be reduced, the cost associated with each component would..
Hits: 1776

Best Practices for Schedule development

Jan 26
Schedule should reflect the workflow. There shouldn’t be conflicts between concurrent activities. Realistic resource loading should be done to support the planned construction operation. Make sure that subcontractors and suppliers meet the planned construction schedule. ..
Hits: 2012

Project Controls Audit Checklist

Jan 26
Base Project Estimate Project Execution Plan Project master Schedule (L2/L3/L4) : Baseline & Current Change/Variation log/Register Risk Register Project Reports : Monthly Project Reports, 4 week look ahead reports/schedules, Cost (Management) Reports, etc. Cas..
Hits: 5149

Project Controls Documents from Estimating : Handover Checklist

Jan 26
Detailed breakdown of all quantities, rates and cost with relevant backup i.e., vendor or subcontractor bids where applicable Scope definition (i.e., ITB as amended by the bid plus agreed amendments/exceptions) Narrative describing the basis of Estimate Manhours Q&D reports inc..
Hits: 3383

Tank fabrication steps & Activities

Jan 26
Tank fabrication steps are mainly, Shop Activities Plate layout and marking Cutting, edge preperation Rolling/bending Inspection, NDT (incase of longitudinal welds) Fabrication of Nozzles/manways/ladder/stairs/platform etc; Blasting and Priming Site ..
Hits: 9527

Application of Critical Chain on High Valuse Petrochem projects

Jan 27
1. INTRODUCTION Contracts are in various forms, usually Lump Sum Turn Key, but can also be reimbursable for and on behalf of the client and various hybrids between the two. The Critical Chain (CC) approach has been successfully applied various projects with a high degree of success. Here we disc..
Hits: 1700

Difference between planner & Scheduler

Aug 12
Yes there is a difference – a BIG difference – and yet, it could be argued that they are one in the same, however I won’t argue that point here because I want to stress the differences first, and then the similarities between the two disciplines. But first you need to understand th..
Hits: 12213

Trending #Tags

Search Blogs

Archived Posts